Question 1

New Single answer

Topic: 1. Projects and Project Work

Skill tested: Selects an implementation strategy by balancing operational risk and continuity requirements.

A regional insurer is replacing its claims system. The new system must be introduced before the existing platform's support contract expires, but claims processing cannot stop for more than a few hours. The two systems can share data only through a temporary interface, and maintaining both environments for several months would exceed the approved budget. A small, representative branch is available for an early deployment, although the regulator requires evidence that the system works across different branch sizes before full rollout. Which implementation strategy best balances these constraints?

Correct Answer: D. Use a pilot in the representative branch, assess the results, then deploy to the remaining branches in a controlled sequence.
Explanation:

A pilot limits initial exposure and produces operational evidence before wider deployment. A controlled subsequent rollout allows results from the branch to inform implementation elsewhere, while avoiding months of parallel operation. Full parallel running is attractive for continuity but conflicts with the stated cost limit and temporary-interface constraint. A simultaneous sudden-death changeover concentrates risk and provides no opportunity to learn from an early deployment. A function-by-function approach may be unsuitable because the scenario provides no evidence that the old and new functions can safely coexist in that way.

Question 2

New Single answer

Topic: 1. Projects and Project Work

Skill tested: Distinguishes project initiation information from detailed stage-level planning.

A public-sector agency has approved a project to introduce a secure online licensing service. The sponsor asks the project manager to prepare the first controlled document after the initial terms of reference. The document must establish the project's objectives, scope, governance, initial business justification, major risks, quality approach and how delivery will be controlled. Detailed task estimates and resource assignments for the first delivery stage are not yet reliable. Which document is the most appropriate next step?

Correct Answer: D. A project initiation document that establishes the project's management and control foundations.
Explanation:

A project initiation document provides a controlled basis for authorising and managing the project, bringing together its objectives, scope, business justification, governance, risks and quality and control arrangements. It is appropriate when detailed stage-level estimates are not yet dependable. A stage plan is more detailed and should be produced for a defined stage, not substituted for the overall initiation basis. A post-project review and an inspection record arise later and address operational results or specific product quality, not project initiation.

Question 3

New Single answer

Topic: 2. Project Planning

Skill tested: Uses activity-network dependencies and float to identify the controlling path.

A data-migration project has four activities. A takes 3 days and starts first. B takes 4 days and follows A. C takes 6 days and also follows A. D takes 2 days and cannot start until both B and C finish. Durations are elapsed working days, and resource limits do not alter the sequence. The project manager needs to determine which activity sequence controls the earliest completion date and where schedule flexibility exists. Which statement is correct?

Correct Answer: A. The critical path is A-C-D, and B has 2 days of total float.
Explanation:

The A-B-D path takes 3 + 4 + 2 = 9 days, while A-C-D takes 3 + 6 + 2 = 11 days. The longer path, A-C-D, controls the earliest project completion. Since B can finish two days later without delaying the point at which D can start, B has 2 days of float. D having two predecessors does not make both paths critical; only a path whose delay moves the project finish has zero total float under these assumptions.

Question 4

New Multiple answers

Topic: 2. Project Planning

Skill tested: Builds a product-based plan and clarifies product relationships before scheduling activities.

A consultancy is planning a regulatory reporting system. The project manager has been asked to show what the project must produce before estimating the work and schedule. The system includes a reporting application, an interface specification and a tested interface. The tested interface is derived from the specification and is a component of the integrated system release. The team has previously started coding before agreeing on product acceptance criteria, causing rework. Which TWO planning actions are most appropriate now? Select TWO.

Correct Answer: A. Create product descriptions that define acceptance and quality criteria for the key products.; D. Create a product breakdown structure that identifies the required products and their component relationships.
Explanation:

A product breakdown structure makes the required outputs and their component relationships explicit, while product descriptions clarify each product's purpose and acceptance or quality criteria. Together these address the team's history of beginning work without agreeing what acceptable outputs look like. Activities describe work done to create products; they are not interchangeable with the tested interface itself. Scheduling coding before defining the products risks repeating the same rework, and milestones mark significant points rather than replacing product definitions or relationships.

Question 5

New Multiple answers

Topic: 3. Monitoring and Control

Skill tested: Selects complementary progress evidence and reporting methods for effective project control.

