Question 1
Topic: System and Server Bring-up
Skill tested: Plans deployment sequencing and validates server readiness before workload acceptance.
A team is bringing up a new rack of GPU servers for a production AI cluster. The systems have been physically installed, but firmware versions, cabling, power delivery, and cooling have not yet been validated. The operations lead wants to avoid diagnosing workload failures that are actually caused by installation defects. Production scheduling must remain disabled until the infrastructure passes its acceptance checks. Which approach should the team take next?
A staged bring-up separates installation defects from software and workload problems. Validate facility power and cooling, confirm that physical links and transceivers match the intended topology, establish the approved firmware baseline, and then verify installed hardware and operation before admitting nodes to production. Booting an OS alone does not validate the full platform, so C is premature. Workload installation cannot replace hardware acceptance (A), and a performance test does not make safety, firmware, or cabling checks unnecessary (D).