Free Scrum Professional Scrum Product Owner II PSPO-II Exam Questions

Last updated: · 15 practice questions with answers and explanations

Page: 1 / 10 Total 92 questions

Want more questions? Get Premium Access.

Question 1

New Single answer

Topic: Understanding and Applying the Scrum Framework

Skill tested: Uses Scrum accountabilities and events to improve transparency and adaptation.

A product team regularly discovers during the Sprint Review that stakeholders expected capabilities different from those the Developers delivered. The Product Owner has been prioritizing the Product Backlog, but stakeholders rarely see working product until the review. The organization is considering adding a formal approval meeting before every Sprint so that expectations are fixed in advance. The team needs to improve feedback without weakening the Scrum framework or turning the Sprint into a sequence of approvals. What is the most appropriate response?

Correct Answer: B. Increase collaboration with stakeholders throughout product development and use the Sprint Review to inspect the outcome and adapt what to do next.
Explanation:

Scrum relies on transparency, inspection, and adaptation; ongoing stakeholder collaboration helps expose assumptions earlier, while the Sprint Review provides a working session for inspecting the outcome and adapting future direction. A pre-Sprint approval gate does not substitute for empirical feedback. The Scrum Master does not approve Product Backlog items, and stakeholders do not approve the Sprint Backlog. A Sprint Review is not merely a presentation controlled by the Product Owner; it is an opportunity for the Scrum Team and stakeholders to collaborate on what to do next.

Question 2

New Multiple answers

Topic: Understanding and Applying the Scrum Framework

Skill tested: Applies empiricism and self-management when responding to emerging Sprint work.

Midway through a Sprint, a new legal requirement makes a product change urgent. The Product Owner believes the change may be more valuable than the current Sprint Goal, while the Developers have begun work on several Sprint Backlog items. No work has yet been released, and the team can discuss the impact immediately. Which TWO actions best reflect Scrum while addressing the new information? Select TWO answers.

Correct Answer: B. The Product Owner and Developers discuss scope adjustments that preserve the Sprint Goal where possible.; D. The Scrum Team assesses whether the Sprint Goal has become obsolete; if so, the Product Owner may cancel the Sprint.
Explanation:

The Sprint Backlog is an evolving plan, so the Product Owner and Developers can negotiate scope changes that do not endanger the Sprint Goal. If new information makes the Sprint Goal obsolete, the Product Owner is the only person who can cancel the Sprint. The Product Owner does not assign Developers work, and Developers should not ignore relevant evidence simply because a Sprint is underway. The Scrum Master supports the framework but does not make product-priority decisions.

Question 3

New Single answer

Topic: Understanding and Applying the Scrum Framework

Skill tested: Distinguishes the accountabilities and purpose of Scrum events.

A newly formed Scrum Team holds Daily Scrums that last 45 minutes. Each Developer reports status to the Product Owner, who then assigns the next day's tasks. Developers say the meeting helps the Product Owner track progress but does little to help them coordinate. The team must retain daily inspection and adaptation while improving self-management; the organization also wants visibility into progress. What should the Scrum Master coach the team to do?

Correct Answer: A. Have the Developers use the Daily Scrum to inspect progress toward the Sprint Goal and adapt their plan for the next day.
Explanation:

The Daily Scrum is an event for Developers to inspect progress toward the Sprint Goal and adapt their plan, not a status report to the Product Owner or a task-assignment meeting. The Developers decide how to structure the event, provided it serves its purpose and stays within its timebox. A weekly report reduces the frequency of inspection, while a meeting at the end of the Sprint cannot support daily adaptation. Product progress can be made transparent without turning the event into managerial oversight.

Question 4

New Single answer

Topic: Understanding and Applying the Scrum Framework

Skill tested: Applies the Definition of Done to increment quality and product release decisions.

