Free APICS Certified in Production and Inventory Management CPIM Exam Questions

Last updated: · 15 practice questions with answers and explanations

Page: 1 / 40 Total 588 questions

Want more questions? Get Premium Access.

Question 1

New Single answer

Topic: Supply Chains and Strategy

Skill tested: Aligns supply chain design and performance measures with competitive business strategy.

A manufacturer competes by offering highly customized equipment with short quoted lead times. Its current supply chain is optimized for long production runs, low unit cost, and high utilization; this has produced long queues and frequent late deliveries of configured orders. Leadership wants to improve responsiveness without abandoning cost discipline. Which strategic change is the best starting point?

Correct Answer: B. Segment products and supply chain policies by demand and customization characteristics, then align service and cost measures to each segment.
Explanation:

A single efficiency-oriented design conflicts with the stated competitive priority of customization and responsiveness. Segmenting products allows predictable, standard items to retain efficient replenishment while configured or volatile items receive policies that protect response time. Measures should reflect the intended balance, such as delivery reliability and lead time alongside cost. Purchase-price variance alone (A) ignores service consequences; maximizing utilization (C) can worsen queues and flow time; and stocking every configuration (D) creates excessive inventory and obsolescence risk.

Question 2

New Single answer

Topic: Supply Chains and Strategy

Skill tested: Selects supply chain risk responses based on likelihood, impact, and recovery needs.

A company depends on one geographically concentrated supplier for a specialized electronic component. A disruption analysis shows that a regional event could stop production for several months, while qualifying a replacement source takes a year. The component is inexpensive, and management has limited capital for broad risk-reduction programs. Which response most directly reduces the identified continuity risk?

Correct Answer: C. Qualify an alternate source or establish a targeted strategic buffer sized to cover the credible recovery interval.
Explanation:

The exposure is a prolonged interruption combined with a long alternate-source qualification time. A targeted contingency - diversification where feasible, or a buffer based on the disruption and recovery interval - addresses continuity directly. Ordinary cycle stock (B) covers expected consumption between replenishments, not a multi-month disruption. A lower price (A) does not reduce the single-source exposure, and consignment (D) changes ownership timing rather than supply availability. The response should be sized to the risk rather than applied indiscriminately.

Question 3

New Single answer

Topic: Sales and Operations Planning (S&OP)

Skill tested: Uses S&OP to reconcile demand, capacity, inventory, and financial objectives.

At an S&OP review, the proposed plan covers a seasonal sales increase by building inventory in advance. The aggregate plan shows that production capacity is sufficient, but finance identifies that the inventory build would breach the working-capital limit. Sales opposes reducing the forecast, and operations cannot add a shift during the peak. What is the most appropriate next step in the S&OP process?

Correct Answer: B. Reconcile feasible alternatives - such as demand shaping, product mix, and phased inventory targets - and present their service, capacity, and financial trade-offs for executive decision.
Explanation:

S&OP integrates demand, supply, and financial considerations; it does not simply ratify one function's plan. The team should quantify alternatives and their trade-offs, then resolve the gap at the appropriate decision level. Capacity availability alone does not make an inventory build financially acceptable. Deferring the issue (A) leaves the plan unbalanced; replacing demand with supply (C) confuses a forecast with a feasible response; and overriding the capital constraint (D) ignores a material business objective.

Question 4

New Multiple answers

Topic: Sales and Operations Planning (S&OP)

Skill tested: Evaluates alternative S&OP plans using capacity feasibility and cross-functional trade-offs.

A food producer must prepare an aggregate plan for a four-month demand peak. Forecast demand exceeds regular-time capacity in months two and three, but the plant has unused capacity before the peak. Finished products are perishable, overtime is available but costly, and subcontracting is prohibited for regulatory reasons. Executives want a balanced recommendation rather than an unconstrained forecast. Which TWO planning actions are most appropriate to evaluate in S&OP? Select TWO.

