Question 1

New Single answer

Topic: Roles and Responsibilities - the Project Manager's view

Skill tested: Distinguishes project-level coordination from responsibilities delegated to AgilePM team roles.

A public-sector team is starting a time-critical service redesign. The Business Sponsor has confirmed the need and funding, while the Business Visionary is responsible for ensuring the solution meets business objectives. The Project Manager is preparing the governance arrangements and is asked to approve detailed design decisions whenever the team encounters uncertainty. The Solution Development Team is capable of making day-to-day technical decisions, and the organization wants to preserve fast progress without weakening project control. What is the Project Manager's most appropriate response?

Correct Answer: B. Establish clear escalation and governance arrangements, while leaving day-to-day solution decisions to the appropriate team roles.
Explanation:

The Project Manager coordinates and controls the project at the project level, ensuring that governance, planning, risks, and escalation routes support delivery. Detailed solution decisions should be made by the roles best placed to make them, rather than routinely escalated to the Project Manager. Taking over design decisions blurs accountability and can slow the team. The Business Visionary provides business direction but does not replace project management, and sponsor approval of every timebox would add unnecessary control overhead.

Question 2

New Single answer

Topic: Roles and Responsibilities - the Project Manager's view

Skill tested: Selects an appropriate response when project governance and team empowerment appear to conflict.

A regulated insurer has appointed a Project Manager for an AgilePM project. Compliance requires evidence that major decisions have an accountable owner, but the delivery team reports that project approvals are delaying routine work. The Business Sponsor expects oversight of continued business justification, while the team needs authority to resolve day-to-day issues within agreed boundaries. Which action best balances these needs?

Correct Answer: D. Agree decision rights and escalation thresholds, retaining governance for significant matters and delegating routine decisions.
Explanation:

AgilePM combines appropriate governance with empowered teams. Explicit decision rights and escalation thresholds let the team handle routine matters while ensuring significant decisions remain visible to accountable project roles. Approving every requirement change creates a bottleneck; unrestricted authority undermines governance and continued justification. Sponsor attendance at daily team meetings is not a substitute for a clear governance model and would burden the sponsor with operational decisions.

Question 3

New Single answer

Topic: Agile Project Management – through the lifecycle

Skill tested: Chooses the correct lifecycle point to assess whether a proposed project is viable.

A retailer has requested a new inventory capability, but the proposed benefits, technical approach, and delivery constraints remain uncertain. Senior management wants to avoid committing a full delivery team until it has enough evidence to decide whether the project is worth pursuing. The organization also needs to identify likely risks and determine whether an AgilePM approach is suitable. What is the most appropriate next lifecycle activity?

Correct Answer: A. Complete a Feasibility assessment to establish whether the project is viable and appropriate to proceed.
Explanation:

Feasibility is the lifecycle point for assessing whether the proposed project is viable, including its business rationale, risks, constraints, and suitability for the approach. Foundations follows once there is a decision to proceed and establishes the basis for controlled delivery. Starting development before determining viability commits resources too early, while deployment is a delivery activity and cannot replace the initial assessment.

Question 4

New Single answer

Topic: Agile Project Management – through the lifecycle

Skill tested: Identifies the purpose of Foundations in establishing project-level agreement before iterative delivery.

A financial-services organization has completed an initial viability assessment and agreed to proceed with an AgilePM project. The team has a broad business vision, but senior stakeholders disagree about the solution boundaries, quality expectations, and how progress will be controlled. They also want delivery to adapt as learning occurs rather than require a complete specification up front. Which is the most appropriate focus before iterative development begins?

Correct Answer: A. Establish the project foundations, including a shared understanding of scope, solution approach, control, and prioritized requirements.
Explanation:

Foundations establishes a sufficient shared basis for delivery: the project's scope and approach, governance and control, quality expectations, and prioritized requirements. It is deliberately not a demand for exhaustive up-front detail. Complete design specifications would restrict adaptation and delay learning; deploying before agreement on essential foundations creates avoidable risk. The business rationale and vision should already inform the decision to proceed, not be invented after delivery starts.

Question 5

New Single answer

Topic: Agile Project Management – through the lifecycle

Skill tested: Distinguishes iterative development from deployment and release activities in the lifecycle.

A product team has completed several development timeboxes. The latest increment has been reviewed and meets its agreed acceptance criteria, but the operational support group has not yet received the deployment information and the business has not confirmed readiness to make the capability live. A manager argues that completing development means the project should automatically be considered deployed. What is the best next step?

