Free CompTIA Project+ Certification (2026) PK0-005 Exam Questions

Last updated: · 13 practice questions with answers and explanations

Page: 1 / 31 Total 460 questions

Want more questions? Get Premium Access.

Question 1

New Single answer

Topic: Project Management Concepts

Skill tested: Selects a delivery methodology based on uncertainty, feedback needs, and fixed constraints.

A regional insurer must replace an outdated claims portal before a regulator-imposed date. The regulatory rules and required audit evidence are stable, but users have not agreed on the most effective claim-review workflow. The project has a small cross-functional team and business representatives can review working software every two weeks. The organization requires documented approval of the baseline scope and formal authorization for changes that affect the committed launch date. Which delivery approach best accommodates both the stable compliance requirements and the evolving user workflow?

Correct Answer: A. Use a hybrid approach: baseline regulatory deliverables and the launch constraint, while iteratively refining the workflow with frequent user reviews.
Explanation:

A hybrid approach fits the different levels of uncertainty. Stable regulatory deliverables and the launch constraint can be planned and governed predictively, while the workflow can be refined through short iterations and frequent user feedback. Formal change control still applies when a proposed change affects the approved baseline or launch date. A purely predictive approach delays useful feedback, while an unrestricted adaptive approach conflicts with the required date governance. Treating every suggestion as a defect incorrectly assumes that all new preferences were part of the original agreed requirements.

Question 2

New Single answer

Topic: Project Management Concepts

Skill tested: Applies project change control to assess scope, schedule, cost, and approval impacts.

During a data-center migration, a department asks the project team to add a reporting feature to the new service. The feature is not in the approved scope, and the migration date is tied to a facility lease ending. A developer estimates that the work may add two weeks, but has not assessed testing, licensing, or operational support impacts. The sponsor asks the project manager to give the department an answer at the next status meeting. What should the project manager do first?

Correct Answer: D. Record the request and assess its effects on scope, schedule, cost, risk, quality, and resources before presenting it for authorized review.
Explanation:

The request should be documented and evaluated before an authorized decision is made. A change-impact assessment needs to consider more than development effort, including testing, licensing, support, and the immovable migration date. The project manager can then route the request through the project's change-control process and communicate the decision. Starting work before approval bypasses control and may jeopardize the date. Automatically rejecting all changes is not sound change management, and a sponsor's request for a timely answer is not itself approval of the change.

Question 3

New Multiple answers

Topic: Project Management Concepts

Skill tested: Prioritizes project risks and selects appropriate response planning and ownership.

A project is integrating a new payment platform with a vendor service. The vendor has not yet confirmed that its production interface supports the organization's required token format, and a failed integration could delay launch. A separate risk is that the project lead may be unavailable for one week; the team has already identified a qualified deputy. The risk register is being prepared before development begins. Which TWO actions are most appropriate? (Select TWO.)

Correct Answer: A. Record the interface compatibility uncertainty, assess its likelihood and impact, and assign an owner to obtain confirmation or plan a test.; B. Record the lead's possible absence as a risk and identify the deputy and handoff steps as a mitigation or contingency.
Explanation:

Both conditions are uncertain future events, so they belong in the risk register rather than the issue log. The interface risk warrants likelihood-and-impact assessment, an accountable owner, and a response such as vendor confirmation or an early integration test. The lead's possible absence can be reduced through a named deputy and planned handoff. Calling an unverified capability an existing issue confuses uncertainty with a realized problem. Waiting until risks occur defeats proactive management, and assigning every response to the sponsor ignores the value of ownership by people able to manage the specific exposure.

Question 4

New Single answer

Topic: Project Management Concepts

Skill tested: Uses schedule dependencies, milestones, and float to protect a fixed delivery date.

A software deployment has a fixed public launch date. The current schedule includes configuration, integration testing, security testing, and user training. Integration testing cannot begin until configuration is complete; security testing depends on a stable integration environment; training materials can be drafted while configuration is underway but cannot be finalized until the user interface is stable. A late training-material review has some schedule float, while security testing is on the critical path. A manager proposes shortening security testing to recover two days. What is the best response?

Correct Answer: D. Map the dependencies and resource availability, then seek recovery through feasible parallel work or additional resources without removing required security testing.
Explanation:

Schedule recovery should begin with a valid dependency and resource analysis. The team can examine whether independent work, such as drafting training materials, can proceed in parallel and whether suitable additional resources can shorten critical-path work without compromising required tests. Cutting security testing may reduce assurance and does not address the underlying schedule logic. Testing before a stable integration environment would produce unreliable results. A single launch milestone also removes the visibility needed to manage dependencies and detect slippage early.

