Question 1

New Single answer

Topic: Understanding and Applying the Scrum Framework:; Empiricism, Scrum Values, Scrum Team, Events, Artifacts, Done.

Skill tested: Applies empiricism and transparency when a Scrum Team faces unreliable progress information.

A product team has repeatedly reported that its Sprint Goal is on track, but integration failures discovered near the end of each Sprint have prevented usable Increments. The Developers say the failures cannot be predicted and want to keep reporting progress based on completed coding tasks. The Product Owner needs credible information to make release decisions, and the organization will not add a separate testing phase after each Sprint. What should the Scrum Master do first?

Correct Answer: B. Help the Scrum Team make its Definition of Done and integration status transparent, then inspect the causes and adapt its approach.
Explanation:

Empiricism depends on transparency, inspection, and adaptation. If integration work is hidden from the Definition of Done or progress view, stakeholders cannot make informed decisions and the team cannot inspect its actual delivery capability. The Scrum Master should facilitate transparency around what qualifies as Done and support the team in examining and adapting its work. Extending a Sprint changes its fixed timebox; a separate testing Sprint preserves the late discovery problem; and having the Scrum Master estimate work undermines the Developers' ownership of the plan.

Question 2

New Single answer

Topic: Understanding and Applying the Scrum Framework:; Empiricism, Scrum Values, Scrum Team, Events, Artifacts, Done.

Skill tested: Uses Sprint Review inspection to adapt product direction with stakeholders.

A team's product roadmap was approved six months ago, but customer behavior has since shifted. At the Sprint Review, the Product Owner presents the completed Increment and asks stakeholders to approve or reject the original roadmap. Several stakeholders raise new market evidence, while the Developers note that the roadmap's next planned feature may no longer be valuable. The company requires release decisions to remain with the Product Owner, but wants stakeholder feedback to shape upcoming work. What is the most appropriate way to use the Sprint Review?

Correct Answer: D. Use the Review to inspect the Increment, discuss changes in the environment, and collaborate on possible adaptations to the Product Backlog.
Explanation:

The Sprint Review is a working session for the Scrum Team and stakeholders to inspect the outcome of the Sprint and discuss adaptations in response to changes. Stakeholders provide input; the Product Owner remains accountable for effective Product Backlog management and decides how that input affects product direction. Treating the roadmap as fixed blocks adaptation. Stakeholders do not select or impose the Sprint Backlog, and limiting the Review to a demonstration wastes its opportunity for collaborative inspection.

Question 3

New Multiple answers

Topic: Developing People and Teams:; Self-Managing Teams, Facilitation, Leadership Styles, Coaching and Mentoring.

Skill tested: Coaches a self-managing team to resolve an impediment without taking over decisions.

A newly formed Scrum Team depends on a department manager to assign individual tasks each morning. During Sprint Planning, the manager also directs the Developers to use a particular design, even though they have identified a lower-risk alternative. The manager is willing to change but expects the Scrum Master to provide a practical way forward. The team must retain responsibility for its technical decisions, and the manager controls access to a specialist required for the work. Which two actions are most appropriate? Select TWO.

Correct Answer: A. Facilitate a conversation in which the Developers clarify how they will organize the work and make technical decisions.; C. Coach the manager on how directive task assignment affects self-management, and help address the specialist-access impediment.
Explanation:

Self-management means the Developers decide who does what, when, and how; the Scrum Master can facilitate a conversation that helps them take that responsibility rather than assigning work. The manager also creates a concrete impediment by controlling access to a needed specialist, so coaching the manager and helping resolve access is appropriate. Taking over assignments repeats the problem. The Product Owner is accountable for maximizing product value, not directing technical design. Immediate escalation may be premature when constructive coaching can address the issue.

Question 4

New Single answer

Topic: Developing People and Teams:; Self-Managing Teams, Facilitation, Leadership Styles, Coaching and Mentoring.

Skill tested: Selects facilitation techniques that help a team address persistent conflict productively.

Two experienced Developers disagree sharply about whether to refactor a fragile component before adding a requested feature. Their debate dominates several Daily Scrums, and other team members have stopped contributing. The Product Owner needs a forecast but does not have the technical expertise to resolve the design dispute. A release deadline is approaching, yet neither approach has been evaluated against the team's Definition of Done or technical risks. What should the Scrum Master do next?

Correct Answer: C. Facilitate a focused discussion in which the Developers surface assumptions, assess risks and options, and agree on an experiment or decision.
Explanation:

The Scrum Master should facilitate collaboration rather than resolve a technical disagreement by authority. A structured discussion can restore participation, make assumptions and risks explicit, and help the Developers decide how to proceed while honoring the Definition of Done. Choosing for the team weakens self-management; the Product Owner does not own technical design decisions; and removing the work avoids the underlying conflict without helping the team improve its decision-making.