Correct Answer: A. Build inventory ahead of the peak only for products with sufficient shelf life and reliable demand, while evaluating the carrying and obsolescence exposure.; B. Plan overtime in peak periods within labor, equipment, and food-safety constraints, and compare its incremental cost with service impact.
Explanation:

The two feasible levers are a selective prebuild and constrained overtime. A prebuild can use available early capacity, but perishability and forecast reliability determine which items are suitable. Overtime can address the residual peak gap, with its cost and operational limits made explicit. Subcontracting (C) violates a stated constraint. Maximum production every month (D) risks waste and excess inventory, while unilaterally capping demand (E) conceals the gap instead of developing an integrated business plan.

Question 5

New Single answer

Topic: Demand

Skill tested: Chooses forecasting methods and forecast evaluation measures appropriate to demand patterns.

A distributor reviews monthly demand for a mature replacement part. Demand has no clear trend or seasonality, but occasional large orders create spikes. Planners currently use a simple average that reacts slowly after a sustained level change. The business wants a method that can respond more quickly while reducing the influence of one-off extremes; it will assess forecast bias separately from forecast magnitude. Which approach is most appropriate to test?

Correct Answer: A. Use a short moving average and select its window by comparing forecast errors on historical holdout periods.
Explanation:

A shorter moving-average window responds more quickly to a persistent level change than a long average, while averaging dampens isolated spikes. Comparing candidate windows on holdout data helps avoid choosing a method solely because it fits the history. A linear trend (B) is unsuitable without a trend and can be distorted by spikes. The maximum (C) systematically overstates typical demand. Prior-period demand (D) is a naïve method that can be tested, but it does not meet the stated goal of moderating isolated extremes, and signed errors can cancel when assessing magnitude.

Question 6

New Multiple answers

Topic: Demand

Skill tested: Separates baseline demand from promotions and coordinates forecast ownership with customer information.

A consumer-products supplier serves a major retailer that provides a promotion calendar and point-of-sale data. The supplier's statistical forecast has been repeatedly raised by sales after promotional orders arrive, but the adjustments are not recorded with reasons. Resulting plans overstate post-promotion demand and leave excess stock. The retailer's data is available before each planning cycle, and the company wants forecast accountability without suppressing legitimate market intelligence. Which TWO actions should the demand-planning process adopt? Select TWO.

Correct Answer: A. Use the retailer's promotion and point-of-sale information to model event demand separately from the underlying baseline.; B. Record and review judgmental forecast overrides with an owner, rationale, and subsequent accuracy assessment.
Explanation:

Separating event-related demand from baseline makes it possible to plan the promotion and avoid carrying its uplift into later periods. Retailer point-of-sale data and the calendar provide relevant demand signals. Maintaining an auditable record of overrides lets the organization learn whether judgment adds value and preserves ownership. Untracked replacement (C) prevents evaluation; permanently embedding promotions (D) causes post-event overforecasting; and ignoring useful customer data (E) discards information that can improve timing and magnitude estimates.

Question 7

New Single answer

Topic: Supply

Skill tested: Selects capacity-planning responses that address a recurring resource constraint economically.

A plant's rough-cut capacity review shows a recurring shortfall at one specialized finishing cell during the next three quarters. Other work centers have slack, and the demand forecast is stable enough to support medium-term decisions. A new permanent line would be expensive and would take many months to install. Management needs a near-term plan that protects customer commitments while it validates the longer-term requirement. What should the planner recommend first?

Correct Answer: B. Evaluate a combination of alternate routing, selective overtime, and order timing, then validate the residual shortfall before committing to permanent capacity.
Explanation:

The constraint is localized and recurring, but the demand and investment case still need validation. Testing feasible short-term measures - alternate routing if qualified, limited overtime, and timing adjustments - can protect commitments while exposing the residual capacity gap. Overloading (A) creates an infeasible schedule rather than capacity. Buying immediately based only on a peak (C) risks overinvestment. Unilateral forecast reduction (D) hides the customer and commercial consequences and does not resolve prioritization.

Question 8

New Multiple answers

Topic: Supply

Skill tested: Uses supplier relationship and procurement controls to reduce supply continuity and quality exposure.

