Free Adobe Workfront Project Manager Certified Professional AD0-E911 Exam Questions

Last updated: · 14 practice questions with answers and explanations

Page: 1 / 10 Total 95 questions

Want more questions? Get Premium Access.

Question 1

New Single answer

Topic: Intake and planning

Skill tested: Maps intake needs to appropriate Workfront objects and reporting views.

A marketing operations team receives campaign requests from several business units. Requesters need to submit a consistent set of details, while project managers need to qualify requests before creating delivery work. The team wants to preserve the original request, track its review separately from project execution, and report on requests by business unit. Which approach best meets these needs?

Correct Answer: A. Create a request queue with an appropriate request form, route submissions for review, and report on the resulting requests.
Explanation:

A Workfront request queue with a request form provides a structured intake path and creates request objects that can be reviewed before the team decides whether to convert or otherwise act on them. Request reporting can group or filter submissions by business unit. Direct project creation bypasses the requested qualification stage, while a task template assumes delivery work already exists. A report can display records but does not provide an intake submission mechanism.

Question 2

New Multiple answers

Topic: Intake and planning

Skill tested: Selects Workfront notification methods appropriate to request and approval events.

A department wants requesters to receive a Workfront notice when their request is converted into a project, and designated reviewers to be alerted when an approval is ready for their action. The organization also wants users to retain their normal personal notification preferences; administrators should not force unrelated notifications on every user. Which two approaches best fit these requirements? Select TWO.

Correct Answer: A. Use an approval process for the review step and configure the appropriate approval-stage notification behavior.; C. Configure the relevant event notifications for users who need those notices, subject to their notification settings.
Explanation:

Event notifications are the appropriate mechanism for notifying users about supported object events, while approval notifications support reviewers when an approval is awaiting action. These approaches target the relevant event without requiring unrelated notification changes for all users. Making everyone a project owner changes responsibilities and access unnecessarily. Dashboards display information but do not, by themselves, generate event alerts. Enabling every notification globally conflicts with the requirement to preserve individual preferences.

Question 3

New Single answer

Topic: Intake and planning

Skill tested: Evaluates custom form field design and reporting suitability for intake data.

A creative services group wants to capture a campaign's sponsoring division, requested launch date, and a brief description on incoming requests. Managers must filter and group request reports by division, while the date must be stored as a date rather than free text. The form should not duplicate fields that already exist as standard Workfront data. What is the best design?

Correct Answer: D. Create a custom form with a text field for division, a date field for launch date, and a text area for the description; attach it to the request intake object.
Explanation:

A custom form attached to the intake object can collect the required request-specific information. A suitable custom field type matters: a date field supports date semantics, and a consistently populated division field can support filtering and grouping in reports. The description belongs in a text area. Capturing data in names or free-text descriptions makes reliable reporting harder, while creating projects at intake would defeat the qualification workflow. Standard fields should be used where they already meet the need.

Question 4

New Single answer

Topic: Intake and planning

Skill tested: Applies Workfront sharing permissions using least-privilege access.

A project manager needs an external agency contact to review a project schedule and add comments, but the contact must not edit tasks, change project settings, or gain access to other projects. The agency contact already has a Workfront account and should have access only to this project. Which action is most appropriate?

Correct Answer: A. Share the specific project with the contact using the least-permissive access level that allows viewing and commenting.
Explanation:

Sharing the individual project provides scoped access, and selecting the least-permissive level that supports viewing and commenting aligns access with the agency's responsibilities. Broad system access and public sharing expose more information than required. Assigning project ownership is unnecessary and may grant duties or capabilities beyond review and comment. Access should be granted at the narrowest relevant object scope.

Question 5

New Multiple answers

Topic: Intake and planning

Skill tested: Locates key project information through Workfront object views and reports.

A portfolio lead needs a repeatable way to review active projects, compare their planned completion dates, and see which project managers own them. The lead also needs to inspect task-level details for a project whose schedule appears delayed. A static spreadsheet is not acceptable because the information changes daily. Which two Workfront approaches best support this review? Select TWO.

