Question 1

New Single answer

Topic: Project Assessment and Sustainability

Skill tested: Evaluates existing-conditions assessment and hazardous-material coordination before renovation design.

A design team is preparing a renovation of a 1970s office suite. The client wants to begin selective demolition in six weeks, but the existing-conditions survey identifies resilient flooring and pipe insulation that may contain asbestos. The client argues that the work is limited to finishes and asks the interior designer to proceed with finish selections and demolition drawings while testing is arranged. The construction schedule has little float, and the suite will remain occupied during some enabling work. What is the most appropriate next step for the designer?

Correct Answer: C. Coordinate assessment by qualified hazardous-material professionals and use their findings to define abatement, access, and schedule requirements before affected work proceeds.
Explanation:

Suspect asbestos-containing materials require appropriate investigation and, where applicable, regulated abatement or other approved controls before disturbance. Qualified professionals can identify the materials, establish the extent of the hazard, and inform phasing and occupied-space protections. Proceeding until visible disturbance risks exposure and costly stop-work; encapsulation cannot be selected responsibly without assessment; and a structural-scope limitation or owner assertion does not establish that materials are safe.

Question 2

New Single answer

Topic: Project Assessment and Sustainability

Skill tested: Applies BOMA measurement concepts to distinguish usable area from rentable area.

A tenant is comparing two office proposals and asks the interior designer to reconcile the landlord's stated rentable area with the area available for workstation planning. The landlord reports a larger rentable figure that includes an allocation of shared building space. The tenant needs a reliable basis for comparing the amount of space it can plan within the leased premises, and the designer has not yet been given the lease exhibit or the landlord's measurement standard. Which action is most appropriate?

Correct Answer: D. Confirm the applicable BOMA measurement standard and review the landlord's area calculations and lease documentation before comparing usable area.
Explanation:

Rentable and usable area are distinct measurement concepts, and the applicable BOMA standard, building-specific calculations, and lease language matter to a defensible comparison. The designer should obtain and review the documented basis rather than apply an assumed factor or infer a measurement method from the perimeter. Rentable area may include a load factor for shared areas, so it should not be treated as the suite's usable planning area.

Question 3

New Single answer

Topic: Project Process, Roles, and Coordination

Skill tested: Coordinates stakeholder approvals, consultant responsibilities, and design milestones.

A corporate workplace project has a fixed move-in date. The facilities director approves plans, the executive sponsor controls funding, and IT must approve network and audiovisual requirements. The design team is nearing design development, but IT has not reviewed the workstation layouts; the facilities director wants to issue the package for pricing immediately. Construction documents depend on final power, data, and display locations, while the general contractor has not yet been selected. What should the project lead do next?

Correct Answer: D. Obtain documented stakeholder decisions on the IT-dependent layouts and identify their effect on the design-development approval and downstream deliverables.
Explanation:

The design team should resolve decisions that affect infrastructure and document them before advancing dependent deliverables. The facilities director's approval does not replace the IT stakeholder's technical review, and budget authority does not make the executive sponsor a substitute technical approver. Issuing incomplete pricing documents or postponing coordination risks rework, change costs, and schedule impacts precisely because power, data, and audiovisual locations depend on the layouts.

Question 4

New Single answer

Topic: Project Process, Roles, and Coordination

Skill tested: Evaluates value-engineering proposals against project performance and lifecycle requirements.

During design development for a healthcare-administration office, a cost review identifies a budget overrun. The contractor proposes replacing a specified high-durability flooring system with a lower-first-cost product. The proposed product meets the initial appearance goal but has a shorter expected service life and more disruptive maintenance. The client needs to reduce capital cost without sacrificing cleanability, accessibility, or the planned occupancy date. Which response is best?

Correct Answer: D. Compare lifecycle cost, performance, maintenance, and schedule impacts, then present the client with a documented alternative for approval.
Explanation:

Value engineering is a disciplined evaluation of function, performance, lifecycle cost, and project constraints - not automatic acceptance of the lowest initial price. A documented comparison lets the client decide whether the savings justify maintenance, durability, and operational consequences while confirming compliance with cleanability and accessibility needs. Automatic acceptance disregards performance; rejecting every alternative prevents a reasoned budget response; and deferring known lifecycle impacts to future change orders is not sound cost management.

Question 5

New Single answer

Topic: Professional Business Practices

Skill tested: Defines proposal scope, exclusions, and additional services for a professional design engagement.

A small design practice is preparing a fee proposal for a tenant improvement. The client's request includes space planning, finish selection, and construction-phase site visits, but it also mentions possible procurement of furniture and coordination of specialty audiovisual equipment. The project budget is not yet confirmed, and the client expects the proposal to cover "everything needed." Which proposal approach best manages expectations and professional liability?