Question 5

New Single answer

Topic: Project Management Concepts

Skill tested: Distinguishes retrospectives, sprint reviews, KPIs, and audit purposes.

A product team has completed three two-week iterations. Stakeholders want to inspect the completed user-facing features and decide whether priorities should change. Separately, the team wants to understand why handoffs repeatedly delay work and agree on a process improvement. The compliance office also requires evidence that release approvals followed policy. Which activity is best suited to the team's process-improvement discussion?

Correct Answer: A. A retrospective focused on how the team worked and on selecting improvements for the next iteration.
Explanation:

A retrospective is the appropriate forum for examining collaboration, handoffs, and process changes the team can make. A sprint review instead inspects the increment with stakeholders and supports product feedback and reprioritization. A KPI review can reveal a performance trend but does not replace a facilitated discussion about causes and team actions. An audit verifies conformity to controls; it is not primarily a mechanism for the team to improve its workflow. The scenario distinguishes these activities by their intended outcomes.

Question 6

New Single answer

Topic: Project Management Concepts

Skill tested: Plans stakeholder communication cadence, channels, and escalation paths.

A project is rolling out a new identity-management process across four business units. Executives need concise monthly status and decisions requiring sponsorship; service-desk staff need weekly operational instructions; the project team needs rapid daily coordination. Some employees work remotely, and sensitive personnel information must not be included in broadly distributed updates. The project has an approved collaboration platform and an internal ticketing system. What should the project manager do to establish effective communication?

Correct Answer: C. Create a communication plan that defines audience-specific content, cadence, channel, owner, confidentiality handling, and escalation route.
Explanation:

A communication plan should match information to stakeholder needs and specify how and when it will be delivered, who owns it, and how urgent matters are escalated. It should also restrict sensitive personnel details to appropriate audiences and channels. A single broad email risks overloading some groups and exposing information. Ticketing is useful for operational work tracking but is not an adequate sole channel for executive decisions or all project communications. Waiting for requests creates inconsistent expectations and can delay important decisions.

Question 7

New Single answer

Topic: Project Life Cycle Phases

Skill tested: Uses business-case and financial information to compare project investment options.

A retailer is considering two proposals to replace its inventory-planning system. Proposal Alpha has a lower initial cost but requires a large annual support contract. Proposal Beta costs more to implement but has lower recurring costs and is expected to reduce stockouts. The steering group has asked the project manager to prepare a discovery-phase comparison before selecting a proposal. The estimates use the same analysis period, but the projected benefits and costs occur at different times. Which financial measure best accounts for the time value of money when comparing the proposals?

Correct Answer: B. Net present value, using the same discount-rate assumptions and analysis period for both proposals.
Explanation:

Net present value discounts expected future cash flows, allowing proposals with different cost and benefit timing to be compared on a consistent basis. The same analysis period and discount assumptions are important for a fair comparison. Payback period can help assess how quickly an investment is recovered, but by itself it may omit cash flows after the payback point and does not provide the same full discounted comparison. Initial cost ignores recurring support, while an undiscounted average fails to account for when costs and benefits occur.

Question 8

New Single answer

Topic: Project Life Cycle Phases

Skill tested: Creates a project charter that establishes purpose, authority, objectives, and constraints.

A healthcare organization has approved funding to build a secure referral portal, but different departments disagree about who can authorize project decisions. The project manager is preparing for initiation. The portal must meet an externally imposed launch date, integrate with an existing patient-record system, and remain within a preliminary budget. Detailed requirements and the work breakdown are not yet known. Which artifact should establish the project's purpose, high-level objectives, key constraints, sponsor, and the project manager's authority before detailed planning begins?

Correct Answer: B. A project charter approved by the sponsor.
Explanation:

The project charter formally authorizes the project and establishes its purpose, high-level objectives, constraints, key stakeholders, and the project manager's authority. It is appropriate before detailed requirements and task-level planning are complete. A detailed schedule is a planning artifact and would be premature without decomposed work. A traceability matrix supports requirements and testing management later, while a closure report is created at the end of the project. Sponsor approval also helps resolve the stated uncertainty about decision authority.

Question 9

New Multiple answers

Topic: Project Life Cycle Phases

Skill tested: Develops planning artifacts that define scope, responsibilities, communication, and risk responses.

A project will replace a regional office's network equipment during a two-hour maintenance window. The approved high-level objective is clear, but the team has not yet established detailed boundaries, ownership, or stakeholder communications. A site outage would interrupt customer service, and a field technician must be available at the installation location. The project manager is preparing the planning package for approval. Which TWO actions should be included? (Select TWO.)