Question 5

New Single answer

Topic: Managing Products with Agility:; Product Backlog Management, Stakeholders & Customers.

Skill tested: Supports Product Backlog ordering using customer outcomes and new evidence.

A Product Owner has a Product Backlog containing a large regulatory feature, several customer-requested improvements, and a speculative platform rewrite. A major customer has supplied new evidence that one improvement would prevent a costly workflow failure. Executives argue that the platform rewrite should come first because it is strategically important, while Developers warn that the rewrite's scope and value are unclear. The Product Owner remains accountable for the ordering and must meet a known regulatory deadline. What is the best next step?

Correct Answer: D. Collaborate with stakeholders and Developers to refine the evidence, value, risk, and dependencies, then order the Product Backlog to maximize value while meeting the regulatory need.
Explanation:

Product Backlog ordering is the Product Owner's accountability, informed by stakeholder needs, customer evidence, value, risk, and dependencies. Refinement with the Developers can clarify uncertainty and support a realistic ordering that accounts for the regulatory deadline without assuming the rewrite is valuable merely because it is strategic. Ranking by stakeholder seniority ignores outcomes, delegating ordering to Developers transfers accountability, and starting the rewrite before clarifying its value risks substantial effort on an uncertain initiative.

Question 6

New Multiple answers

Topic: Managing Products with Agility:; Product Backlog Management, Stakeholders & Customers.

Skill tested: Improves stakeholder collaboration while preserving Product Owner accountability for value decisions.

A public-sector product has several stakeholder groups with conflicting needs. The Product Owner receives requests through separate email chains and has difficulty distinguishing regulatory obligations from preferences. Developers often begin work before examples and acceptance expectations are understood, causing rework. The Product Owner wants a better way to engage stakeholders without turning the team into a committee or promising every request. Which two actions are most appropriate? Select TWO.

Correct Answer: A. Collaborate with stakeholders to clarify desired outcomes and constraints, then have the Product Owner make transparent ordering decisions.; B. Create regular opportunities for relevant stakeholders and the Scrum Team to inspect product outcomes and discuss emerging needs.
Explanation:

Regular collaboration gives stakeholders a useful route to share evidence and inspect outcomes, while clarifying outcomes and constraints helps reduce rework. The Product Owner remains accountable for Product Backlog ordering and can make decisions transparent without promising every request. A senior stakeholder veto converts product decisions into approval bureaucracy. Developers should not accept requests directly into the Sprint Backlog, and freezing the Product Backlog prevents adaptation to changing needs.

Question 7

New Single answer

Topic: Developing and Delivering Products Professionally:; Managing Technical Risk.

Skill tested: Uses incremental integration and a Definition of Done to reduce technical delivery risk.

A team is building a service that must exchange data with a partner system. The partner provides a test environment, but access is intermittent. Historically, the team has postponed integration until the final week of a release, when interface mismatches have caused major delays. The next release has a fixed external commitment, and adding a dedicated integration phase is not possible. Which approach best reduces the technical risk while preserving Scrum's incremental delivery?

Correct Answer: A. Integrate and test the partner interface as early and frequently as feasible, making integration work part of the Definition of Done.
Explanation:

Early, frequent integration exposes interface mismatches while there is still time to adapt and supports a usable Increment each Sprint. Including integration in the Definition of Done makes the quality expectation transparent and avoids treating a risky, essential activity as later work. A final hardening phase recreates the known failure pattern. Product Owner acceptance cannot make an unintegrated Increment Done, and a separate team working only after Sprints delays feedback and increases handoff risk.

Question 8

New Multiple answers

Topic: Developing and Delivering Products Professionally:; Managing Technical Risk.

Skill tested: Identifies practices that make quality and technical debt visible during iterative development.

A team delivers features quickly, but its production defect rate is rising. Developers have been bypassing automated checks under schedule pressure, and the Product Owner has accepted work that still requires manual regression testing. The organization will not add a separate testing department or extend Sprint timeboxes. The team wants to make quality sustainable while still delivering valuable functionality. Which two actions best address the underlying risk? Select TWO.

Correct Answer: A. Make technical debt and quality improvement work visible in Product Backlog discussions and account for it in product decisions.; D. Strengthen the Definition of Done to include the agreed quality checks required for a usable Increment.
Explanation:

An agreed Definition of Done makes the quality bar transparent and prevents incomplete work from being treated as a usable Increment. Making technical debt and quality needs visible supports informed Product Backlog decisions and helps the team address accumulating risk. Allowing exceptions hides quality gaps, while a separate testing Sprint delays feedback and conflicts with the constraint. The Scrum Master is not a substitute quality gate; Developers remain responsible for creating a Done Increment.