A medical-device assembler sources a critical molded component from a supplier with good price performance but recurring late deliveries and inconsistent lot documentation. A second supplier exists, but it has not completed qualification. Production cannot use undocumented lots, and the company must preserve traceability. Purchasing proposes larger orders to earn a discount. Which TWO actions best address the operational risk while supporting a sound supplier relationship? Select TWO.

Correct Answer: A. Implement a joint corrective-action and delivery-improvement review with measurable quality, documentation, and delivery performance.; B. Complete qualification of the alternate supplier, including required quality and traceability validation, before relying on its capacity.
Explanation:

The company needs both improvement of the current source and a validated alternative. Joint corrective action using defined measures addresses root causes and makes performance expectations visible. Qualifying the second supplier creates resilience, but quality and traceability must be confirmed before production reliance. Larger orders and waived checks (C) increase exposure and violate the stated control requirement. Price-only allocation (D) ignores delivery and quality, while withholding performance information (E) undermines effective supplier improvement.

Question 9

New Single answer

Topic: Detailed Schedules

Skill tested: Applies finite-capacity scheduling and priority rules to protect due-date performance at a bottleneck.

A machine shop releases jobs to a single bottleneck work center. The current schedule uses earliest due date, but several long jobs repeatedly delay short orders that have little remaining slack. The shop cannot add capacity, and managers want to improve due-date performance without allowing arbitrary favoritism. Routings and remaining processing times are reliable. Which scheduling approach is the best next step?

Correct Answer: B. Use a priority rule based on remaining slack or critical ratio, review exceptions, and monitor the resulting lateness and flow time.
Explanation:

A slack-based or critical-ratio priority incorporates both time remaining and work remaining, making it more responsive to urgency than due date alone. The shop should validate the rule against its performance objectives and retain controlled exception review. Shortest processing time (A) may reduce average flow time but can defer urgent long jobs. Releasing everything (C) increases work-in-process and queue time without adding capacity. Manual expediting (D) preserves the observed problem and can create unstable priorities.

Question 10

New Single answer

Topic: Detailed Schedules

Skill tested: Sequences production batches to reduce setup losses while respecting delivery commitments.

A packaging line makes several products with sequence-dependent changeovers. The weekly schedule currently groups all production by product family, minimizing setups, but this causes late shipments for an urgent customer order. The line has no spare capacity this week; materials for all orders are available. The plant manager wants a revised schedule that improves service without ignoring setup losses. What is the most appropriate scheduling decision?

Correct Answer: B. Re-sequence the affected jobs using a due-date and setup-aware trade-off, confirming that the urgent order can be completed without making other commitments infeasible.
Explanation:

A finite schedule must account for both sequence-dependent setup time and customer due dates. Re-sequencing should explicitly assess whether the urgent order can be inserted while preserving feasibility for other commitments, rather than optimizing one criterion blindly. Keeping the original sequence (A) disregards the service failure. Simply placing the order first (C) may create excessive setup time and displace other due work. Small batches for all products (D) can multiply changeovers and exceed available capacity.

Question 11

New Single answer

Topic: Inventory

Skill tested: Sets safety stock using demand and lead-time variability to achieve a target service level.

A distributor replenishes a stocked item from a supplier with variable lead time. Average demand and average lead time have remained stable, but the item has frequent stockouts despite a reorder point calculated from average demand during average lead time. The business has a defined service target and reliable historical demand and receipt data. Which change is most appropriate?

Correct Answer: B. Include demand and lead-time variability in the protection-period demand estimate and set safety stock to match the service target.
Explanation:

A reorder point based only on average demand and average lead time covers expected demand, not uncertainty during replenishment. Safety stock should reflect variability over the protection period and the selected service objective. An arbitrary increment (A) may be excessive or insufficient and cannot be tied to service. Reducing the point (C) worsens exposure. A larger order quantity (D) changes replenishment lot size and cycle stock; it does not directly correct the trigger level for variable lead time.

Question 12

New Multiple answers

Topic: Inventory

Skill tested: Distinguishes cycle stock, safety stock, and obsolescence controls in inventory policy design.

