Limited-Time Offer: Enjoy 50% Savings! Ends in 00h 00m 00s Coupon code: 50OFF
Skip to content

Free GAQM Associate in Project Management APM-001 Exam Questions

Page: 1 / 47 Total 704 questions

Want more questions? Get Premium Access.

Question 1

Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?

Correct Answer: B. Motivation

Question 2

Which defines the portion of work included in a contract for items being purchased or acquired?

Correct Answer: D. Procurement statement of work

Question 3

A complete set of concepts, terms, and activities that make up an area of specialization is known as:

Correct Answer: A. a Knowledge Area

Question 4

Which technique is utilized in the Control Schedule process?

Correct Answer: D. Variance analysis

Question 5

Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:

Correct Answer: C. preventive actions.

Question 6

Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?

Correct Answer: C. Perform Qualitative Risk Analysis

Question 7

When cost variance is negative and schedule variance is positive, the project is:

Correct Answer: B. over budget and ahead of schedule.

Question 8

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

Correct Answer: B. 0.06

Question 9

The formal and informal interaction with others in an organization industry, or professional environment is known as:

Correct Answer: D. networking

Question 10

Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

Correct Answer: C. Risk and uncertainty decrease; the cost of changes increases.

Question 11

The process for performing variance analysis may vary, depending on:

Correct Answer: C. application area, the standard used, and the industry,

Question 12

What is the term assigned to products or services having the same functional use but different technical characteristics?

Correct Answer: D. Grade

Question 13

The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:

Correct Answer: A. Human resource management plan.

Question 14

The purpose of the Project Communications Management Knowledge Area is to:

Correct Answer: D. Ensure timely and appropriate collection of project information.

Question 15

Which stakeholder approves a project's result?

Correct Answer: A. Customer