Free ScrumStudy Scrum Master Certified (SMC) SMC Exam Questions

Last updated: · 10 practice questions with answers and explanations

Page: 1 / 10 Total 100 questions

Want more questions? Get Premium Access.

Question 1

New Single answer

Topic: Agile Overview

Skill tested: Apply Agile values and principles when balancing delivery, customer feedback, and changing requirements.

A company is developing a compliance portal for several regional customers. The initial contract describes a fixed set of features, but regulatory interpretations are changing during development and customer representatives can review working increments every few weeks. Executives want reliable progress reporting, while the delivery group is concerned that strict adherence to the original feature sequence will produce unusable work. The organization cannot pause delivery until every requirement is settled. Which approach best reflects Agile values and principles while maintaining responsible planning?

Correct Answer: B. Deliver usable increments frequently, use customer feedback to reprioritize remaining work, and retain enough planning to communicate forecasts and risks.
Explanation:

Frequent delivery of usable increments and ongoing customer collaboration let the organization respond to regulatory learning while validating value early. Agile does not reject planning, documentation, or agreements; it values working software and responsiveness without eliminating those supporting practices. Freezing requirements, as in A, treats the initial plan as more important than changing needs. C misrepresents Agile as having no documentation or forecasting. D delays feedback and increases the risk that the delivered solution no longer fits customer needs.

Question 2

New Single answer

Topic: Scrum Overview

Skill tested: Use empiricism and Scrum events to inspect progress and adapt plans within a Sprint.

A product team has agreed on a Sprint Goal, but midway through the Sprint the Product Owner learns that a proposed regulatory change may affect a high-priority backlog item. The change is not yet confirmed, and the team has already selected work based on the current Product Backlog. The Product Owner asks the Scrum Master to add a daily approval meeting where executives can direct individual Developers to change tasks. The team must preserve focus while remaining responsive to meaningful new information. What is the most appropriate response?

Correct Answer: A. Keep the Sprint Goal and selected work stable, clarify the uncertainty with stakeholders, and adapt the Product Backlog for future planning as appropriate.
Explanation:

Scrum uses transparency, inspection, and adaptation. The Product Owner can investigate the potential change and update the Product Backlog, while the Developers maintain focus on the Sprint Goal and manage their own work. A gives executives control over Developers' task assignments and incorrectly assigns coordination authority to the Scrum Master. C is not justified by an unconfirmed change; Sprint cancellation is for when the Sprint Goal becomes obsolete. D blocks useful collaboration and delays learning unnecessarily.

Question 3

New Multiple answers

Topic: Scrum Roles

Skill tested: Distinguish Product Owner, Scrum Master, and Developers' accountabilities in backlog and Sprint work.

A product group is reorganizing after several releases missed customer expectations. The Product Owner is accountable for maximizing product value, but asks the Scrum Master to rank backlog items because the Scrum Master has the most meeting experience. A functional manager also wants to assign individual Developers' tasks during the Daily Scrum to improve utilization. The Scrum Team has three weeks before the next planning cycle to clarify its working agreements and decision rights. Which TWO actions best align with Scrum accountabilities? Select TWO.

Correct Answer: B. Have Developers decide how to turn selected Product Backlog items into a usable Increment and organize their work.; D. Have the Product Owner order Product Backlog items to best support product value, using stakeholder input and evidence.
Explanation:

The Product Owner is accountable for effective Product Backlog management, including ordering items to maximize value. Developers are accountable for creating a usable Increment and organize the work needed to meet the Sprint Goal. The Scrum Master supports Scrum effectiveness but does not take over product decisions or assign tasks. A manager may provide input, but requiring approval for every backlog change undermines the Product Owner's accountability. Likewise, temporary unavailability does not transfer the Product Goal to the Scrum Master.

Question 4

New Single answer

Topic: Scrum Roles

Skill tested: Select Scrum Master interventions that remove impediments without directing the Developers' technical work.