Correct Answer: C. Prepare and carry out the appropriate Deployment activity, including readiness and handover considerations, before treating the capability as live.
Explanation:

Iterative development produces and reviews increments; it does not by itself make a solution live or complete deployment and handover responsibilities. The team should address operational readiness and carry out the appropriate Deployment activity in line with the project's release arrangements. Treating timebox acceptance as automatic deployment confuses development with release. Waiting for every possible requirement may delay usable delivery unnecessarily, and operational support needs do not by themselves invalidate feasibility.

Question 6

New Multiple answers

Topic: The Effective Use of the Products

Skill tested: Uses AgilePM products to communicate business rationale and maintain a controlled record of project progress.

A charity is funding an AgilePM project to replace its volunteer scheduling process. At the end of Foundations, executives need a concise basis for continued investment and a clear record of what has been completed, what remains, and the current outlook. They do not want a detailed technical specification as a substitute for business justification. Which TWO products best serve these needs? Select TWO.

Correct Answer: A. Project Review Report, to provide a status snapshot while the project is still progressing.; D. Business Case, to document the continuing justification for the project.
Explanation:

The Business Case captures the project's business justification and supports continued investment decisions. A Project Review Report provides a point-in-time view of project status, including progress and outlook, making it suitable for the executives' reporting need. The Solution Architecture Definition describes the solution architecture, not project-wide status. A Benefits Assessment focuses on benefits, and a Timebox Plan is for planning a specific timebox rather than replacing the Business Case or project status reporting.

Question 7

New Single answer

Topic: The Effective Use of the Products

Skill tested: Selects the appropriate product for planning and controlling a defined delivery timebox.

A delivery team has agreed the objectives and prioritized work for its next fixed-length timebox. The team needs a practical plan showing how it intends to achieve the timebox objectives, coordinate the work, and monitor progress during that period. The Project Manager already maintains project-level plans, and stakeholders do not want a new document that duplicates those plans. Which product should the team use?

Correct Answer: D. Timebox Plan, to guide the work and progress monitoring for that timebox.
Explanation:

The Timebox Plan is the product used to plan and control a specific timebox, including the work and objectives the team intends to complete. It complements rather than duplicates project-level planning. The Project Approach Questionnaire helps consider the suitability and tailoring of the approach; it is not a task plan. A Benefits Assessment and Business Case have benefits and justification purposes, not daily timebox coordination.

Question 8

New Multiple answers

Topic: Deliver on time – Combining MoSCoW Prioritization and Timeboxing

Skill tested: Applies MoSCoW categories to protect fixed timebox dates while managing scope trade-offs.

A team is delivering an online claims feature within a fixed-length timebox. A late technical issue means the original scope cannot all be completed on time. The Business Ambassador confirms that identity verification and claim submission are essential for a usable release. A reporting enhancement is desirable but can be delivered later, and a proposed dashboard has no current business need. The team must protect the timebox end date and avoid silently reducing quality. Which TWO actions best follow AgilePM practice? Select TWO.

Correct Answer: C. Reassess the work using MoSCoW, protecting essential Must Have scope and considering lower-priority scope for removal.; D. Negotiate the treatment of the Could Have dashboard and other lower-priority work, documenting agreed scope trade-offs.
Explanation:

AgilePM uses MoSCoW prioritization with timeboxing to protect the delivery date by flexing lower-priority scope, while preserving quality and essential Must Haves. The team should reassess priorities and agree which Should or Could Have work can be deferred; agreed trade-offs should be made visible. Extending the timebox abandons the fixed-time principle, lowering acceptance criteria undermines quality, and planned work does not become Must Have merely because it was scheduled.

Question 9

New Single answer

Topic: Deliver on time – Combining MoSCoW Prioritization and Timeboxing

Skill tested: Recognizes the minimum usable subset needed to satisfy a Must Have requirement.

A team is building a timeboxed customer-account update. The Must Have requirement is that a customer can change an address and receive confirmation that the request was recorded. A proposed confirmation email is desirable, but the service can provide an on-screen confirmation instead. The team has limited capacity and cannot complete both confirmation methods without risking the timebox objective. Which decision best preserves the requirement while supporting delivery on time?

