Limited-Time Offer: Enjoy 50% Savings! Coupon code: 50OFF Use it at checkout
Skip to content

Free ASTQB ISTQB Foundation Level CTFL Exam Questions

Last updated: · 14 practice questions with answers and explanations

Page: 1 / 15 Total 219 questions

Want more questions? Get Premium Access.

Question 1

New Single answer

Topic: 1 Learning Objectives for Fundamentals of Testing

Skill tested: Distinguishes an error, a defect, a failure, and a defect's root cause.

A team investigates an outage in an online booking system. A developer misunderstood a requirement that stated bookings close at midnight local time and instead coded a UTC cutoff. This mistake introduced a defect. On the first day after a daylight-saving change, customers in one region could not submit valid bookings, producing a visible failure. The investigation also finds that the requirement had never been reviewed with regional business representatives. Which statement best distinguishes the root cause from the failure in this scenario?

Correct Answer: B. The root cause is the developer's misunderstanding; the failure is the inability of customers to submit valid bookings.
Explanation:

The developer's misunderstanding is the human action that led to the defect, so it is the root cause. The defect is the incorrect cutoff logic in the software. Its observable effect during operation - the rejected valid bookings - is a failure. The missing stakeholder review is a process condition that may have contributed to the misunderstanding, but it is not the failure. The daylight-saving change exposed the problem; it did not itself constitute the software failure.

Question 2

New Single answer

Topic: 2 Testing Throughout the Software Development Lifecycle

Skill tested: Selects confirmation or regression testing based on the change and its risk.

A payment service team fixes a defect that incorrectly rejects cards issued in a particular country. The release is time-critical, and the team has limited capacity for pre-release testing. It must establish that the fix works and gain evidence about unintended effects on existing payment behavior. Which testing approach most directly addresses both needs?

Correct Answer: A. Run confirmation testing for the reported defect and risk-based regression tests for affected existing behavior.
Explanation:

Confirmation testing checks that the specific defect has been corrected; the original failing scenario, or an appropriately updated equivalent, should now pass. Regression testing looks for unintended consequences of the change in areas that previously worked, with selection guided by risk and likely impact. Repeating one test alone cannot establish that side effects are absent. Regression testing is not limited to changed code, and static review can complement but cannot replace execution-based confirmation of runtime behavior.

Question 3

New Single answer

Topic: 3 Static Testing

Skill tested: Applies review-process activities and review roles to a requirements inspection.

A safety-critical project is reviewing a requirements specification before implementation. The organization requires a formal review with documented findings and follow-up, but wants to avoid turning the meeting into an editing session. The author has distributed the document, and reviewers have completed individual preparation using a checklist. Which next step best follows a structured inspection process?

Correct Answer: C. Have the moderator lead a review meeting in which the reader paraphrases the work product, a recorder logs identified anomalies, and the team focuses on defect detection.
Explanation:

After planning and individual review, a formal inspection typically conducts a review meeting focused on identifying defects, with roles such as moderator, reader, recorder, and author. The recorder captures findings; the meeting is not primarily a forum for solving every issue or editing the document. Revision and follow-up occur after the meeting, and the work product is assessed against exit criteria. Immediate unrecorded edits, management approval without resolution, or competing rewrites do not provide the required traceable inspection process.

Question 4

New Single answer

Topic: 4 Test Techniques

Skill tested: Derives boundary-value test cases for an inclusive numeric input range.

An insurance portal accepts an applicant's age as a whole number from 18 through 65 inclusive. Values outside this range must be rejected. A tester is applying two-value boundary value analysis to the valid-age interval and can execute only a small number of tests. Which set best covers both boundaries using this technique?

Correct Answer: D. 17, 18, 65, and 66
Explanation:

For an inclusive valid interval from 18 to 65, the two-value boundary set includes each boundary value and its nearest outside neighbor: 17 and 18 at the lower boundary, and 65 and 66 at the upper boundary. These tests check the transition between invalid and valid input at both ends. Values well inside the range, as in B, do not test the boundary transitions. C uses values farther from the boundary, while D omits the actual boundary values 18 and 65.

Question 5

New Multiple answers

Topic: 4 Test Techniques

Skill tested: Uses decision-table conditions to identify rule coverage and missing combinations.

A shipment is eligible for a discount only when the customer is a member and the order total is at least $100. A special promotion overrides that rule: any order with the promotion code receives the discount, whether or not the customer is a member or reaches $100. The team wants a compact decision table with distinct rules and tests that demonstrate each rule's outcome. Which three test scenarios represent the three distinct discount rules? Select THREE answers.