During a Sprint, a software team cannot access a shared test environment because another department controls provisioning. Developers have identified a workaround that would create a separate, costly environment, but they have not assessed its security implications. The Product Owner asks the Scrum Master to tell the Developers which workaround to implement so the Sprint Goal remains achievable. The team needs the blockage addressed quickly, but the Scrum Master is not the technical decision-maker. What should the Scrum Master do first?

Correct Answer: C. Escalate the access dependency to the responsible department, facilitate resolution, and support the Developers in evaluating safe options.
Explanation:

The Scrum Master helps remove impediments and enables the Scrum Team to work effectively, while Developers determine how to build the Increment. Addressing the organizational dependency and facilitating a safe technical assessment respects those accountabilities and the security concern. A puts the Scrum Master in the role of technical director and postpones risk assessment. C makes a unilateral scope change without assessing its impact on the Sprint Goal. D creates an unnecessary authority layer and does not resolve the department's provisioning dependency.

Question 5

New Single answer

Topic: Scrum Phases

Skill tested: Facilitate Initiate activities by establishing product direction, stakeholders, and the initial Product Backlog.

A startup has approved funding for a new subscription service, but its executives disagree about the primary customer segment and success measures. A vendor is ready to begin a large implementation based on a preliminary feature list. The organization wants to use Scrum and has only a short window before committing substantial development capacity. It needs enough shared direction to begin product work without pretending that every requirement is already known. Which Initiate-phase action is most appropriate?

Correct Answer: B. Align key stakeholders on the product vision and initial goals, identify the Product Owner, and create an initial ordered Product Backlog for refinement.
Explanation:

Initiation should establish a coherent product direction, clarify key stakeholders and ownership, and provide an initial Product Backlog that can be refined as learning occurs. This gives the team enough alignment to start without requiring a complete specification. A delays collaboration and assumes requirements can be made fixed in advance. C assigns product-direction decisions to Developers without alignment. D improperly makes the Scrum Master accountable for commercial priorities and backlog decisions that belong with the Product Owner and relevant stakeholders.

Question 6

New Multiple answers

Topic: Scrum Phases

Skill tested: Apply Plan and Estimate practices to refine backlog items and prepare a credible Sprint plan.

A financial-services team is preparing for its next Sprint. Several highly ranked Product Backlog items still have unclear acceptance expectations, a dependency on an external fraud-detection service, and effort estimates that vary widely. The team must maintain a usable Increment and has limited capacity for work that depends on the external provider. The Product Owner wants a forecast, but the team does not want to treat estimates as guarantees or select work it cannot reasonably complete. Which TWO actions best support effective Plan and Estimate work? Select TWO.

Correct Answer: A. Estimate the work collaboratively, make dependencies visible, and select a feasible amount of work in light of capacity and the Sprint Goal.; B. Refine the candidate items with the Product Owner to improve clarity and split work where useful before selecting Sprint work.
Explanation:

Refinement improves shared understanding and can split overly large items into manageable work. Collaborative estimation and transparent dependencies help the Developers make a realistic Sprint forecast that supports a Sprint Goal and accounts for capacity. B creates an unreliable plan by ignoring a known dependency. D makes the Scrum Master responsible for estimates and individual commitments rather than enabling Developers to plan their work. E is unnecessarily restrictive: uncertainty can be managed through refinement, ordering, and explicit risk awareness rather than removing valuable work entirely.

Question 7

New Single answer

Topic: Scrum Phases

Skill tested: Use the Sprint Review to inspect outcomes with stakeholders and adapt the Product Backlog.

A team has completed a Sprint and produced an Increment that meets its Definition of Done. Several stakeholders have not attended the last two Sprint Reviews, and the Product Owner is considering replacing the next review with a slide presentation to senior management. The product serves users in a rapidly changing market, and the team needs timely feedback on an important workflow before ordering upcoming work. What is the best approach for the next Review and Retrospect phase?

