Question 1
Topic: Pre-Design Preparation
Skill tested: Evaluate regulatory, financial, and forecast inputs before selecting an OSP design basis.
A municipality is planning a fiber route through an area where the roadway will be reconstructed in three years. The client's current forecast supports a small initial fiber count, but the forecast shows substantial growth in enterprise connections over the next decade. The route crosses public right-of-way and a railroad property, and the funding plan requires a defensible comparison of initial and lifecycle costs. Before fixing the route and cable capacity, what should the designer do FIRST?
The design basis must incorporate applicable authorities, existing infrastructure information, forecast demand, and financial criteria before the designer commits to a route or capacity. Early railroad and right-of-way requirements can materially affect alignment, construction method, schedule, and cost. The current-only design in A risks premature capacity limitations and delayed approvals. C assumes both route feasibility and a suitable cable size without validating records or lifecycle value. D postpones critical constraints until they are expensive to address.