A team has agreed on a Definition of Done that includes automated regression tests, security review, and integration into the product. Near the end of the Sprint, one feature meets its acceptance criteria and passes unit tests, but its security review is pending and it has not been integrated. A stakeholder needs to see evidence of progress before a funding discussion. The Product Owner asks whether the feature can be counted as part of the Increment if it is clearly labeled unfinished. What is the best response?

Correct Answer: A. Treat it as not Done, keep it out of the Increment, and return it to the Product Backlog for future consideration.
Explanation:

The Definition of Done establishes the quality state required for work to be part of the Increment. Since integration and security review remain incomplete, the feature is not Done and cannot be represented as part of a Done Increment. Acceptance criteria do not replace the Definition of Done, and stakeholder acceptance cannot waive the team's quality standard. The Scrum Master has no authority to waive it. The team can still communicate progress transparently without misrepresenting incomplete work as Done.

Question 5

New Multiple answers

Topic: Understanding and Applying the Scrum Framework

Skill tested: Uses Sprint Retrospective outcomes to make inspectable process improvements.

A Scrum Team has held several Retrospectives, but identified improvements rarely happen because they are recorded in meeting notes and quickly forgotten. The Developers say they do not want a separate improvement project that competes with product work. The Product Owner wants the team to make meaningful changes while maintaining focus on the product goal. Which TWO approaches are most appropriate? Select TWO answers.

Correct Answer: B. Select a small number of improvements and make their progress visible during subsequent Sprints.; E. Include a sufficiently important improvement in the Sprint Backlog so the team can act on it during the Sprint.
Explanation:

A Retrospective should lead to actionable improvements, and making progress visible helps the team inspect whether changes are effective. A sufficiently important improvement can be included in the Sprint Backlog, balancing product work with the team's need to improve. The Product Owner does not assign work to Developers, and improvement does not need to be postponed to a separate Sprint. Stopping Retrospectives or awaiting a special budget undermines continuous improvement and does not address why actions are being forgotten.

Question 6

New Single answer

Topic: Professional Scrum Competency

Skill tested: Connects product vision to customer outcomes and strategic direction.

A company is investing in a product for small retailers. Executives have described the vision as "become the most innovative platform," while teams receive quarterly lists of features to build. Customer interviews show retailers chiefly need to reduce the time spent reconciling sales across channels. The organization wants a vision that guides Product Backlog decisions yet does not prescribe a fixed solution or guarantee delivery dates. What should the Product Owner do?

Correct Answer: D. Frame the vision around the target customers, the problem to solve, and the outcome the product seeks to create.
Explanation:

A useful product vision communicates whom the product serves, what important need it addresses, and the intended value or outcome. It gives teams and stakeholders a shared direction while leaving room to discover the best solution. A feature list or fixed release plan is not a vision and can constrain learning. Waiting for complete validation deprives the organization of strategic direction; prescribing architecture confuses a product outcome with an implementation decision.

Question 7

New Multiple answers

Topic: Professional Scrum Competency

Skill tested: Uses outcome evidence and stakeholder insight to order Product Backlog work.

A Product Owner is deciding between three proposed Product Backlog items. A high-profile stakeholder requests a dashboard, several customers request an export feature, and discovery evidence suggests that reducing onboarding failures could materially improve customer retention. The team has capacity for only one of these items in the next Sprint, and the product strategy prioritizes sustained customer adoption. Which TWO practices best support a value-based decision? Select TWO answers.

Correct Answer: A. Compare the expected contribution of each item to the product goal and customer outcomes.; C. Use relevant customer and product evidence to inform the ordering, while recognizing uncertainty.
Explanation:

Product Backlog ordering should support the product goal and maximize value, using available evidence about customers, outcomes, risk, and uncertainty. Comparing the expected contribution of the alternatives and incorporating relevant customer and product data makes the decision more defensible while preserving room to learn. Seniority alone is not a measure of value, and a vote count can hide differences in customer impact. Splitting work does not create capacity or justify an incoherent Sprint Goal.

Question 8

New Single answer

Topic: Professional Scrum Competency

Skill tested: Forecasts product delivery using historical evidence and explicit uncertainty.

