Question 1

New Single answer

Topic: 1.1 Section I – Organizational Roadblocks and Lean Management

Skill tested: Uses takt time, cycle time, and available capacity to identify a flow constraint.

A service center receives 420 requests during a 7-hour staffed shift. Demand is reasonably level, and the team has 25,200 seconds of available production time per shift after planned breaks. A process step currently completes one request every 65 seconds, while the downstream step averages 58 seconds. The center has accumulated a large queue between the two steps and cannot add staff or extend operating hours. Management wants a daily operating target that aligns output with customer demand before selecting improvement actions. Which interpretation should guide that target?

Correct Answer: B. Set the target at one request every 60 seconds because takt time is available time divided by demand.
Explanation:

Takt time is available production time divided by customer demand: 25,200 seconds ÷ 420 requests = 60 seconds per request. This is the pace the process must meet to satisfy demand. Cycle time describes the actual time a process step takes, so the 65-second step is currently slower than takt and is a likely constraint; the 58-second downstream cycle time does not define customer demand. Lead time includes waiting and processing across the flow, so the queue affects lead time but does not set takt.

Question 2

New Single answer

Topic: 1.2 Section II – Pre-define DMAIC

Skill tested: Prioritizes improvement projects using NPV, strategic fit, and enterprise-wide impact.

A company's steering committee must choose one of two proposed process-improvement projects. Project Alpha has a positive net present value (NPV) of $180,000, a 19% internal rate of return (IRR), and benefits a single business unit. Project Beta has a positive NPV of $145,000, a 24% IRR, and removes a recurring handoff defect affecting four business units; its benefits are supported by validated volume and cost data. The company's hurdle rate is 12%, and both projects fit within the available budget and staffing. The executive sponsor has stated that the selected project must maximize enterprise-wide value rather than select solely on the highest IRR. What is the best recommendation?

Correct Answer: B. Choose Beta, confirming its cross-business benefits and assumptions in the prioritization review.
Explanation:

Both proposals clear the 12% hurdle and have positive NPVs, so neither is rejected on financial grounds. Beta best matches the stated enterprise-wide objective because it addresses a recurring issue across four business units, and its quantified benefits have been validated. Its higher IRR is supportive but should not be the sole selection criterion. Alpha has the greater NPV, but that figure alone does not establish greater enterprise-wide strategic value. Deferring both is unwarranted given the stated financial and resource conditions.

Question 3

New Single answer

Topic: 1.2.2 Define

Skill tested: Converts voice-of-customer needs into measurable CTQs using a CTQ tree.

An online lender receives complaints that applicants experience an "unpredictable approval experience." Interviews clarify that customers primarily want a quick decision and reliable status updates. The project team is defining measurable requirements before collecting baseline data. A proposed metric is the average end-to-end application lead time, but executives note that a low average could conceal a long tail of very delayed applications. The team needs a CTQ operational definition that reflects the customer need and supports later measurement. Which definition is most appropriate?

Correct Answer: B. Ensure at least 95% of complete applications receive a decision within 24 hours, measured from receipt of all required information to decision notification.
Explanation:

A CTQ translates a customer need into a specific, measurable requirement. The 95%-within-24-hours definition identifies the eligible applications, start and end points, and a threshold, making it suitable for operational measurement and baseline comparison. An average alone can hide delayed cases, while throughput per employee is an internal process metric that does not directly establish the promised customer outcome. A broad satisfaction score may be useful as a business measure, but it is not a sufficiently precise CTQ operational definition.

Question 4

New Single answer

Topic: 1.3 Section III – Measure

Skill tested: Selects an appropriate capability index when process centering and specification limits matter.

A manufacturer measures a stable, approximately normal shaft diameter. The lower and upper specification limits are 9.90 mm and 10.10 mm. The process mean is 10.06 mm, and the estimated within-process standard deviation is 0.02 mm. The engineering manager asks whether the process can meet both specifications consistently, not merely whether its spread is narrow relative to the tolerance. The measurement system has acceptable resolution and repeatability, and no recent special causes appear on the control chart. Which capability measure and interpretation are most appropriate?

Correct Answer: D. Use Cpk; it accounts for the process mean's proximity to the nearest specification, and the upper side limits performance.
Explanation:

Cpk incorporates both process spread and centering by comparing the mean's distance to each specification with the within-process variation. Here the mean is closer to the upper limit: (10.10 - 10.06) ÷ (3 × 0.02) is approximately 0.67, while the lower-side index is larger. Cp considers tolerance width relative to process spread but ignores off-centering, so it cannot answer the manager's question by itself. PCE and RTY address flow efficiency and rolled yield, not continuous dimensional capability.

Question 5

New Multiple answers

Topic: 1.3 Section III – Measure

Skill tested: Diagnoses measurement-system variation using crossed variable Gage R&R study design.

A plant wants to determine whether measurement variation is obscuring differences among machined parts. Three inspectors can each measure every sampled part, and parts can be measured repeatedly without changing their physical characteristics. Measurements are numeric and the measurement method is nondestructive. The quality engineer needs to estimate repeatability and reproducibility separately, while minimizing the chance that inspectors infer prior readings. Which two design practices should the engineer use? Select TWO.

Correct Answer: B. Have each inspector measure the same representative parts multiple times, with measurements blinded and randomized in order.; C. Use a crossed study in which every inspector measures every selected part.
Explanation:

A crossed variable Gage R&R design has each appraiser measure each part, allowing the analysis to separate part-to-part variation, repeatability, and reproducibility. Repeated, blinded measurements are needed to estimate repeatability and help prevent an inspector from copying or being influenced by an earlier reading; randomizing the order reduces sequence-related bias. Giving inspectors different parts confounds appraiser and part effects. One inspector cannot provide an estimate of reproducibility, and single readings cannot estimate repeatability.