Correct Answer: A. Open the project and use its task list or schedule view to investigate task-level dates and assignments.; C. Use a project report with relevant project fields, filters, and groupings for the portfolio-level review.
Explanation:

A project report can present changing project-level fields such as planned completion date and project manager, with filters and groupings suited to portfolio review. To diagnose a particular schedule, the project's task list or schedule view exposes the task-level dates and assignments that contribute to execution. Proof decisions concern proof workflows, not authoritative project scheduling. A form collects or displays configured data but is not a substitute for a report, and a one-time export becomes stale.

Question 6

New Single answer

Topic: Intake and planning

Skill tested: Distinguishes request object configuration from project execution settings.

A project office is standardizing how proposals enter Workfront. An intake queue should collect a business justification and requested delivery date, assign the proposal to the correct review team, and allow reviewers to decide whether the work should become a project. Delivery tasks, predecessors, and project dates should be created only after approval. Which configuration best preserves this separation?

Correct Answer: D. Configure a request queue and request form for proposal details, then use the review workflow before creating delivery work.
Explanation:

A request queue and form are designed to capture and route proposed work before delivery planning. Reviewers can assess the request and determine whether it should proceed; project scheduling can then be established for accepted work. Creating projects for every unapproved proposal blurs intake and execution and generates unnecessary project records. Milestones belong to project schedules, while proofs support review of proof content rather than serving as a general proposal intake workflow.

Question 7

New Single answer

Topic: Execute

Skill tested: Configures project milestones to represent meaningful schedule checkpoints.

A product launch project contains several workstreams with different task sequences. Executives want a consistent way to identify three major checkpoints - requirements approved, pilot completed, and launch authorized - across many projects. The checkpoints must be visible on project schedules, but they should not create artificial work assignments or replace the underlying tasks. What should the project manager configure?

Correct Answer: B. Create milestone paths and associate appropriate milestone tasks with the defined milestones.
Explanation:

Workfront milestones provide named schedule checkpoints, and milestone paths allow those milestones to be represented consistently. Milestones are associated with tasks in the schedule, so the team can retain the actual work while highlighting key events. Assigning executives artificial long-duration tasks misrepresents the work. Project status is not a substitute for several schedule checkpoints, and proof approvals are appropriate when proof content needs review, not for every milestone.

Question 8

New Single answer

Topic: Execute

Skill tested: Selects date types and task constraints to protect realistic schedule logic.

A regulatory review task cannot begin before a fixed submission date, but it should move later automatically if its predecessor finishes late. The project manager wants the schedule to reflect dependency-driven dates rather than pinning the task to an immovable date. Which task configuration best meets the requirement?

Correct Answer: C. Use a Start No Earlier Than constraint for the submission date and retain the predecessor relationship.
Explanation:

A Start No Earlier Than constraint enforces the earliest permitted start while allowing the schedule to move later when dependency logic requires it. Retaining the predecessor preserves the relationship between upstream work and regulatory review. Must Start On is a hard date and can prevent the task from shifting as intended. A finish constraint addresses a different scheduling requirement, and removing dependencies or ignoring them undermines schedule logic.

Question 9

New Multiple answers

Topic: Execute

Skill tested: Uses the Workload Balancer to identify and resolve capacity conflicts.

A project manager sees that one specialist is assigned overlapping work across several active projects during the same week. The specialist's manager can reallocate work, but the manager must preserve task ownership history and avoid changing planned effort without consulting project leads. The team wants to use Workfront's Workload Balancer to identify feasible changes. Which two actions are most appropriate? Select TWO.

Correct Answer: D. Review the specialist's scheduled work and capacity in the Workload Balancer for the relevant time period.; E. Reassign selected work to an available, appropriately qualified user while coordinating any resulting schedule impact with project leads.
Explanation:

The Workload Balancer helps managers evaluate assigned work over a time period and make informed assignment changes based on availability. Reassigning appropriate work, with project-lead coordination, addresses the capacity issue while preserving meaningful task records. Reducing planned hours merely to alter a capacity display distorts estimates. Deleting and recreating assignments damages continuity, and moving project dates without investigating workload does not resolve the underlying allocation conflict.

Question 10

New Single answer

Topic: Execute

Skill tested: Distinguishes task Condition from Progress Status during execution reporting.

