Question 1
Topic: Source inspection fundamentals and ITPs
Skill tested: Traces an ITP hold point and verifies acceptance evidence against project criteria.
A supplier's inspection and test plan identifies a hold point before energization of a packaged distribution panel. The project specification requires the purchaser's representative to witness the specified insulation-resistance test and review its readings against the approved acceptance criteria. The supplier reports that the test was completed before the inspector arrived; a signed internal checklist is available, but the test record contains no instrument identification or recorded readings. Production is waiting for release, and the ITP does not permit retrospective waiver by the supplier. What is the most appropriate inspection action?
A hold point is a required pause for the designated inspection or approval before work proceeds. A checklist without readings and instrument identification does not demonstrate that the specified test met its acceptance criteria, and the missed witness opportunity cannot be repaired by simply accepting a supplier assertion. The inspector should document the deviation and obtain an authorized disposition and adequate objective evidence before release. Conditional release (B) bypasses the ITP control; energizing first (D) changes the sequence and may create safety or equipment risks; the internal sign-off alone (A) is insufficient evidence.