Correct Answer: B. Non-member, total at least $100, no promotion code: discount does not apply.; D. Non-member, total below $100, valid promotion code: discount applies.; E. Member, total at least $100, no promotion code: discount applies.
Explanation:

Without a promotion code, the ordinary rule requires both membership and a total of at least $100. A demonstrates that rule granting the discount; C demonstrates that a high total alone is insufficient for a non-member. D demonstrates the separate promotion override, which grants the discount regardless of membership or amount. B contradicts the ordinary rule, and E contradicts the stated override because a valid promotion code must grant the discount.

Question 6

New Single answer

Topic: 4 Test Techniques

Skill tested: Calculates statement and decision coverage from execution paths through conditional code.

A developer provides this pseudocode for review: `if balance >= amount then approve; record_approval; else reject;`. The test team executes one test with `balance = 80` and `amount = 50`, followed by one test with `balance = 20` and `amount = 50`. Assume each executable statement is counted once, and the decision has two outcomes. What coverage has this test set achieved?

Correct Answer: A. 100% statement coverage and 100% decision coverage.
Explanation:

The first test takes the true branch, executing `approve` and `record_approval`; the second takes the false branch, executing `reject`. Together, the tests execute every executable statement and exercise both outcomes of the decision, yielding 100% statement and decision coverage. A single branch test would not execute all statements or both outcomes. This coverage result does not prove the code is defect-free or that every possible input combination has been tested.

Question 7

New Single answer

Topic: 5 Test Management

Skill tested: Schedules test execution using priority and technical dependency constraints.

A release team has four tests ready, but its test environment supports only one execution at a time. Test T1 validates an authentication library and is a prerequisite for T2, which validates account recovery. T3 tests a low-risk report export and has no dependencies. T4 tests a critical payment authorization change and has no dependencies. Business risk ranks T4 highest, then T2, then T1, then T3; however, T2 cannot run until T1 has passed. Which execution order best respects both risk priority and the prerequisite?

Correct Answer: A. T4, T1, T2, T3
Explanation:

T4 has the highest business risk and no dependency, so it can be run first to provide early information about the most critical change. T2 has higher risk than T1 but cannot execute until its prerequisite T1 has passed; therefore T1 must precede T2. T3 is low risk and independent, so placing it last is reasonable. C violates the dependency, while A delays the highest-risk test unnecessarily and D spends early execution capacity on the lowest-priority test.

Question 8

New Multiple answers

Topic: 5 Test Management

Skill tested: Distinguishes test manager responsibilities from tester responsibilities in planning and control.

A software organization is establishing responsibility for a cross-team test effort. The test manager must coordinate planning and communicate progress, while testers remain responsible for the technical execution and analysis of assigned tests. Management wants clear accountability without concentrating every test activity in one role. Which THREE assignments are appropriate? Select THREE answers.

Correct Answer: B. Testers report test progress and defects using agreed procedures and supporting information.; D. The test manager defines the test approach and coordinates the test plan with relevant stakeholders.; E. Testers analyze test basis and test objects to identify, design, and implement test cases.
Explanation:

The test manager typically leads or coordinates test planning, monitors progress, and communicates with stakeholders. Testers perform technical work such as analyzing the test basis, designing and implementing tests, executing them, and reporting defects and progress. The manager need not personally execute all tests or diagnose every failure; doing so would undermine effective delegation. A tester or test manager can raise requirement issues, but changing product requirements is a product and stakeholder decision, not a unilateral test-management responsibility.

Question 9

New Multiple answers

Topic: 5 Test Management

Skill tested: Selects test metrics that support monitoring, control, and evidence-based reporting.

During a release, the test lead must report whether execution is progressing, whether the product is becoming more stable, and whether important coverage gaps remain. The report must support decisions rather than imply that one number proves quality. Which THREE measures are suitable inputs to this monitoring and control? Select THREE answers.

Correct Answer: A. The number of tests executed, passed, failed, and blocked compared with the plan.; B. Requirements-to-test traceability and coverage status for important requirements.; D. The number and severity of open defects, together with trends in defect status.
Explanation:

Execution progress against the plan, defect status and severity, and coverage or traceability information provide complementary evidence for monitoring and control. They help identify delays, quality risks, and untested requirements. Lines of test code are not a dependable direct measure of product quality. A pass percentage can be informative in context, but it cannot prove the absence of significant defects and may conceal blocked tests, weak coverage, or high-risk unresolved defects.

Question 10

New Single answer

Topic: 6 Tool Support for Testing?

Skill tested: Evaluates tool pilot objectives and organizational success factors before wider deployment.

A company is considering an automated test execution tool for several product teams. A vendor demonstration looked promising, but the teams use different build pipelines, and the organization has limited staff for tool administration and training. Leadership wants evidence of suitability before committing to broad adoption. What is the most appropriate next step?

