Question 1
Topic: 1.1 Section I – Organizational Roadblocks and Lean Management
Skill tested: Uses takt time, cycle time, and available capacity to identify a flow constraint.
A service center receives 420 requests during a 7-hour staffed shift. Demand is reasonably level, and the team has 25,200 seconds of available production time per shift after planned breaks. A process step currently completes one request every 65 seconds, while the downstream step averages 58 seconds. The center has accumulated a large queue between the two steps and cannot add staff or extend operating hours. Management wants a daily operating target that aligns output with customer demand before selecting improvement actions. Which interpretation should guide that target?
Takt time is available production time divided by customer demand: 25,200 seconds ÷ 420 requests = 60 seconds per request. This is the pace the process must meet to satisfy demand. Cycle time describes the actual time a process step takes, so the 65-second step is currently slower than takt and is a likely constraint; the 58-second downstream cycle time does not define customer demand. Lead time includes waiting and processing across the flow, so the queue affects lead time but does not set takt.