Limited-Time Offer: Enjoy 50% Savings! Coupon code: 50OFF Use it at checkout
Skip to content

Free AACE International Planning & Scheduling Professional (PSP) Exam AACE-PSP Exam Questions

Last updated: · 10 practice questions with answers and explanations

Page: 1 / 15 Total 216 questions

Want more questions? Get Premium Access.

Question 1

New Single answer

Topic: Basic Development Scheduling and Planning

Skill tested: Evaluates selecting and validating planning inputs before establishing an integrated schedule.

A manufacturer is preparing a baseline schedule for a facility expansion. Engineering has issued a preliminary equipment list, procurement has supplier lead-time estimates, and construction has provided a sequence based on access areas. The project charter contains a required start-up date, but the owner has not approved the commissioning duration or the operating team's acceptance criteria. The sponsor wants a date-driven schedule issued for funding review next week. Which action is most appropriate before the planner establishes the baseline?

Correct Answer: A. Identify and obtain decisions on the missing scope and planning inputs, validate assumptions with responsible parties, and develop the schedule using the agreed basis.
Explanation:

A schedule basis must be built from sufficiently defined, validated scope and planning inputs, including commissioning duration and acceptance requirements. The planner should make the gaps and decision owners explicit and resolve or formally bound them before baseline approval. Backward-planning from a required date can conceal infeasibility, while documenting unresolved assumptions does not make an incomplete basis reliable. A generic allowance may be useful for early estimating, but it is not a substitute for project-specific scope and validated planning.

Question 2

New Multiple answers

Topic: Basic Development Scheduling and Planning

Skill tested: Assesses translating scope, interfaces, and constraints into a traceable work breakdown structure.

A transit authority is developing a schedule for a station modernization involving civil works, fare systems, communications, and a short operational shutdown. Several contractors will deliver separate work packages, and the authority needs to measure progress consistently without prescribing each contractor's detailed means and methods. The existing scope statement identifies deliverables but mixes permanent works, temporary works, and testing activities. Which actions should the planner take when structuring the schedule? Select TWO.

Correct Answer: C. Organize the work into a deliverable-oriented work breakdown structure, including project management and other required scope elements.; D. Define work packages at a level that supports assignment, estimating, progress measurement, and control, then decompose them into schedule activities as needed.
Explanation:

A deliverable-oriented WBS provides a common scope structure across contractors and should account for the full project scope, including management and temporary or enabling work where applicable. Work packages should be manageable for responsibility assignment, estimating, progress measurement, and control; activities are then developed to describe the work needed to produce those deliverables. Contractor lists can inform lower-level detail but should not define inconsistent top-level scope. Testing should be represented at an appropriate level, not hidden in a single milestone. Activities need not each be WBS elements.

Question 3

New Single answer

Topic: Basic Development Scheduling and Planning

Skill tested: Evaluates distinguishing logical relationships from imposed date constraints in schedule development.

A process plant schedule shows a critical installation activity scheduled to start on a fixed date because a specialist crew is available only during a planned outage. The installation's predecessor is expected to finish three days earlier, but the outage date is also tied to an approved operating plan. The project manager asks the scheduler to preserve the outage date while keeping the network logic useful for forecasting. What is the best treatment?

Correct Answer: C. Retain the valid predecessor logic and document the justified date constraint and its basis, then assess its effect on the forecast and critical path.
Explanation:

The physical or contractual logic should remain represented even when an external operating window imposes a justified date constraint. Retaining both allows the team to see whether the predecessor forecast threatens the outage and to understand the constraint's effect on schedule flexibility. Removing the predecessor hides a real dependency. Applying mandatory constraints broadly can distort the network and mask movement, while changing relationship type without a real technical basis misrepresents the work.

Question 4

New Multiple answers

Topic: Basic Development Scheduling and Planning

Skill tested: Assesses development of realistic activity durations and resource-informed schedule assumptions.

A contractor is preparing a baseline for repetitive pipeline installation across varied terrain. The current draft assigns the same duration to every segment, although access, crew productivity, and inspection requirements differ. Management wants credible activity durations and a transparent basis that can later support schedule updates. The available estimating data include recent project actuals, crew production rates, and preliminary quantities. Which actions are most appropriate? Select TWO.

Correct Answer: C. Estimate durations from quantities and applicable production rates, adjusting for documented segment-specific conditions.; D. Document duration assumptions, sources, and exclusions, and validate them with the organizations responsible for the work.
Explanation:

Quantity-based estimates using relevant production data can produce durations grounded in the work, while segment conditions should be reflected rather than averaged away without justification. Recording the basis and validating it with the responsible parties makes assumptions reviewable and useful during updates. A best-case duration is not a sound default, and fitting durations to a target date reverses the estimating logic. Resource leveling addresses resource conflicts; it cannot validate implausible productivity assumptions.

Question 5

New Single answer

Topic: Basic Development Scheduling and Planning

Skill tested: Evaluates selection of schedule calendars and working-time assumptions for different work scopes.

A building project includes weekday interior fit-out, continuous concrete curing, and a utility tie-in that can occur only during a weekend shutdown. The draft schedule applies one five-day calendar to all activities. The owner needs the forecast to show realistic working dates without creating artificial time for activities that do not stop outside normal shifts. What should the planner do?

Correct Answer: D. Develop and assign calendars that reflect the applicable work patterns and permitted windows, while representing continuous elapsed-time processes appropriately.
Explanation:

Different work scopes can have different working-time rules. Assigning calendars that reflect weekday work, permitted shutdown windows, and continuous elapsed-time processes allows dates to calculate in accordance with the work. A single seven-day calendar overstates working availability for normal crews, while a five-day calendar misrepresents weekend work and continuous processes. A lag is not an appropriate substitute for modeling a required work window, and milestones do not solve activity-calendar differences.

