Question 1
Topic: Delivery Performance Domain
Skill tested: Prioritizes scope decisions using business value, acceptance criteria, and change control.
A security team is replacing a legacy incident-tracking system. During user acceptance testing, executives request an additional analytics dashboard that was not in the approved scope. The dashboard may improve executive visibility, but delivering it now would delay the planned rollout by three weeks and consume contingency reserved for migration defects. The project's agreed success measures emphasize timely adoption of core incident workflows, and the sponsor has not approved a scope change. What should the project manager do FIRST?
The project manager should evaluate the requested change's value and its effects on scope, schedule, cost, risk, and the project's success measures, then route it through the established approval process. A potentially valuable request is not automatically authorized work. Building it immediately bypasses governance and risks the committed rollout; categorically rejecting it prevents an informed decision. Overtime does not resolve the need to assess impact or obtain approval and may create additional quality and sustainability risks.