Question 6

New Single answer

Topic: 1.4 Section IV – Analyze

Skill tested: Interprets multiple regression coefficients while controlling for confounding predictors.

A distribution company analyzes delivery delay using multiple linear regression with distance, number of stops, and traffic congestion as predictors. The model has acceptable residual diagnostics for the intended operational use. A manager observes that the simple correlation between distance and delay is positive, but the fitted coefficient for distance is negative after the other predictors are included. The manager proposes removing distance as an error because longer routes should take longer. The data show that long-distance routes typically have fewer stops and less urban congestion. What is the most defensible next interpretation?

Correct Answer: A. The sign reversal may reflect the conditional effect after controlling for correlated route characteristics; investigate collinearity and interpret the coefficient conditionally.
Explanation:

A multiple-regression coefficient describes the association with delay while holding the other included predictors constant. Because distance is related to stops and congestion, its conditional coefficient can differ in sign from its simple correlation; this pattern may reflect confounding or multicollinearity and should be investigated rather than treated as proof that longer distance reduces delay. The coefficient does not automatically justify changing routes. Removing meaningful predictors without analysis risks omitted-variable bias, and multiple regression can represent relationships that differ from marginal correlations.

Question 7

New Multiple answers

Topic: 1.5 Section V – Improve

Skill tested: Plans factorial experiments that estimate main effects and interactions without confounding treatment order.

A laboratory wants to reduce a coating defect by studying curing temperature and line speed, each at two practical levels. Preliminary evidence suggests the effect of temperature may depend on line speed. The team can afford 16 experimental runs, has two production shifts that may differ, and must avoid confounding treatment settings with run order. It wants estimates of both main effects and their interaction, with a defensible assessment of experimental error. Which TWO choices best meet these requirements? Select TWO.

Correct Answer: D. Run a full 2^2 factorial with four treatment combinations, replicated across runs, and randomize treatment order within shift blocks.; E. Use a full 2^2 factorial, block runs by shift, and randomize treatment order within each block.
Explanation:

A full 2² factorial includes all four combinations of temperature and line speed, so it can estimate both main effects and their interaction. Replication supplies information about experimental error, while blocking by shift accounts for a known nuisance source of variation and randomization within blocks helps protect against time-order effects. Testing temperature at only one speed cannot reveal an interaction. Grouping runs by treatment or changing one factor at a time risks confounding and does not provide a sound interaction estimate.

Question 8

New Single answer

Topic: 1.6 Section VI – Control

Skill tested: Selects and interprets an appropriate attribute control chart for defect rates.

A claims-processing operation audits a fixed sample of 200 claims each day and records the number containing at least one error. Each claim is classified as defective or not defective, and the audit sample size remains constant. The team has completed improvements and wants to detect whether the underlying fraction of defective claims changes over time. The data are not counts of individual errors, and multiple errors on one claim still count as one defective claim. Which control chart is most appropriate?

Correct Answer: A. A p-chart, because it tracks the fraction of defective claims in samples of constant size.
Explanation:

A p-chart monitors the proportion of nonconforming units and accommodates the stated binary classification of each claim. With a constant sample size of 200, its control limits remain constant under the usual p-chart calculation. A c-chart counts defects rather than defective units, and a u-chart monitors defects per unit; neither matches the rule that a claim with multiple errors counts once. X-bar and R charts are for measured continuous data, not attribute classifications.

Question 9

New Single answer

Topic: Lean Process Improvement

Skill tested: Uses PDSA cycles to test a process change before broader implementation.

A regional clinic's improvement team believes that moving a commonly used supply cart closer to the treatment area will reduce staff walking and improve patient flow. The team has not yet established whether the new location will create congestion during peak hours or increase restocking time. Leadership wants evidence before changing the layout at all clinics, and a full-scale rollout would be disruptive. Which action best follows the PDSA approach?

Correct Answer: A. Pilot the layout in one treatment area for a short period, specify measures and predictions, study the results, and adapt before expanding.
Explanation:

PDSA supports small-scale, measured tests of change: plan the trial and predictions, do the pilot, study the data, and act by adapting, adopting, or abandoning the change. A limited pilot can reveal congestion and restocking effects without imposing a disruptive system-wide rollout. Immediate implementation makes problems costly to reverse, while a staff vote does not establish process performance. A large randomized trial is not necessary to begin learning about a low-risk layout change.

Question 10

New Multiple answers

Topic: 1.1 Section I – Organizational Roadblocks and Lean Management

Skill tested: Applies SMED principles to reduce changeover time while preserving safe setup requirements.

A packaging line loses 70 minutes per shift to product changeovers. A walk-through shows that operators search for tools after the line stops, adjust guides while equipment is idle, and complete some cleaning tasks that could be performed without accessing moving parts. Food-safety rules require the product-contact surfaces to be cleaned and verified before the next run; operators may not bypass lockout requirements. The plant wants to shorten changeover without compromising safety or sanitation. Which TWO actions best apply SMED principles? Select TWO.

Correct Answer: C. Stage and verify the next product's tools, materials, and settings before stopping the line.; E. Separate internal tasks requiring a stopped line from external tasks that can safely occur while the line runs, then convert suitable tasks to external work.
Explanation:

SMED reduces changeover time by preparing and staging materials in advance and by converting tasks that can safely be done while production continues from internal to external work. The described tool search and eligible external tasks are clear opportunities. Cleaning product-contact surfaces and verification remain mandatory, and lockout requirements cannot be bypassed; cleaning inside guarded equipment while it runs is unsafe. Skipping verification violates the stated food-safety control. Larger batches may reduce changeover frequency but do not improve the changeover process itself.