Question 1
Topic: Basic Development Scheduling and Planning
Skill tested: Evaluates selecting and validating planning inputs before establishing an integrated schedule.
A manufacturer is preparing a baseline schedule for a facility expansion. Engineering has issued a preliminary equipment list, procurement has supplier lead-time estimates, and construction has provided a sequence based on access areas. The project charter contains a required start-up date, but the owner has not approved the commissioning duration or the operating team's acceptance criteria. The sponsor wants a date-driven schedule issued for funding review next week. Which action is most appropriate before the planner establishes the baseline?
A schedule basis must be built from sufficiently defined, validated scope and planning inputs, including commissioning duration and acceptance requirements. The planner should make the gaps and decision owners explicit and resolve or formally bound them before baseline approval. Backward-planning from a required date can conceal infeasibility, while documenting unresolved assumptions does not make an incomplete basis reliable. A generic allowance may be useful for early estimating, but it is not a substitute for project-specific scope and validated planning.