Limited-Time Offer: Enjoy 50% Savings! Ends in 00h 00m 00s Coupon code: 50OFF
Skip to content

Free APM Project Fundamentals Qualification APM-PFQ Exam Questions

Page: 1 / 28 Total 409 questions

Want more questions? Get Premium Access.

Question 1

Where in the project life cycle would the project manager typically be appointed?

Correct Answer: B. At the start of the definition phase.

Question 2

Scope management in an iterative life cycle would ensure that:

Correct Answer: A. the must have' requirements are given the top priority for delivery.

Question 3

Which of the following is a definition of project management?

Correct Answer: C. The application of processes, methods, knowledge, skills and experience to achieve specific objectives for change.

Question 4

A review most closely linked to the phases Of the project life cycle could be described as a:

Correct Answer: A. gate review.

Question 5

The risk management process is concerned with managing which of the following?

Correct Answer: A. Threats and opportunities.

Question 6

Critical path analysis places emphasis upon:

Correct Answer: D. activities

Question 7

What is the prime advantage of using a parametric estimating method?

Correct Answer: A. Accuracy,

Question 8

Which one of the following best describes

Correct Answer: A, A

Question 9

Quality control consists of:

1) improvement

2) inspection

3) measurement

4) testing

Correct Answer: B. 2, 3 and 4

Question 10

Which one is a true statement relating to project communications?

Correct Answer: B. Different stakeholders typically have different communication needs.

Question 11

What aspect of the project will have greatest influence on the estimating method being used?

Correct Answer: A. The point in the life cycle where the estimate is being carried out.

Question 12

Which one of the following best describes the purpose of a project's business case?

Correct Answer: D. Provides justification for undertaking the project, in terms of evaluating the benefits, cost and risks

Question 13

Establishing success criteria is important at the start of the project, as they:

Correct Answer: A. indicate how the stakeholder needs will be met.

Question 14

Which of the following would be considered as the main purpose of a project management plan?

Correct Answer: B. To enable agreement between the project sponsor and project manager with regard to project budget, resource requirements and timescale.

Question 15

Which of the following is not a key aspect of issue resolution?

Correct Answer: A. Increase risk budget.