Limited-Time Offer: Enjoy 50% Savings! Ends in 00h 00m 00s Coupon code: 50OFF
Skip to content

Free BICSI Registered Communications Distribution Designer Exam RCDDv14.1 Exam Questions

Page: 1 / 22 Total 320 questions

Want more questions? Get Premium Access.

Question 1

In which phase of the protect design would an ICT distribution designer be expected to prepare preliminary cost estimates?

Correct Answer: B. SD

Question 2

A program manager joins a learn to fix a troubled enterprise-wide customer relationship management (CHM) system Analysis indicates that duplicate customer information data is resulting in redundant client information. The program manager accesses the knowledge repository tor similar programs to gather historical data and trends. A corrective action is identified, and a change in process is implemented to regain data integrity

What should the program manager do with the knowledge gained from this activity?

Correct Answer: C. Update the lessons learned database

Question 3

The ICT distribution designer is hired to design a Telecommunications Room on the third floor of a building. The size of the floor is 20 m by 26 m (92 x 85 It). What is to be the MINIMUM size of the TR?

Correct Answer: B. =3 m (10 ft) by = 2.40 m (8 ft)

Question 4

An IT-related program has a critical team in a region experiencing a crisis. Due to uncertainty about the region's changing environment a company's senior leadership asks the program manager to decrease dependencies on the critical team that should the program manager do to mitigate the Impacts of this request?

Correct Answer: D. Revisit the program management plan to clearly identify how decreasing critical team dependencies will impact component projects

Question 5

A program manager is assigned to a large cross-functional program trial includes five different technologies and multiple workstreams.

Some potential stakeholders have conflicting program expectations

What should the program manager do next/?

Correct Answer: C. Document stakeholder expectations in the program's risk register to determine their influence

Question 6

The transfer of unwanted signals may occur over one path or several paths. What method addresses the mitigation or suppression of unwanted signals?

Correct Answer: B. Bonding and grounding

Question 7

An RFQ usually provides more detail than RFP in selecting material such as:

Correct Answer: D. color.

Question 8

Which two of the following are included in the ICT distribution designer's role of vendor and contractor coordination'? (Select two options.)

Correct Answer: D. Communicate status to stakeholders; E. Assist in the resolution of unforeseen conditions, change orders. RFIs, and changes to the project's critical path

Question 9

A company's marketing department Tails an internal compliance audit To comply with the auditor's remediation plan the legal department mandates that a content management system (CMS) be implemented After initiating the program for CMS implementation the program manager discovers that the marketing department has already preselected which CMS technology will be implemented.

What should the program manager do to ensure the success of the program?

Correct Answer: B. Host a kick-off meeting, request preliminary requirements from the marketing department, conduct a design session present the steering committee with a solution that meets the requirements: and meet with interested vendors

Question 10

A component is scheduled to close at the end of the week. What should the program manager verity prior to allowing the component to close?

Correct Answer: B. The component has met the quality requirements to meet program objectives

Question 11

A program manager needs to establish direction and identity the essential aspects of a program. In addition, they must ensure that the context and framework of the program are properly defined assessed and documented

Which document will be created to support this activity?

Correct Answer: D. Program scope statement

Question 12

A large international manufacturing company is centralizing its IT which is currently spread over 16 countries. The transition means physically regrouping the infrastructure and aligning processes and organizations The high-level scope of this transformation encompasses three main areas.

1. The technology area---assessing which technology/tooling should be retained for the target data center

2. The policies and procedure area-aimed at establishing a common set of processes supporting the new way of delivering services

3. The HR area-assuring the new organization best fits the diversity of the countries and functional domains, while offering equivalent compensations for comparable functions

You have selected your team and you are preparing the business case to support 1) the team selections you made and 2) your recommendation to proceed to the program's next phase

Which document should be present m your business case?

Correct Answer: D. A cost/benefit analysis of the different scenarios, presenting their respective contributions

Question 13

Which two of the following items should be considered for inclusion in a comprehensive working outline of a SoW? (Select two options.)

Correct Answer: A. Schedule; D. Technical considerations

Question 14

The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan determine that project. A can wait until the resource becomes available, and assigns the resource to project B.

This is an example of which of the following?

Correct Answer: C. Resource interdependency management

Question 15

The project manager of project A develops a communications management plan. The project manager of project B is new and is uncertain how to develop appropriate communications for the company's staff

What should the program manager do to ensure communications on the component projects are consistent?

Correct Answer: D. Rework the communications management plans for all projects to be consistent