Correct Answer: D. Use the Sprint Review to inspect the Increment with relevant stakeholders, discuss market changes, and adapt the Product Backlog; then hold a separate Retrospective for team improvement.
Explanation:

The Sprint Review is a collaborative opportunity to inspect the outcome with stakeholders and consider changes in the environment, then adapt the Product Backlog. A demonstration or presentation alone does not provide the same inspect-and-adapt collaboration. The Retrospective has a different purpose: the Scrum Team inspects how it worked and identifies improvements. A delays valuable feedback; C misuses the Review for individual appraisal; and D confuses the purposes of the Review and Retrospective.

Question 8

New Single answer

Topic: Scaling Scrum

Skill tested: Coordinate cross-team dependencies through Scrum of Scrums without transferring team-level accountability.

Four Scrum Teams are building parts of a shared customer platform. A dependency between the identity service and two consuming applications has repeatedly surfaced late in Sprints, creating integration delays. Each team already holds its own Daily Scrum, and executives propose a large daily meeting where every Developer reports task status to a program manager. The organization wants faster coordination while preserving team autonomy and keeping the discussion focused on cross-team work. What is the most appropriate next step?

Correct Answer: B. Establish a Scrum of Scrums with appropriate representatives to coordinate cross-team dependencies, impediments, and integration concerns.
Explanation:

A Scrum of Scrums provides a coordination forum for representatives to discuss issues that cross team boundaries, such as the identity integration dependency. It complements rather than replaces each team's own Daily Scrum and should focus on integration, dependencies, and impediments rather than individual task reporting. A increases status overhead and displaces team-level events. C gives one Scrum Master authority over other teams' Developers. D postpones inspection of a recurring dependency until too late to coordinate effectively.

Question 9

New Multiple answers

Topic: Scaling Scrum

Skill tested: Align portfolio governance and stakeholder involvement with iterative product delivery and executive support.

A large organization is transitioning several business units from annual project funding to a portfolio of products delivered by multiple Scrum Teams. Executives want continued visibility into strategic alignment and investment decisions, while teams need to deliver increments without waiting for a complete annual specification. Stakeholders currently receive updates only at quarterly steering meetings, and funding decisions are disconnected from evidence about product outcomes. Which TWO changes best support a Scrum-aligned transition and ongoing stakeholder involvement? Select TWO.

Correct Answer: A. Engage executives and stakeholders regularly around product goals, outcomes, and impediments while allowing Product Owners to manage their Product Backlogs.; B. Use periodic portfolio reviews to compare product outcomes and strategic alignment, adjusting investment as evidence emerges.
Explanation:

Portfolio-level inspection of outcomes and strategic alignment allows investment to adapt to evidence rather than relying only on annual estimates. Regular stakeholder and executive engagement can clarify goals, surface organizational impediments, and sustain support, while Product Owners retain responsibility for ordering their Product Backlogs. B extends governance into Developers' Sprint-level work and creates approval delays. D preserves a plan-driven fixed-scope model that conflicts with iterative adaptation. E removes useful strategic alignment and executive support rather than making governance responsive.

Question 10

New Single answer

Topic: Scaling Scrum

Skill tested: Plan a Scrum transition by mapping existing managers to appropriate support and product accountabilities.

A company is moving from functional departments to cross-functional Scrum Teams. Department managers currently assign specialists to projects, approve technical work, and conduct performance reviews. During the transition, executives want to retain useful people-management responsibilities but avoid creating a parallel chain of command that directs Sprint work. The teams need stable access to skills, while Product Owners must remain able to make product decisions. Which transition approach is most appropriate?

Correct Answer: A. Clarify that managers support people, capability development, and organizational conditions, while Product Owners order product work and Developers manage Sprint execution.
Explanation:

A transition does not require every traditional role to disappear, but accountabilities must be clarified. Managers can support people development, staffing capability, and organizational conditions without directing Sprint work. Product Owners remain accountable for product value and backlog ordering; Developers decide how to accomplish the work. A turns managers into task assigners and misuses the Scrum Master role. B combines unrelated management and product decision rights. D removes important organizational responsibilities rather than mapping them appropriately.