Question 1
Topic: Understanding and Applying the Scrum Framework:; Empiricism, Scrum Values, Scrum Team, Events, Artifacts, Done.
Skill tested: Applies empiricism and transparency when a Scrum Team faces unreliable progress information.
A product team has repeatedly reported that its Sprint Goal is on track, but integration failures discovered near the end of each Sprint have prevented usable Increments. The Developers say the failures cannot be predicted and want to keep reporting progress based on completed coding tasks. The Product Owner needs credible information to make release decisions, and the organization will not add a separate testing phase after each Sprint. What should the Scrum Master do first?
Empiricism depends on transparency, inspection, and adaptation. If integration work is hidden from the Definition of Done or progress view, stakeholders cannot make informed decisions and the team cannot inspect its actual delivery capability. The Scrum Master should facilitate transparency around what qualifies as Done and support the team in examining and adapting its work. Extending a Sprint changes its fixed timebox; a separate testing Sprint preserves the late discovery problem; and having the Scrum Master estimate work undermines the Developers' ownership of the plan.