Correct Answer: D. Define the included services and deliverables, identify assumptions and exclusions, describe a process and fee basis for additional services, and clarify the client's approval responsibilities.
Explanation:

A clear proposal establishes scope, deliverables, assumptions, exclusions, and how additional services will be authorized and compensated. This is especially important where procurement and specialty-system coordination may require different effort, risk, or expertise. A vague fee-change clause does not define obligations; silent exclusions create expectation disputes; and tying a fee to an unconfirmed budget without a defined scope leaves both parties uncertain about the services being purchased.

Question 6

New Multiple answers

Topic: Code Requirements, Laws, Standards, and Regulations

Skill tested: Coordinates accessibility and life-safety review with the authority having jurisdiction.

A design team is renovating an existing restaurant in a jurisdiction that adopts a locally amended building code. The proposed layout changes the dining-room seating, relocates a door, and reconfigures an accessible service counter. The owner wants to submit for permit next week and claims the existing certificate of occupancy means no code review is needed. The designer has not confirmed the adopted code edition, local accessibility provisions, or whether the changes trigger review of the means of egress. Which TWO actions are most appropriate before finalizing the permit set? Select TWO.

Correct Answer: A. Confirm applicable adopted codes and amendments with the jurisdiction and determine the permit and review requirements for the proposed scope.; E. Coordinate accessibility and egress review for the changed layout with the responsible design professionals and verify applicable requirements.
Explanation:

The locally adopted code and amendments govern, and permit requirements can vary by jurisdiction and scope. The team should establish those requirements and evaluate accessibility and egress implications of the changed layout before issuing a permit set. A model code edition is not automatically enforceable locally, and an existing certificate of occupancy does not approve proposed alterations. The authority having jurisdiction reviews submitted work but does not replace the design team's responsibility to prepare coordinated, code-informed documents.

Question 7

New Single answer

Topic: Code Requirements, Laws, Standards, and Regulations

Skill tested: Identifies when local zoning and change-of-use review affects interior project feasibility.

A client proposes converting a ground-floor retail space into a small fitness studio. The interior concept fits within the existing suite, and the owner says the building already has a valid occupancy permit. The proposal adds group exercise classes, extended operating hours, and a higher expected occupant load. Before the design team commits to the proposed plan and schedule, what is the best first step?

Correct Answer: C. Confirm with the local jurisdiction whether the proposed use and operating conditions comply with zoning and applicable change-of-use or permit requirements.
Explanation:

A change from retail to a fitness studio may raise zoning, use, occupancy, egress, and permit questions that must be investigated with the relevant jurisdiction before the design is committed. An existing permit does not necessarily authorize a different use or the proposed operating conditions. The contractor should not be expected to resolve a fundamental feasibility issue after documents are developed, and simply reducing equipment does not establish zoning compliance.

Question 8

New Multiple answers

Topic: Integration with Building Systems and Construction

Skill tested: Coordinates ceiling design with mechanical distribution and fire-protection requirements.

An office renovation replaces an open ceiling with a suspended acoustic ceiling. The reflected ceiling plan shifts several partitions and adds enclosed focus rooms. Existing supply diffusers, return-air paths, sprinkler heads, smoke detection, and lighting are shown on separate consultant drawings, and the mechanical engineer notes that airflow must remain balanced. The client wants the ceiling package issued for construction without delaying the project. Which TWO actions best reduce coordination risk before issue? Select TWO.

Correct Answer: C. Overlay and coordinate the reflected ceiling plan with mechanical, fire-protection, electrical, and life-safety layouts, resolving conflicts with the responsible consultants.; D. Confirm that enclosed rooms have coordinated supply and return-air provisions and that system changes are reviewed by the mechanical engineer.
Explanation:

A suspended ceiling and new enclosed rooms affect the coordinated location and operation of multiple systems. Reviewing the combined reflected ceiling and consultant information helps resolve clashes before construction; confirming supply and return provisions supports the mechanical engineer's airflow design. Unreviewed field relocations can compromise performance or code compliance. Decorative-only plans and omitted detection overlook the need to coordinate ceiling-mounted devices and life-safety systems.

Question 9

New Single answer

Topic: Integration with Building Systems and Construction

Skill tested: Recognizes post-tensioned structural constraints before specifying slab penetrations.

A tenant requests a new floor outlet near a conference table in a building with a concrete floor. The existing drawings identify the slab as post-tensioned, but they do not show verified tendon locations at the proposed outlet. The furniture plan is approved, and the electrical contractor asks the interior designer to mark a core-drill location so procurement can proceed. What should the designer do?

