Question 1
Topic: CONCEPT PLANNING & ANALYSIS
Skill tested: Evaluates site feasibility using utility capacity, growth forecasts, and availability objectives.
A financial-services firm is comparing two sites for a new data center. Its forecast shows IT load increasing from 1.2 MW to 2.0 MW within five years, and the business requires maintainable critical infrastructure without planned IT outages during routine component maintenance. Site North has abundant land but only one utility substation feed; Site South has two independent utility feeds, limited expansion space, and higher land cost. Both sites have similar fiber access. The utility has not yet confirmed deliverable capacity or restoration times. Which next step should the consultant prioritize before recommending a site?
A feasibility recommendation must reconcile the forecasted load, maintainability objective, and actual site utility characteristics. The consultant should establish a phased electrical load basis and verify deliverable capacity, feed independence, restoration expectations, and feasible expansion at each site before comparing lifecycle cost and risk. Two feeds do not by themselves guarantee independence or a particular availability outcome. Generators do not eliminate the need to assess utility capacity and failure exposure. Deferring the analysis could make a site appear viable despite an unresolvable utility constraint.