Limited-Time Offer: Enjoy 50% Savings! Ends in 00h 00m 00s Coupon code: 50OFF
Skip to content

Free Adobe Workfront Project Manager Certified Professional AD0-E911 Exam Questions

Page: 1 / 10 Total 95 questions

Want more questions? Get Premium Access.

Question 1

A user wants to add users to a proof based on who requested the project and the additional approvers listed in the request.

Which Workflow should the user choose?

Correct Answer: B. Basic
Explanation:

In Adobe Workfront proofing, the user should choose a Basic workflow when the proof recipients need to be added manually based on information from the request, such as the project requester and additional approvers listed in request details. Adobe's documentation for creating an advanced proof with a Basic workflow states that the user selects Basic in the Workflow type section, then specifies the users to add and chooses each person's proof role. This fits the scenario because the reviewers and approvers are determined by the request information rather than by a preconfigured staged workflow. By contrast, Adobe explains that an Automated Workflow is best when the review process is complex or when proofs are regularly sent to the same people, because it moves the proof from stage to stage and notifies participants when it is their turn. ''Manual'' is not the documented proof workflow type for this setup. Therefore, the correct workflow is B. Basic.


Question 2

All of the tasks on a project show as 100% complete, but when the Project Owner tries to update the status of the project to Complete, the Owner receives an error that reads "Project cannot be marked Complete if there are open issues and tasks that are not complete." How can the Project Owner determine which tasks are incomplete?

Correct Answer: C. The task status needs to be updated to Done even though the percent complete is at 100%. The Project Owner could filter the project task list for incomplete tasks and check the task status to determine which tasks are not complete.
Explanation:

Even if the task shows 100% complete, the Status of the task may still be listed as something other than 'Done.' Workfront requires that both the Status and the Percent Complete indicate the task is fully completed before the project can be marked as complete. The Project Owner can filter for tasks that are not marked as 'Done' and update their statuses accordingly.


Question 3

What are two ways to associate milestone steps to tasks? (Choose two.)

Correct Answer: A. In-line editing a task list on a project; B. From the Milestone View in the Projects area
Explanation:

Milestones in Adobe Workfront allow project managers to mark significant phases in a project. There are two primary methods for associating milestone steps to tasks:

In-line editing a task list on a project: This method allows you to quickly assign milestones while editing the task list. It's a convenient option when working directly within a project's task list, ensuring you can associate tasks with milestone steps in a streamlined way without navigating away from the list view.

From the Milestone View in the Projects area: The Milestone View is specifically designed to help manage milestones. It allows you to view and organize milestones and their associated tasks in one place, making it easy to connect tasks to milestones without manually editing individual tasks.

These methods are integral for tracking progress and ensuring that tasks align with the significant steps of a project.


Question 4

A team lead wants to see all hours that have been logged this month by members of the team lead's home team, organized by project. How should the team lead create this view?

Correct Answer: B. Visit the Reports area and create a new Hour report. Add the filters for Owner > Home Team ID > Equal > [Name of Home Team] and Hour > Entry Date > This Month. Group the results by Project > Name.
Explanation:

The team lead should create a report in the Reports area to see all hours logged by the home team during the current month. By using filters for Home Team ID and Entry Date, and grouping the results by Project Name, the team lead can view hours logged in a project-based format for the entire home team during the selected time period.


Question 5

An organization has created unique data fields relevant to their projects. Starting by navigating from a project's landing page, where is this data found?

Correct Answer: C. Business Case > Project Info
Explanation:

In Workfront, custom data fields created for projects are typically found within the 'Business Case' section, specifically under 'Project Info.' This area houses key project information and unique custom fields that are relevant to the project's setup. The 'Project Details' section is more focused on task-related information and the overall summary of the project.


Question 6

Task 1 on Project 1 can only be started once the final milestone on Project 2 is completed.

How can the project manager configure this relationship?

Correct Answer: C. Add a cross-project predecessor on the final milestone in Project 2.
Explanation:

In Workfront, cross-project predecessors allow dependencies between tasks across different projects. To ensure that Task 1 in Project 1 starts only after the final milestone of Project 2, the project manager must configure a cross-project predecessor linking the final milestone in Project 2 to Task 1 in Project 1. This establishes a dependency and aligns the timelines of the two projects.


Question 7

A team member has five days to complete a critical path task, and the task requires only one hour. Today is the fourth day in the timeframe, and the team member has not yet worked on it.

What impact does this have on the project progress status?

Correct Answer: C. The project shows an At Risk automatic condition.
Explanation:

In Workfront, if a task that is part of the critical path is delayed, it affects the overall project schedule. Even though the task is not overdue yet, Workfront's automated system flags the project as 'At Risk' if there is a delay in progress that could impact the project's timeline. This 'At Risk' condition acts as a warning to project managers and stakeholders that immediate attention is needed.


Question 8

Given this information regarding a Task:

Planned Start Date: May 14

Actual Start Date: May 14

Planned Completion Date: May 20

Projected Completion Date: May 22

Percent Complete: 50%

Duration: 5 Days

Planned Hours: 8 Hours

Status: In Progress

If today's date were May 19, what would be the Task's progress status?

Correct Answer: C. At Risk
Explanation:

In Workfront, when the projected completion date exceeds the planned completion date and the task is only 50% complete by May 19, it is automatically flagged as 'At Risk.' This alerts the project manager that the task is not progressing according to the original plan, potentially causing delays in the project timeline.


Question 9

A project manager has set up and launched a new project for an annual marketing campaign.

Where can the project team locate their work requests?

Correct Answer: A. Email, Workfront Home, Project tasks list
Explanation:

Workfront provides multiple ways for team members to track and locate their assigned work. The primary tools include the Workfront Home area, which centralizes all work items assigned to a user, and email notifications that can alert users to new assignments or updates. Additionally, users can view specific tasks in the Project tasks list. Workfront Home is a key component for workers as it consolidates all active assignments and updates in a single view.


Question 10

What item, when shared with a user, can never give that user inherited permission to a project?

Correct Answer: C. Report
Explanation:

Adobe Workfront, permissions can be inherited through various objects like projects, portfolios, or tasks when shared with users. However, when sharing a report, the permissions do not cascade to related items like projects or tasks within that report. This is because reports are generated views and do not directly control object-level permissions. A report can be shared to allow a user to see data within the report, but it will not grant them inherited permissions to the underlying projects or tasks displayed in that report.