Question 6

New Single answer

Topic: Practical Exercise

Skill tested: Assesses critical-path calculation and identification of total float from a precedence network.

A small project has the following activities and finish-to-start relationships, with no calendars or constraints: A takes 4 days and starts the project; after A, B takes 5 days and C takes 3 days. D takes 4 days and can start only after both B and C finish. E takes 2 days and follows C. Project completion requires both D and E to finish. The planner has calculated an early project duration of 13 days. Which statement correctly describes the critical path and the total float of activity E?

Correct Answer: C. A-B-D controls completion; E has 1 day of total float.
Explanation:

The path through B and D takes 4 + 5 + 4 = 13 days. The path through C and E takes 4 + 3 + 2 = 9 days, but E must finish by the project completion at day 13, so it has four days of float? Consider the network: C finishes at day 7; E finishes at day 9. Its latest finish is day 13, yielding four days of total float. Therefore, the correct answer is D. The D branch controls completion, and E's shorter path has four days of float.

Question 7

New Single answer

Topic: Practical Exercise

Skill tested: Evaluates schedule update calculations using status dates, actuals, and remaining-duration forecasts.

A control schedule is being updated at the end of day 20. Activity P was planned to finish on day 18, started on day 15, and is still in progress; the field team reports that it has 3 working days remaining. Activity Q is a successor to P and has not started; its original duration is 4 working days. The schedule uses finish-to-start logic, no lag, and a five-day working calendar; all stated days are working days. The team wants a status update that reflects actual progress and supports a current forecast. Which update is most appropriate?

Correct Answer: B. Set P's actual start to day 15, leave its actual finish blank, enter 3 days remaining, and recalculate Q from P's forecast finish.
Explanation:

The update should record what occurred and what remains: P has an actual start, no actual finish because it is incomplete, and three working days remaining. The schedule can then calculate P's forecast finish and propagate the finish-to-start relationship to Q. Marking P complete or assigning an actual finish would misstate status. Changing original duration damages the baseline basis, while an invented lag or altered successor duration conceals the actual forecast impact rather than modeling it.

Question 8

New Single answer

Topic: Planning and Scheduling Applications

Skill tested: Assesses diagnosing negative float caused by a required completion constraint and forecast logic.

A project schedule is logically linked and calculates without open ends. Its forecast completion is 12 working days later than a contractual required finish, and the schedule reports 12 days of negative total float on the controlling path. The project director asks the scheduler to remove the negative float before the next review. No scope, logic, or contract dates have changed, and the owner has not approved a revised completion date. What should the scheduler do first?

Correct Answer: A. Preserve the date requirement and validate the status, remaining durations, logic, calendars, and constraint basis to identify the source of the variance.
Explanation:

Negative float communicates that the current forecast cannot meet the imposed required date under the modeled logic and assumptions. The first step is to verify the schedule inputs and determine whether the gap reflects actual delay, incorrect status, unrealistic remaining durations, calendar errors, or an invalid relationship. Adding another constraint or removing the requirement changes the display rather than resolving the condition. Arbitrarily shortening durations creates an unsupported forecast and obscures the recovery work needed.

Question 9

New Single answer

Topic: Planning and Scheduling Applications

Skill tested: Evaluates resource analysis and schedule refinement when competing work exceeds crew availability.

A maintenance program contains several independent work packages that must use the same specialist inspection crew. The current schedule shows overlapping assignments that exceed the crew's capacity, and management requires a feasible forecast. Some work has fixed access windows, while other work can move within the quarter. The planner has verified durations and precedence logic. Which approach is most appropriate?

Correct Answer: A. Apply resource leveling or otherwise sequence flexible work within the crew limit, then review resulting dates and any impact on required access windows and completion.
Explanation:

Resource leveling or a deliberate resource-constrained sequence addresses the actual capacity conflict. Because some work has fixed access windows, the planner must check whether leveling produces infeasible dates and escalate conflicts that cannot be resolved within the available flexibility. Inflating capacity misrepresents the resource, blanket links can impose false technical logic and unnecessary delay, and shortening durations without a productivity basis creates an unreliable plan.

Question 10

New Multiple answers

Topic: Planning and Scheduling Applications

Skill tested: Assesses schedule integration and interface control across related projects and shared milestones.

Two related capital projects share a commissioning team and depend on a common utility energization milestone. Each project maintains its own schedule and reports progress to a joint steering group. Project Alpha's energization forecast has slipped, but Project Beta's schedule still shows the original date and assumes the commissioning team is available immediately afterward. The steering group needs a reliable integrated view without taking ownership of either project's detailed execution schedule. Which actions should the planners take? Select TWO.

Correct Answer: A. Update Beta's dependent dates using the current approved Alpha interface forecast and assess the shared-team demand and resulting impacts.; E. Establish an agreed interface milestone and relationship between the project schedules, with a named owner for maintaining its forecast.
Explanation:

An agreed, controlled interface milestone provides a clear cross-project dependency while preserving each project's detailed schedule ownership. Beta must use the current Alpha forecast as an input and assess the shared commissioning team's availability; otherwise, the integrated outlook remains inconsistent. Combining all detailed activities into one file is unnecessary and can blur accountability. Waiting until actual completion prevents useful forecasting, and fixing a date without supporting evidence hides movement rather than integrating the projects.