Correct Answer: A. Require structural review and appropriate verification of tendon locations before authorizing any slab penetration, then coordinate a feasible electrical route.
Explanation:

Post-tensioned tendons are structural components, and an unverified penetration can cause serious damage. The team must not authorize coring based only on furniture geometry; qualified structural review and reliable tendon-location information are needed before a route is approved. Moving the outlet unilaterally may fail the client's requirements, while a larger core does not make drilling safe and can increase the risk of tendon interference.

Question 10

New Single answer

Topic: Integration of Furniture, Fixtures, & Equipment

Skill tested: Coordinates modular workstation power integration with furniture and electrical documentation.

A workplace project specifies modular workstations with power poles and under-desk power components. During shop-drawing review, the furniture supplier's layout places several poles directly below ceiling-mounted power feeds, while the electrical drawings show floor boxes at the original workstation locations. The client has approved the new furniture count but not the revised layout. The move-in date cannot shift. What is the most appropriate action?

Correct Answer: D. Coordinate the workstation, power-feed, and electrical layouts with the supplier and electrical engineer, obtain required client approval, and resolve discrepancies before release.
Explanation:

Furniture power integration depends on coordinated furniture layouts, feed locations, electrical design, and approved workstation configuration. Discrepancies should be resolved and approved before shop drawings and orders are released, particularly with a fixed move-in date. Supplier responsibility does not eliminate design-team coordination. Extension cords are not a substitute for a designed installation, and deleting power components without confirming capacity and distribution could leave workstations inadequately served.

Question 11

New Multiple answers

Topic: Integration of Furniture, Fixtures, & Equipment

Skill tested: Plans procurement and installation sequencing for customer-supplied materials and long-lead furniture.

A hotel project includes custom banquette upholstery using Customer's Own Material (COM) and imported lounge seating with a long manufacturing lead time. The owner intends to purchase the upholstery fabric directly, but the fabric has not been tested against the supplier's requirements. The banquettes must be installed after wall finishes but before final furniture placement, and the opening date is fixed. Which TWO actions are most appropriate? Select TWO.

Correct Answer: B. Track submittal approval, purchase, production, and delivery dates for the long-lead seating against the project schedule.; C. Confirm the manufacturer's COM requirements and approvals, and clarify responsibility for fabric quantity, delivery, inspection, and any required testing.
Explanation:

COM procurement requires agreement on technical suitability, quantity, delivery, and responsibility so the fabric is available and accepted for fabrication. Long-lead items should be tracked through approvals, purchase, production, and delivery against the opening date. Ordering imported furniture at the last moment threatens the schedule; fabric that has not been accepted can delay or invalidate fabrication; and banquette installation should follow the planned sequence to avoid damage and rework.

Question 12

New Single answer

Topic: Contract Administration

Skill tested: Distinguishes an RFI clarification from a change to the contract documents.

During construction of a reception area, the contractor submits an RFI asking whether a dimension shown between two fixed partitions should be measured to the framing or finished face. The contract documents do not clearly resolve the issue. A response could affect the millwork fit, but the contractor has not proposed a price or requested a scope change. The millwork is scheduled for fabrication shortly. What should the designer do?

Correct Answer: D. Issue a clarification through the established RFI process, coordinating with relevant consultants and identifying any resulting document correction or potential cost and schedule impact.
Explanation:

An RFI seeks clarification of the contract documents; it does not automatically authorize a change to scope, price, or time. The designer should respond promptly through the project's documented process, resolve the technical ambiguity before fabrication, and determine whether a formal document revision or change process is needed. A change order is premature without an agreed change, while leaving the interpretation to the contractor or postponing resolution risks defective or misfitting millwork.

Question 13

New Single answer

Topic: Contract Administration

Skill tested: Reviews contractor payment applications against verified progress and contract documentation.

A contractor submits a monthly payment application that includes a large percentage for custom reception millwork. The millwork is in fabrication off-site, but the contract documents and payment schedule do not clearly state whether stored or off-site materials are eligible for payment. The designer has received no evidence of ownership, insurance, or protection of the materials, and the client asks for a recommendation before the payment deadline. What is the best response?

Correct Answer: B. Review the contract and payment provisions, request required substantiation for off-site materials, and recommend certification only for amounts supported by the agreed requirements and verified progress.
Explanation:

Payment certification must follow the contract's requirements and be supported by appropriate evidence of progress. For off-site materials, the contract may require documentation such as identification, ownership, insurance, storage, and protection; the designer should not assume eligibility or approve unsupported amounts. Automatically approving because fabrication began exposes the client to risk. Conversely, withholding all payments disregards properly earned amounts, and deferring substantiation leaves the current payment unsupported.