Question 9

New Single answer

Topic: Evolving the Agile Organization:; Organizational Design & Culture

Skill tested: Addresses organizational dependencies that prevent cross-functional teams from delivering usable Increments.

A company formed Scrum Teams around business features, but every team must request database changes from a centralized operations group. The operations group works from a quarterly queue, so completed feature work often waits several Sprints before it can be released. Management says the separate group must remain for regulatory control, and changing reporting lines is not currently possible. The organization wants to improve flow without weakening required controls. What should the Scrum Master do first?

Correct Answer: C. Help the teams and operations group visualize the dependency and collaborate on reducing its delay while preserving the required controls.
Explanation:

The organization's structure is creating a delivery dependency, so making its impact visible and collaborating on a safer, faster way of working is a practical first step. The solution can address handoffs and flow while respecting regulatory controls and current reporting constraints. Bypassing required controls is not acceptable, and simply moving work into a Product Backlog does not grant the team the necessary authority or expertise. Planning further ahead does not remove the queue or improve responsiveness.

Question 10

New Single answer

Topic: Evolving the Agile Organization:; Organizational Design & Culture

Skill tested: Promotes an organizational culture that supports learning rather than individual blame.

After a failed release, executives demand that the Scrum Master identify which Developer caused the defect. The defect passed through several handoffs, and the team's Retrospective has not yet occurred. Executives need accountability and a credible plan to reduce recurrence, but public blame has previously caused people to hide problems. What should the Scrum Master do?

Correct Answer: A. Support a blameless examination of the system and contributing conditions, then help the team and organization agree on measurable improvements.
Explanation:

A learning-oriented response investigates how the defect passed through the system, identifies contributing conditions, and turns findings into improvements. This supports transparency and accountability without encouraging concealment. Naming an individual prematurely promotes blame and adds approval gates without addressing root causes. Collective responsibility does not remove the need to investigate or act. The Scrum Master can communicate promptly with executives while also ensuring the team conducts a constructive Retrospective.

Question 11

New Multiple answers

Topic: Understanding and Applying the Scrum Framework:; Empiricism, Scrum Values, Scrum Team, Events, Artifacts, Done.

Skill tested: Applies Sprint Goal and Sprint Backlog principles when new work threatens the Sprint outcome.

Midway through a Sprint, an executive asks the Developers to add an urgent analytics request. The request is valuable, but the current Sprint Goal remains achievable only if the team protects its planned capacity. The Product Owner is available, and the Developers believe there may be a way to renegotiate scope without jeopardizing the goal. The executive expects an immediate commitment, but the team must not reduce quality or treat the Sprint Backlog as fixed regardless of new information. Which two actions are appropriate? Select TWO.

Correct Answer: C. Have the Developers and Product Owner collaborate to clarify the request and negotiate Sprint Backlog scope while protecting the Sprint Goal.; E. Keep the Sprint Goal and Definition of Done, and let the Developers adapt their plan as they learn.
Explanation:

The Sprint Backlog is updated by the Developers as they learn, and scope can be clarified and renegotiated with the Product Owner without endangering the Sprint Goal. Maintaining the Definition of Done protects quality. An executive cannot unilaterally add work to the Sprint Backlog, and a valuable new request does not automatically require canceling the Sprint; cancellation is reserved for when the Sprint Goal becomes obsolete and is the Product Owner's decision. Overtime is neither a reliable nor sustainable way to preserve scope.

Question 12

New Single answer

Topic: Developing People and Teams:; Self-Managing Teams, Facilitation, Leadership Styles, Coaching and Mentoring.

Skill tested: Uses coaching questions to help Developers improve forecasting without imposing individual performance targets.

A team's Sprint forecasts vary significantly, and a director proposes measuring each Developer by completed story points. The Developers say that estimates are being used to compare people, so they have started padding estimates and avoiding uncertain work. The director needs more reliable planning information, but the organization wants to preserve collaboration and learning. What should the Scrum Master do?

Correct Answer: D. Coach the director on the misuse of estimates and facilitate a team discussion about forecasting, uncertainty, and improvements to its planning.
Explanation:

Forecasts are planning aids, not individual performance measures. Comparing Developers through story points encourages gaming and discourages collaboration, exactly as the scenario shows. Coaching the director and facilitating a discussion helps restore a shared understanding of uncertainty and supports the team in improving its own forecasting. Individual targets reinforce the harmful incentive; the Product Owner does not control estimates; and the Scrum Master should not take ownership of the Developers' estimation and planning.