A software project has begun system integration testing. The project manager's weekly report currently relies on verbal estimates from team leads, but the board has found that reported progress does not match the defect backlog or completed work. The organisation wants evidence that can be checked against planned outputs, early visibility of changes affecting scope, and a concise view of cumulative expenditure compared with the plan. The board does not expect the project manager to calculate earned value figures. Which TWO actions best improve monitoring and reporting? Select TWO.

Correct Answer: A. Collect regular progress against defined work and products, corroborating team updates with completed deliverables and test evidence.; D. Use an accumulative resource or cost chart to present actual cumulative expenditure against the planned profile.
Explanation:

Progress control needs timely, verifiable information tied to planned activities and products; completed outputs, test evidence and team updates provide stronger corroboration than unsupported verbal percentages. An accumulative chart can show whether resource use or expenditure is tracking the planned profile and supports concise reporting. Waiting until acceptance removes the opportunity to identify and correct variance during delivery. Escalating every defect to the board confuses operational issue handling with governance and does not replace routine reporting.

Question 6

New Single answer

Topic: 3. Monitoring and Control

Skill tested: Applies tolerance and exception escalation when forecast variance exceeds delegated authority.

A project board has authorised the current stage with a delivery tolerance of five working days. During the stage, the project manager learns that a supplier delay is likely to push the stage end date out by eight working days. The team has identified a recovery option, but it would require the board to accept a revised delivery date and additional cost. No urgent safety or legal issue requires immediate intervention. What should the project manager do next?

Correct Answer: A. Prepare and submit an exception report, including the forecast variance and recovery options, for the board's decision.
Explanation:

The forecast is already outside the project manager's delegated tolerance, so the matter should be escalated through the agreed exception process before the stage's authority is exceeded. An exception report should state the forecast variance and provide options, enabling the board to decide whether to revise the plan or take another course. Acting first would commit the project to changes beyond authority. Waiting for the delay to become actual ignores forecast-based control, while shifting cost to the supplier without agreement does not resolve the governance issue.

Question 7

New Single answer

Topic: 4. Change Control and Configuration Management

Skill tested: Evaluates change requests through impact analysis and formal change authority.

During development of a hospital appointment system, clinicians request a new triage field that could affect the user interface, data migration, training and the approved business case. The team believes the change is valuable and can implement it quickly, but the current release baseline has already been approved. The project manager has authority to assess requests but not to approve changes that alter scope or business benefits. What is the most appropriate action?

Correct Answer: A. Record the change request, assess its impact on products, schedule, cost, quality and business case, then submit it to the authorised change body for a decision.
Explanation:

A controlled change process records the request, assesses its consequences - including effects on the baseline and continuing business justification - and sends it to the body with authority to approve or reject it. This preserves traceability and prevents an informal scope change from undermining plans or benefits. Implementing first and baselining later reverses the control sequence. Refusing every change is not the purpose of change control, and deferring the change without evaluation does not address its potential business value or operational implications.

Question 8

New Single answer

Topic: 5. Quality

Skill tested: Differentiates quality assurance from product-level quality control activities.

A software supplier is delivering a payroll interface to a financial services firm. The firm wants confidence both that the supplier's development process is capable of producing compliant outputs and that the specific interface meets its agreed requirements. The supplier offers a process audit, a demonstration of its quality procedures, and test results for the interface. Which approach best addresses both needs?

Correct Answer: D. Use the process audit and review of quality procedures for assurance, and inspect test evidence and interface results for product control.
Explanation:

Quality assurance provides confidence that appropriate processes and procedures are in place and followed; it focuses on the way work is managed. Quality control checks whether a particular product meets its defined requirements, using activities such as inspection and testing. A process audit cannot prove that a specific interface has no defects, while a successful product test does not establish that the supplier's process is consistently controlled. User acceptance testing is useful for operational acceptance but does not replace either process assurance or product-level verification.

Question 9

New Single answer

Topic: 5. Quality

Skill tested: Chooses test levels that isolate defects and confirm integrated user requirements.

A logistics company is testing a new dispatch system. Developers have verified individual calculation routines, but the first combined build fails when the dispatch service sends data to the warehouse interface. The interface is corrected, and the project team now needs to verify that the connected components exchange data correctly and then confirm that the completed workflow supports dispatch staff's business needs before release. Which sequence is most appropriate?

Correct Answer: C. Perform integration testing on the connected components, followed by user acceptance testing of the business workflow.
Explanation:

Integration testing focuses on interactions between combined components, directly addressing the failure at the service-to-warehouse boundary. Once those interfaces work, user acceptance testing lets intended users assess whether the end-to-end workflow meets their business needs. Repeating unit tests alone does not establish that components communicate correctly. User acceptance testing is not a substitute for component integration testing, and process audits or peer reviews do not demonstrate that the operational workflow behaves as required.