A manufacturer holds a broad range of spare parts. A review finds that several slow-moving parts are becoming obsolete, while a few critical parts experience intermittent stockouts. The parts differ in value, criticality, and demand variability. Finance requires lower total inventory investment, but maintenance requires protection against production-stopping shortages. Which TWO actions best improve the inventory policy? Select TWO.

Correct Answer: A. Segment items using relevant value, criticality, and demand characteristics, then apply differentiated service and replenishment policies.; B. Review excess and obsolete exposure and reduce or dispose of items with no credible future requirement, subject to engineering and service approval.
Explanation:

Differentiated policies avoid treating a low-criticality, obsolete item like a production-critical spare. Segmentation supports targeted service levels and replenishment methods; a controlled excess-and-obsolete review reduces investment without discarding parts that remain essential. Across-the-board cuts (C) can create avoidable critical shortages. Larger lots (D) may increase exposure and obsolescence, and maximum service for every item (E) would conflict with the investment constraint.

Question 13

New Single answer

Topic: Quality, Technology and Continuous Improvement

Skill tested: Uses root-cause analysis and corrective action to reduce recurring process defects.

A production cell reports a defect rate that varies significantly by shift. Operators have been retrained several times, but the defect remains, and the inspection process detects the problem only after substantial work has accumulated. Product specifications and measurement equipment are confirmed to be valid. The operations manager wants a sustainable improvement rather than another short-term reminder. What should the team do first?

Correct Answer: B. Stratify defect data by shift and relevant process conditions, investigate causes at the source, and verify corrective actions with measured results.
Explanation:

Variation by shift is a signal to examine process conditions and stratify data before selecting a cause. Root-cause investigation followed by verified corrective action addresses the process rather than relying on repeated reminders. More final inspection (A) detects defects later but does not prevent them. Blaming a shift (C) assumes causation without evidence, and changing specifications (D) is not an authorized process correction and may compromise customer requirements.

Question 14

New Multiple answers

Topic: Quality, Technology and Continuous Improvement

Skill tested: Selects process-control and mistake-proofing improvements to prevent defects at their source.

A company assembles a product with two visually similar fasteners. An incorrect fastener is occasionally installed, and final inspection catches some but not all instances. The assembly sequence is otherwise stable, and engineering can change fixtures, but the company cannot alter the product design or rely on adding inspectors. The quality team wants to reduce defect occurrence and detect process shifts promptly. Which TWO actions best meet these goals? Select TWO.

Correct Answer: A. Modify the fixture or presentation method so the wrong fastener cannot be selected or installed where practical.; B. Use an appropriate process-control method to monitor the relevant process characteristic and investigate signals of special-cause variation.
Explanation:

A mistake-proofing fixture or presentation change prevents the selection error at the source, while process control helps identify meaningful changes in the process before defects accumulate. These actions complement rather than replace one another. More final inspection (C) remains a detection-only response and is expressly constrained. Capability analysis (D) summarizes performance under appropriate conditions but does not substitute for ongoing control. Visual acceptance of the wrong component (E) does not ensure conformance.

Question 15

New Single answer

Topic: Quality, Technology and Continuous Improvement

Skill tested: Evaluates technology adoption using process requirements, data quality, and measurable operational benefits.

A distribution center is considering automated identification technology to improve inventory accuracy. Current records are unreliable because receiving scans are sometimes skipped and item master data contain duplicate identifiers. A vendor demonstration showed rapid cycle counts, but the proposal requires a substantial investment and management has not defined a target improvement. The center cannot interrupt operations for a large-scale rollout. What is the best next step?

Correct Answer: B. Define the accuracy and process objectives, address master-data and receiving controls, and run a limited pilot with measurable acceptance criteria.
Explanation:

Technology can improve visibility and transaction capture, but it will not reliably correct duplicate identifiers or skipped receiving transactions by itself. Defining measurable outcomes and stabilizing foundational data and process controls makes a limited pilot informative and reduces rollout risk. Immediate purchase (A) assumes the tool fixes root causes. A wholesale process replacement (C) risks operational disruption and integration failure. Permanent rejection (D) is premature; technology may help once requirements and controls are addressed.