Limited-Time Offer: Enjoy 50% Savings! Ends in 00h 00m 00s Coupon code: 50OFF
Skip to content

Free ScrumStudy Scrum Master Certified (SMC) SMC Exam Questions

Page: 1 / 10 Total 100 questions

Want more questions? Get Premium Access.

Question 1

Which of the following is NOT a core dimension of collaborative work?

Correct Answer: D. Team members working in sub groups so that a competitive environment is maintained among the groups.

Question 2

Which of the following statements is NOT true of an Impediment Log?

Correct Answer: B. Internal impediments from within the team are never recorded in the Impediment Log, and only brought up during the Daily Standups.
Explanation:

a-scrum-team/

Question 3

You are a Scrum Master on a project that is preparing to begin its first Sprint. You explain to the Scrum team

the concept of Daily Standup Meetings. You include all of the following points in your introduction to the Daily

Standup Meeting, EXCEPT:

Correct Answer: B. The meeting may be cancelled or delayed if one or more members are not able to attend.

Question 4

While creating the Sprint Backlog, the Scrum Team along with the Scrum Master and Product Owner must

consider which of the following as inputs?

Correct Answer: C. Length of Sprint, Previous Sprint Velocity, Dependencies, Team Calendar.

Question 5

The table given below presents some Scrum roles that play an important part in business justification and their

responsibilities. Choose the option that correctly matches each role in the left hand column to its action in the

right hand column.

Correct Answer: C. I-c, II-d, III-b, IV-a

Question 6

Listed below are some risks and issues that might be encountered during the course of a project. Identify

which of the following are risks (not issues).

A) After extensive training, marketing representatives might still not be ready to take orders after the project is

launched.

B) The painting crew might be delayed due to heavy rain, which could negatively impact the project schedule.

C) Funding was not approved.

D) Requirements, as currently defined, are unclear.

Correct Answer: B. A and C
Explanation:

Risks are potential future events that may or may not occur and would have a negative impact. Issues are problems that have already occurred.

  • A) Marketing representatives might not be ready (RISK): This is a future uncertainty that might happen - it has not occurred yet
  • B) Painting crew might be delayed due to rain (RISK): This is a potential future event (rain) that might impact the schedule - it has not occurred yet
  • C) Funding was not approved (ISSUE): This has already happened - it is a current problem, not a future uncertainty
  • D) Requirements are unclear (ISSUE): This is a current state/problem that exists now, not a potential future event

Only A and B represent risks because they are potential events that may occur in the future, whereas C and D are existing issues/problems.

Question 7

Scrum Masters have to solve both internal and external impediments for the Scrum team during the Create

Deliverables process. To do so, they record the impediments in the Impediment Log during

_________________________.

A) Daily Standup Meetings.

B) Sprint Review Meetings.

C) Release Planning Meetings.

D) Sprint Planning Meetings.

Correct Answer: A. A and
Explanation:

Impediments are recorded in the Impediment Log during Daily Standup Meetings. This is when the Scrum Team meets daily to synchronize activities and identify blockers. When team members report what is blocking their progress, the Scrum Master records these impediments in the Impediment Log so they can be tracked and resolved. While impediments may be discussed in other meetings, the Daily Standup is the primary event where impediments are identified and logged on a consistent basis.

Question 8

Collaboration is one of the Scrum principles. Which of the following are the three dimensions of this principle?

Correct Answer: A. Awareness, articulation, and appropriation
Explanation:

:

The core dimensions of collaborative work are as follows:

1. Awareness --- Individuals working together need to be aware of each other's work.

2. Articulation --- Collaborating individuals must partition work into units, divide the units among team

members, and then after the work is done, reintegrate it.

3. Appropriation --- Adapting technology to one's own situation; the technology may be used in a manner

completely different than expected by the designers.


Question 9

Which of the following events does NOT help the Scrum Team in identifying or resolving risks?

Correct Answer: D. Prioritized Product Backlog Review Meeting

Question 10

During a Scrum of Scrums, each Scrum Team representative provides an update on which of the following:

A) What has my team been working on since the last meeting?

B) What will my team do until the next meeting?

C) How many story points has my team completed since the last meeting?

D) What is our team planning on doing that might affect other teams?

Correct Answer: A. A, , and
Explanation:

During a Scrum of Scrums, each Scrum Team representative provides updates on:

  • A) What has my team been working on since the last meeting? - Yes, team updates on completed work and progress
  • B) What will my team do until the next meeting? - Yes, plans and commitments for the next period
  • D) What is our team planning on doing that might affect other teams? - Yes, cross-team dependencies and impacts are critical to discuss in a Scrum of Scrums

C) How many story points has my team completed since the last meeting? - This is NOT typically a focus of Scrum of Scrums. While velocity metrics may be discussed informally, the Scrum of Scrums specifically focuses on inter-team dependencies, blockers, and coordination rather than detailed metrics like story point completion.