Correct Answer: B. Document risk responses for the maintenance-window outage and confirm the necessary technician and fallback resources.; C. Define in-scope and out-of-scope work, acceptance criteria, and the deliverables needed for the replacement.
Explanation:

Planning should make the work and its boundaries testable by defining deliverables, acceptance criteria, and exclusions. It should also address the material outage risk with response planning and verify that required people and fallback resources are available for the constrained maintenance window. Assigning everything to the project manager obscures accountability rather than clarifying it. Communication planning is needed before execution, particularly when a service interruption is expected. A high-level objective alone is not a sufficiently detailed scope baseline for estimating and controlling the work.

Question 10

New Single answer

Topic: Project Life Cycle Phases

Skill tested: Manages vendor performance and uses phase-gate evidence before authorizing execution.

A company is implementing a new customer-support platform under a fixed-price vendor contract. The vendor reports that configuration is complete and requests approval to begin production data migration. The project plan requires a phase-gate review before migration, including evidence of successful integration testing, approved security findings, and a documented rollback approach. The vendor says the evidence can be supplied after migration because the schedule is tight. What should the project manager do?

Correct Answer: D. Hold the gate decision until the required evidence is reviewed and any unmet acceptance conditions are resolved or formally dispositioned by the authorized decision-maker.
Explanation:

A phase gate is a decision point, not a formality. The project manager should verify required test, security, and rollback evidence before authorizing a production migration, and escalate any exception to the appropriate decision-maker. Proceeding first exposes production data and service continuity to avoidable risk and reverses the intended control sequence. A partial production migration is not an acceptable substitute for required evidence. The vendor's request alone does not justify immediate contract cancellation; the project should manage performance against contract terms and approved acceptance criteria.

Question 11

New Single answer

Topic: Project Life Cycle Phases

Skill tested: Closes a project by validating acceptance, contracts, resources, and records.

A consulting team has completed a document-management implementation. Users have signed the acceptance record, but the project still has an open vendor purchase order, temporary administrator accounts, and project files stored in individual team members' workspaces. A lessons-learned meeting has not been held. The sponsor wants the project marked complete before the team is reassigned. What is the most appropriate next step?

Correct Answer: D. Complete administrative closure by resolving the vendor commitment, removing temporary access, archiving project records, releasing resources, and documenting lessons learned.
Explanation:

Deliverable acceptance is essential, but closure also requires administrative and operational wrap-up. The project should reconcile and close the vendor commitment, remove or formally transfer temporary access, archive records in an accessible repository, release resources, and capture lessons learned. Marking the project complete while these matters remain unresolved creates financial, security, and records-management gaps. Keeping it open for a hypothetical future replacement is unnecessary. Unrecorded transfers of financial or privileged access responsibilities weaken accountability.

Question 12

New Single answer

Topic: Tools and Documentation

Skill tested: Selects a chart that identifies the highest-contributing sources of defects.

A release manager is reviewing 240 defects found during testing. The team has classified them by cause, including interface failures, data errors, usability problems, and environment configuration. The manager needs to identify which few categories account for most defects so that limited remediation time is directed at the largest contributors. The team does not need to explore correlation between two numeric variables or the sequence of causes behind one specific defect. Which tool is most appropriate?

Correct Answer: C. A Pareto chart ranking defect categories by frequency, typically with a cumulative percentage.
Explanation:

A Pareto chart ranks categories by frequency and commonly displays cumulative contribution, helping the manager focus on the categories that account for the largest share of defects. A scatter diagram examines relationships between paired variables, not category prioritization. A fishbone diagram is useful for exploring possible causes of a defined problem, while a histogram shows the distribution of a numerical measure such as repair duration. Those tools do not directly answer which defect categories contribute most to the total.

Question 13

New Multiple answers

Topic: Basics of IT and Governance

Skill tested: Applies secure change control across staging, production, and CI/CD deployment.

A financial-services team is preparing a web application release. Developers deploy builds automatically to a staging environment, where testers use synthetic data. Production contains regulated customer information, and the organization requires documented approval for production changes. The release pipeline currently allows a developer to promote a build directly to production, and the project manager has been asked to recommend two controls that preserve automated delivery while meeting governance and security requirements. Which TWO actions are most appropriate? (Select TWO.)

Correct Answer: A. Use staging validation and approved release evidence as a gate before the authorized production deployment.; C. Require documented authorization and appropriate separation of duties for production promotion, while retaining automated build and test steps.
Explanation:

Automated delivery can coexist with formal production change control. Production promotion should require the documented authorization and separation of duties mandated by policy, and staging results and release evidence should support the deployment decision. Synthetic data avoids unnecessary exposure of regulated customer information in staging; copying production data would create privacy and security risk unless a specifically authorized, protected process existed. Disabling automated tests undermines quality controls, while self-approval by the developer does not provide the required independent authorization merely because the pipeline logs the action.