Correct Answer: C. Deliver the smallest acceptable solution that records the address change and confirms it on screen, deferring email if agreed.
Explanation:

A Must Have requirement should represent a minimum usable need, not an unnecessarily expansive implementation. The scenario explicitly allows on-screen confirmation to satisfy the essential need, so the team can deliver the address change and record confirmation within the timebox while deferring the desirable email feature by agreement. Omitting all confirmation fails the stated need. Extending the timebox defeats timeboxing, and a Must Have label does not mean every optional implementation detail is mandatory.

Question 10

New Multiple answers

Topic: People, Teams and Interactions

Skill tested: Improves collaboration by using empowered, cross-functional teamwork and direct communication.

A distributed product team is missing timebox objectives because analysts complete documents and pass them to developers, who then discover unanswered business questions. The Business Ambassador is available for regular collaboration, but managers have been routing questions through a weekly approval meeting. The organization cannot add staff or change the agreed timebox length. Which TWO changes are most likely to improve team interaction and flow? Select TWO.

Correct Answer: A. Encourage cross-functional team members to collaborate on work and share responsibility for achieving timebox objectives.; E. Promote direct, frequent collaboration between the team and the Business Ambassador to resolve business questions promptly.
Explanation:

AgilePM favors close collaboration between business and delivery roles and a collaborative, cross-functional team focused on shared objectives. Direct access to the Business Ambassador reduces delays in clarifying business intent, while shared work helps resolve handoffs and bottlenecks. Isolated requirement completion recreates the problem. Weekly-only decisions are too slow for timeboxed work, and individual task counts can reward activity without delivering the agreed outcome.

Question 11

New Single answer

Topic: People, Teams and Interactions

Skill tested: Chooses a facilitative response that helps a team resolve conflict and reach a shared decision.

During a solution review, two experienced developers disagree about an implementation approach. One wants to decide immediately based on technical simplicity; the other raises concerns about operational support. The rest of the team has stopped contributing, and the timebox is at risk. The Project Manager is not the technical authority and should avoid imposing a design decision without evidence. What is the most appropriate action?

Correct Answer: C. Facilitate a focused discussion of the shared objective, relevant evidence, and decision criteria, then support the team in agreeing a way forward.
Explanation:

A facilitative approach helps the team surface the operational concern, agree relevant criteria, and reach a decision grounded in the shared objective. The Project Manager need not act as the technical authority to help the team collaborate. Picking a design without considering evidence risks a poor operational outcome; the sponsor is not the appropriate arbiter of technical detail. Building two full alternatives consumes time and capacity without first determining whether a smaller investigation would resolve the disagreement.

Question 12

New Single answer

Topic: Requirements and User Stories

Skill tested: Writes a user story that expresses a user, a need, and its business value.

A city transport team is replacing a paper process for reporting damaged bus shelters. The current requirement says, "Create a mobile reporting screen with a photo upload field." During discovery, maintenance staff explain that they need to report hazards while in the field so dispatchers can prioritize urgent repairs. The team wants a user story that communicates the user perspective and purpose without prematurely dictating a full design. Which is the best story?

Correct Answer: A. As a maintenance worker, I want to report a damaged shelter while in the field so that dispatch can prioritize a response.
Explanation:

A useful user story identifies a user or role, a need, and the value the need provides. The maintenance worker is the relevant user, reporting damage is the need, and enabling dispatch to prioritize a response expresses the business value. The first choice treats the application as the user and emphasizes an implementation detail. The third is a feature specification rather than a concise user-centered story, while the fourth invents an approval constraint not established by the scenario.

Question 13

New Multiple answers

Topic: Requirements and User Stories

Skill tested: Uses acceptance criteria and ongoing conversation to make a user story testable and understood.

A hospital team has drafted the story, "As a ward clerk, I want to request a patient transport so that the patient can reach the next appointment." Developers disagree about what counts as a complete request, and ward staff are not available during the team's daily planning session. The team needs to make the story sufficiently clear to develop and validate without attempting to specify every future transport scenario. Which TWO actions are most appropriate? Select TWO.

Correct Answer: A. Write concise, observable acceptance criteria that define when this story will be considered acceptable.; D. Collaborate with the ward staff or Business Ambassador to clarify the story's intent and important examples.
Explanation:

User stories benefit from conversation with the relevant business role and from clear, observable acceptance criteria that help the team understand and validate the outcome. The team should resolve the current ambiguity through examples and collaboration, while keeping detail proportionate to the story being delivered. Specifying every possible future case is excessive and can impede adaptation. Independent interpretations invite inconsistent results, and a title alone does not establish shared acceptance expectations.