Question 1
You work as a project manager for company Inc. Your project was baselined at 8 hours, but 11 hours have been spent and the estimate to complete is 1 additional hour. The project must have been completed already. An hourly rate of $100 per hour is provided. Which of the following is the planned value (PV) for the project?