A leadership team asks a Product Owner to promise an exact date for a set of capabilities needed for a market campaign. The Developers have completed several Sprints, but item sizes vary and new customer feedback may change the Product Backlog. Leadership will accept a range and wants assumptions stated, but it needs a useful forecast soon. Which approach is most appropriate?

Correct Answer: C. Use empirical delivery evidence to create a forecast range, explain assumptions and uncertainty, and update it as new information emerges.
Explanation:

A forecast should be grounded in empirical evidence and communicate uncertainty, assumptions, and the conditions that could change the outcome. It can be updated as the Product Backlog and delivery evidence evolve. A single deterministic calculation hides variability, and requiring a perfectly stable backlog is unrealistic in product development. Promising a date and relying on overtime turns an uncertain forecast into a commitment unsupported by evidence and may damage sustainable delivery.

Question 9

New Multiple answers

Topic: Professional Scrum Competency

Skill tested: Improves backlog transparency through refinement, value context, and usable item detail.

A distributed Scrum Team repeatedly selects Product Backlog items at Sprint Planning that turn out to be too large or poorly understood. Stakeholders also struggle to see why particular items are near the top of the backlog. The Product Owner wants to improve readiness for planning without introducing a mandatory sign-off gate or treating estimates as commitments. Which TWO actions are most appropriate? Select TWO answers.

Correct Answer: A. Make the ordering and relevant value rationale transparent to stakeholders and the Scrum Team.; B. Collaborate with the Developers to decompose and clarify items as needed, while keeping refinement ongoing.
Explanation:

Product Backlog refinement is an ongoing activity in which the Product Owner and Developers clarify and decompose items as useful, improving understanding for future planning. Making ordering and value rationale transparent helps stakeholders understand why items are prioritized without creating a formal approval gate. Estimates support planning but are not promises. The Scrum Master does not approve backlog items, freezing the backlog prevents adaptation, and task assignment belongs to Developers rather than the Product Owner.

Question 10

New Single answer

Topic: Professional Scrum Competency

Skill tested: Manages stakeholder disagreement through transparent goals and product evidence.

Two departments fund a shared product. One wants an advanced reporting capability for a small group of strategic accounts; the other wants improvements to a common workflow used by most customers. Both claim their request is urgent, and the Product Owner cannot satisfy both in the next release. The product has a published goal focused on reducing customer effort, but the evidence for the two requests is incomplete. What should the Product Owner do first?

Correct Answer: C. Bring the stakeholders together around the product goal, make the trade-offs and uncertainty transparent, and seek evidence relevant to customer value.
Explanation:

The Product Owner is accountable for maximizing product value and should use the product goal and relevant evidence to make trade-offs transparent. Bringing stakeholders into a conversation about outcomes and uncertainty can clarify impact and improve the decision, without transferring accountability to them. Budget size alone is not a reliable proxy for customer value. An arbitrary split can dilute focus, while the Scrum Master facilitates Scrum and does not decide product priorities.

Question 11

New Single answer

Topic: Professional Scrum Competency

Skill tested: Balances release risk, stakeholder expectations, and empirical product learning.

A Product Owner is planning a release for a regulated service. A sales team wants a large launch after all planned features are complete, while customer support reports that a smaller set of changes could already resolve the most common user problem. The organization can deploy safely in increments, but each release requires coordinated customer communication. There is no contractual requirement to wait for the full feature set. Which release approach best supports value and learning?

Correct Answer: D. Release the smallest valuable, Done increment when appropriate, observe its impact, and use evidence to inform subsequent decisions.
Explanation:

A valuable Done increment can be released when appropriate; releasing earlier can address a real customer problem and provide evidence for subsequent decisions. Incremental release does not require abandoning coordination or regulatory controls, which remain relevant. Waiting for the entire roadmap delays value and learning without a stated need. Releasing work that is not Done risks quality and trust, and sales may contribute communication needs but does not own the Product Owner's product decisions.