A project manager reviews a task that has started and is progressing as expected, but the task owner has completed only a small portion of the work. In a report, the manager wants to represent whether the task is on track separately from how far the work has progressed. Which interpretation should the manager use?

Correct Answer: A. Use Condition to communicate whether the task is on track and Progress Status to reflect its progress state.
Explanation:

Condition communicates the task's health or whether it is on track, while Progress Status represents the state of progress. A task can therefore be progressing slowly in percentage terms but still be on track, or have substantial completion while being at risk. Completion percentage is not the meaning of Condition, and neither field represents an approval decision or assignment. Keeping both concepts distinct supports clearer execution reporting.

Question 11

New Multiple answers

Topic: Execute

Skill tested: Builds execution reporting that combines project and task-level indicators.

A PMO director wants an execution dashboard for project managers. It must show active projects with their planned completion dates and project managers, then provide a focused view of late or at-risk tasks for follow-up. The director wants users to drill into Workfront records rather than maintain separate spreadsheets. Which two dashboard components best meet the need? Select TWO.

Correct Answer: B. A task report filtered for relevant project tasks and displaying schedule or condition indicators useful for follow-up.; D. A project report filtered to active projects and displaying project manager and planned completion date.
Explanation:

The project report provides the portfolio-level view of active projects, owners, and planned completion dates. A separate task report can focus on execution details, including tasks needing attention, and users can open the underlying Workfront records to act. Proof data does not replace project and task scheduling fields. A manually maintained panel becomes stale, while a user report grouped by license type does not address project execution needs.

Question 12

New Single answer

Topic: Execute

Skill tested: Applies Gantt chart predecessor relationships to analyze schedule effects.

In a project Gantt view, a design task must finish before a build task can begin. The build task currently has no predecessor, so moving the design task later does not move the build task. The project manager wants the schedule to reflect the actual work sequence and continue recalculating dates when the design schedule changes. What should the manager do?

Correct Answer: D. Add a finish-to-start predecessor relationship from the design task to the build task.
Explanation:

A finish-to-start predecessor expresses that the design task must finish before the build task starts. With the dependency in place, schedule changes to the predecessor can flow through the project's scheduling logic. Condition indicates health, not date dependency. Milestone configuration does not create the required relationship by itself, and changing ownership does not cause one task's dates to drive another task.

Question 13

New Single answer

Topic: Execute

Skill tested: Chooses Workfront proof workflows for controlled content review and approval.

A communications team must obtain tracked feedback on a campaign brochure from several reviewers. Reviewers need to comment on specific locations in the uploaded content, and the project manager needs to know who has completed the review. The team wants to preserve the project schedule and task assignments rather than collecting feedback in email. Which approach is most appropriate?

Correct Answer: D. Upload the brochure as a proof, configure the required reviewers and approval workflow, and track their decisions in the proof.
Explanation:

A Workfront proof supports review of specific content, including anchored comments and a recorded review or approval workflow. This keeps feedback associated with the brochure and makes reviewer completion visible without misusing the project schedule. Tasks can track work, but their descriptions do not provide the same content-focused proof review experience. Project ownership and Condition do not record individual proof decisions, and a milestone alone cannot establish that reviewers approved the artifact.

Question 14

New Multiple answers

Topic: Execute

Skill tested: Configures approval routing to capture required review decisions before progression.

A communications project cannot proceed to release until both the legal reviewer and the brand reviewer approve the final deliverable. Each reviewer must make an explicit decision, and the project manager needs to see outstanding approvals in Workfront. The team does not want a task to be marked complete merely because the artifact was uploaded. Which two actions best implement this control? Select TWO.

Correct Answer: C. Require the approval decision before the deliverable advances to its next controlled stage.; D. Attach an approval process to the appropriate object or work item and include both required reviewers in the approval routing.
Explanation:

An approval process with both reviewers provides explicit, trackable decisions in Workfront. Requiring approval before progression enforces the release gate rather than treating upload or task completion as consent. Assigning a task to reviewers does not reliably capture separate approval decisions. A milestone indicates a schedule checkpoint, not each reviewer's decision, and email silence is not an auditable explicit approval.