Question 10

New Single answer

Topic: 6. Estimating

Skill tested: Applies size-based productivity data while accounting for project-specific productivity factors.

A team must estimate the effort for a new data-entry application. A senior manager proposes a target of 30 person-days based on the funding limit. The project manager has measurements from several comparable completed applications, expressed as function points delivered per person-day, but the new team includes less experienced developers and will use an unfamiliar reporting tool. The scope is reasonably understood, while the target date is negotiable. Which approach provides the most defensible initial effort estimate?

Correct Answer: A. Estimate application size using function points, apply relevant historical productivity data, and adjust the rate for the team's experience and tool unfamiliarity.
Explanation:

A size-based estimate uses an explicit size driver and productivity rates drawn from comparable completed work, then considers factors that make the new project different. Less experienced staff and an unfamiliar tool may reduce productivity, so they should be reflected in the estimate rather than ignored. A funding limit is a constraint or target, not evidence of the effort required. Choosing a date first risks circular reasoning, and assuming the best historical rate ignores the stated differences and can produce an unrealistic commitment.

Question 11

New Single answer

Topic: 7. Risk

Skill tested: Prioritises project risks by considering probability, impact and proportionate response cost.

A retailer's new inventory system depends on a data conversion that has not yet been rehearsed. The team identifies two risks: a low-probability conversion failure that could prevent opening for several days, and a high-probability formatting defect that would require a short manual correction. A full independent conversion rehearsal would reduce the first risk substantially but consume a large portion of the remaining test budget. The opening date is commercially important, and a limited rehearsal is feasible. What is the best risk-management approach?

Correct Answer: B. Prioritise the conversion failure based on its exposure, assess the value and cost of a limited rehearsal, and record an agreed contingency for residual risk.
Explanation:

Risk prioritisation considers both likelihood and potential impact, so a low-probability event with severe consequences may merit more attention than a frequent, easily corrected defect. The response should be proportionate: evaluate what a limited rehearsal can reduce, compare its cost with the exposure, and plan a contingency for what remains. Automatically choosing the full rehearsal ignores the budget and the cost-benefit decision. A supplier may share responsibility, but transferring a risk does not eliminate the project's need to monitor and plan for it.

Question 12

New Multiple answers

Topic: 8. Project Communications and Project Organisation

Skill tested: Assigns project governance and delivery responsibilities to appropriate roles.

A matrix-managed project is building a customer identity service for several business units. The sponsor expects the project board to decide whether the business case remains viable and to resolve major issues outside the project manager's authority. The project manager is responsible for day-to-day delivery, while technical specialists report to their functional managers as well as contributing to project work. The organisation also has a project support office that can maintain common records. Which TWO allocations of responsibility are most appropriate? Select TWO.

Correct Answer: D. The project manager coordinates delivery, monitors progress and manages within the authority delegated by the board.; E. The project board provides direction and makes decisions on major issues and continued business justification.
Explanation:

The project board provides governance, including direction, major decisions and oversight of continuing business justification. The project manager manages day-to-day delivery within the authority and tolerances delegated by that board. A project support office can provide administrative and information support, but it does not automatically own the business case or approve scope changes. Matrix reporting does not transfer product acceptance solely to functional managers, and a team leader cannot unilaterally alter project tolerances.

Question 13

New Single answer

Topic: 8. Project Communications and Project Organisation

Skill tested: Selects communication arrangements suited to distributed teams and shared decision-making.

A project team includes analysts in two offices and a security architect who works remotely. The team must resolve a design issue that requires rapid discussion, shared review of a complex diagram and a decision recorded for later reference. Travel is not funded, and not everyone can attend at the same physical location. Which communication arrangement is most appropriate for the decision session?

Correct Answer: A. Hold a scheduled real-time online meeting with shared visual materials, then circulate a written record of the decision and actions.
Explanation:

A real-time online meeting supports immediate clarification and joint inspection of the diagram despite participants being in different places. A written decision and action record preserves the outcome for later reference and project control. Email may be useful for review, but independent asynchronous replies are poorly suited to resolving a complex issue that needs rapid shared discussion. Posting a document without an explicit decision process can leave disagreement hidden, while delegating the decision to one participant excludes necessary stakeholders.