Question 12

New Single answer

Topic: Professional Scrum Competency

Skill tested: Uses customer discovery to validate product assumptions before scaling investment.

A team has built a prototype for a new subscription feature after executives expressed confidence that customers would pay for it. Early usability sessions show customers understand the feature, but none of the sessions tested willingness to pay. The next phase would require a substantial investment and could displace work on the existing product goal. Executives want a decision this month. What is the most appropriate next step?

Correct Answer: A. Run focused discovery that tests the key willingness-to-pay assumption, then use the evidence to decide whether to continue, adapt, or stop.
Explanation:

Usability evidence shows that participants can understand or use a concept; it does not establish willingness to pay. Since the investment is substantial and competes with existing product work, the Product Owner should identify and test the riskiest assumption before scaling. Positive usability alone does not validate the business model. Executive sponsorship is relevant context but does not prove value, and sunk effort in a prototype is not evidence that the opportunity is viable.

Question 13

New Multiple answers

Topic: Professional Scrum Competency

Skill tested: Aligns product measures with value outcomes and Evidence-Based Management.

A product leadership group reports success using the number of features shipped and the percentage of planned work completed. The product has recently increased its release frequency, but customer retention has declined and support demand has risen. The organization wants to assess whether the product is creating value rather than merely delivering output. Which TWO measurement changes are most appropriate? Select TWO answers.

Correct Answer: B. Track relevant customer and business outcome trends, such as retention or successful customer behavior, alongside delivery measures.; E. Use evidence to identify hypotheses about the decline and inspect whether changes improve outcomes over time.
Explanation:

Evidence-Based Management distinguishes output from outcomes and encourages using measures of current value and the ability to create future value. Tracking customer and business outcome trends makes the product's impact more visible; investigating evidence and inspecting the results of changes supports learning. Individual utilization is a poor proxy for product value and can encourage local optimization. Feature counts demonstrate output, not benefit, and waiting for a stable market forfeits useful evidence.

Question 14

New Single answer

Topic: Professional Scrum Competency

Skill tested: Shapes organizational design around empowered, cross-functional product teams.

A company organizes its product work into separate analysis, development, testing, and deployment departments. Each department optimizes its own queue, so Product Backlog items often wait between handoffs and teams cannot deliver a usable Increment within a Sprint. Leaders propose adding a coordination office to schedule handoffs more tightly. The company wants to improve end-to-end flow without losing specialist expertise. What is the most appropriate organizational change?

Correct Answer: C. Create stable, cross-functional Scrum Teams with the skills needed to create a Done Increment and let them manage their work.
Explanation:

Stable, cross-functional teams reduce dependencies and handoffs by bringing the capabilities needed to create a Done Increment together. Specialists can retain and develop expertise while collaborating within teams. A coordination office may make queues more visible but does not remove the structural delays or support self-management. Separate testing Sprints delay feedback, and utilization reporting can encourage departmental optimization rather than improving end-to-end product flow.

Question 15

New Multiple answers

Topic: Professional Scrum Competency

Skill tested: Uses portfolio evidence to make strategic investment and product continuation decisions.

An organization has more product initiatives than its teams can support. Several initiatives have been funded for years, but their customer outcomes are unclear. Executives want to preserve strategic focus, avoid starting more work, and make investment decisions using evidence rather than sunk costs. Which TWO actions best support these aims? Select TWO answers.

Correct Answer: A. Limit work in progress by making explicit choices about which initiatives to start, continue, pause, or stop.; D. Review portfolio initiatives against strategic outcomes and current evidence, including whether continued investment remains justified.
Explanation:

Portfolio decisions should continually align investment with strategy and evidence about outcomes, rather than treating past spending as a reason to continue. Explicitly limiting work in progress helps focus capacity and may require pausing or stopping initiatives. Completing original scope regardless of current value is a sunk-cost response. Team count does not establish strategic value, and equal allocation can spread capacity too thinly to produce meaningful outcomes.