Question 1
Topic: 1. Introduction to Huawei Smart PV C&I Solution
Skill tested: Evaluates C&I solution architecture selection for load profiles and export constraints.
A food-processing plant has a large daytime refrigeration load, limited roof area, and a strict grid-interconnection limit on exported power. Management wants to reduce purchased electricity without changing production schedules. The site can use a Huawei C&I PV solution and has an energy management system capable of coordinating generation and consumption. The customer is not seeking backup power, and the utility will not approve an increase in the export limit. Which solution approach best aligns the PV system with these requirements?
A load-oriented PV design can offset the plant's substantial daytime consumption, while export limitation prevents surplus power from exceeding the interconnection agreement. Measurement and control must be coordinated so the system responds to the site's net flow. Option A risks violating the export cap. An off-grid design is disproportionate and incompatible with the stated grid-connected operating context. Storage may be considered for other objectives, but adding it as the primary measure without control coordination is not the best fit, especially because the customer did not request backup.