Question 1

Who is responsible for meeting the minimum specifications of the product design?

Correct Answer: C. Manufacturing

Question 2

and uncouples the sales forecast from manufacturing by establishing a manufacturing plan

Correct Answer: A. Production plan, MPS

Question 3

The CPI system is based on the scientific methods. This general method is used to solve many kinds of problems. Which of the following is NOT the out of six steps continuous improvement process?

Correct Answer: C. Bottlenecks

Question 4

The available time depends on the number of machines, number of workers and:

Correct Answer: C. hours of operation

Question 5

What reduces the planning and control effort needed, the number of items required, and the inventory that has to be carried?

Correct Answer: A. Standardization

Question 6

What represents the master schedule for the operation, which is focused around the pace of throughput as defined by the constraint?

Correct Answer: A. Drum

Question 7

What consists of taking a sample of a batch of product and using it to estimate the overall quality of the batch?

Correct Answer: A. Acceptance sampling

Question 8

Which one of the following tools that cannot be used to evaluate feasibility of a strategy?

Correct Answer: D. None of these

Question 9

Which of the following are the purposes of material requirement planning so items in the master production schedule are made on time?

Correct Answer: D. All of the above

Question 10

Based on material flow, processes can be organized in which way?

Correct Answer: D. All of the above

Question 11

A statistical value that measures how closely the individual values cluster about the average is called:

Correct Answer: B. Standard deviation

Question 12

Over time, as the operator does the tasks repetitively, speed will increase and errors decrease, this process is known as:

Correct Answer: C. Leaning curve

Question 13

What are purchased items received that have not entered the production process?

Correct Answer: A. Raw materials

Question 14

What involves long-range capacity resource requirements and is directly linked to production planning?

Correct Answer: B. Resource planning

Question 15

For master production schedule planning horizon usually extends from:

Correct Answer: A. 3-18 months