Correct Answer: B. Run a bounded pilot with representative users and tests, evaluating integration, benefits, risks, training needs, and ongoing support effort against agreed criteria.
Explanation:

A pilot should establish whether the tool fits the organization's technical environment and working practices, while exposing practical issues such as integration, training, support, and maintenance. Agreed evaluation criteria make the result useful for an informed adoption decision. Buying organization-wide licenses before assessing suitability creates cost and deployment risk. Feature count alone does not establish value, and automating an entire suite without evaluating maintainability can obscure whether the tool is sustainable.

Question 11

New Single answer

Topic: 1 Learning Objectives for Fundamentals of Testing

Skill tested: Explains how testing contributes to quality assurance without equating testing with quality.

A product owner argues that a project can eliminate testing because the development team follows a documented coding standard and conducts peer reviews. The project must still provide evidence that the delivered service meets its key user requirements and behaves acceptably in realistic operating conditions. Which response best describes the relationship between testing and quality assurance?

Correct Answer: C. Testing contributes to quality by providing information about product quality and exposing defects, while quality assurance also includes process-oriented activities such as standards and reviews.
Explanation:

Testing is a product-oriented activity that evaluates work products and provides information about quality; it can reveal defects and reduce risk, but it cannot prove that no defects remain. Quality assurance is broader and process-oriented, aiming to provide confidence that appropriate processes are established and followed. Coding standards and peer reviews contribute to quality assurance and static testing, but they do not establish how the service behaves during execution. QA is not a final certification step that follows testing.

Question 12

New Single answer

Topic: 2 Testing Throughout the Software Development Lifecycle

Skill tested: Matches integration and system test levels to their objectives and test bases.

A logistics provider is delivering a new route-planning service. Individual modules have passed their component tests, but the team is concerned about both data exchange between the route engine and mapping adapter and whether the complete service meets the agreed operational requirements. The release schedule allows separate testing activities, and failures must be localized efficiently. Which approach best addresses these objectives?

Correct Answer: C. Perform integration testing on interactions between the route engine and adapter, then system testing of the complete service against its requirements.
Explanation:

Integration testing focuses on interfaces and interactions among integrated components or systems, so it is well suited to finding data-exchange defects between the route engine and mapping adapter. System testing evaluates the complete integrated system against its specified requirements, including broader behavior. Separating these levels supports clearer objectives and can make failures easier to localize. Component testing does not exercise the interaction, while acceptance testing is not the appropriate substitute for focused integration and system testing.

Question 13

New Multiple answers

Topic: 3 Static Testing

Skill tested: Identifies work products suitable for static testing and distinguishes static from dynamic evidence.

Before a regulated product enters implementation, its team wants to find defects early without executing the software. The work products include requirements, an architecture diagram, and source code for a completed component. Reviewers can use defined checklists and language-analysis tools, but they cannot yet run an integrated build. Which THREE statements accurately describe this work? Select THREE answers.

Correct Answer: B. Source code can be analyzed statically for issues such as violations of coding rules without executing it.; D. Requirements and architecture diagrams can be examined using reviews even though they are not executable.; E. Static testing can reveal certain defects early, but it cannot demonstrate runtime behavior for the unexecuted system.
Explanation:

Static testing examines work products without executing the software. Reviews can assess non-executable artifacts such as requirements and architecture diagrams, while static analysis tools can inspect source code for detectable defects or rule violations. This can find issues early and reduce later rework, but it does not provide evidence of runtime behavior or integration behavior. Discussion during a review does not make it dynamic testing; dynamic testing requires execution of the test object.

Question 14

New Single answer

Topic: 4 Test Techniques

Skill tested: Uses state-transition testing to identify valid and invalid behavior across workflow states.

A device-management application allows an administrator to change a device from `Registered` to `Active` after successful verification. From `Active`, an administrator may suspend the device, producing state `Suspended`; only a suspended device may be reactivated. A request to activate a suspended device is invalid, and invalid transitions must leave the state unchanged. The team needs a test that checks both a valid transition and rejection of an invalid transition. Which sequence is most appropriate?

Correct Answer: C. Register, verify, activate, suspend, attempt activate; confirm the final state remains Suspended.
Explanation:

The sequence in A follows valid transitions from Registered to Active and then to Suspended, before attempting the explicitly invalid activation from Suspended. The expected result is that the invalid request is rejected and the state remains Suspended. B attempts a transition that is not defined from Registered. C does not exercise the stated suspended-device reactivation rule. D attempts to suspend a Registered device, so it does not establish the required valid path or the invalid-transition behavior.