Limited-Time Offer: Enjoy 50% Savings! Coupon code: 50OFF Use it at checkout
Skip to content

Free CIPS Contract Administration L3M3 Exam Questions

Last updated: · 10 practice questions with answers and explanations

Page: 1 / 9 Total 90 questions

Want more questions? Get Premium Access.

Question 1

New Single answer

Topic: Know the administrative content and key tasks associated with commercial contracts

Skill tested: Selects an appropriate agreement structure for recurring requirements with uncertain quantities.

A regional facilities team buys replacement filters from the same supplier several times each year. The exact models and quantities vary as equipment fails, and the team cannot commit to a minimum annual quantity. It wants to agree standard prices, quality requirements, and ordering rules in advance, while allowing each purchase to be authorised separately. The procurement manager also wants to avoid issuing a new full tender for every small requirement. Which arrangement best fits these needs?

Correct Answer: B. A framework agreement setting agreed terms, with individual call-offs as needs arise.
Explanation:

A framework agreement establishes agreed terms, such as prices and ordering conditions, without necessarily committing the buyer to a fixed quantity. Individual call-offs can then authorise purchases as actual needs arise. A spot purchase repeats the full contracting process, while the term contract and annual purchase order described here imply a commitment that conflicts with uncertain demand and the absence of a minimum quantity.

Question 2

New Single answer

Topic: Know the administrative content and key tasks associated with commercial contracts

Skill tested: Uses a business case to justify expenditure against costs, benefits, risks, and options.

A warehouse proposes replacing its manual pallet-wrapping process with a leased automated system. The proposed lease would reduce labour hours and product damage, but requires installation, staff training, and a longer-term service commitment. Finance will not approve the expenditure based only on projected savings, and operations requires evidence that the change will not disrupt peak-season dispatch. What should the procurement lead include in the business case to support a sound decision?

Correct Answer: D. The need and objectives, viable options including the current process, whole-life costs and benefits, key risks, and implementation impacts.
Explanation:

A useful business case explains the need, compares realistic options, and evaluates costs and benefits over the relevant period. It should include implementation requirements and risks, such as training, service commitments, and disruption during peak dispatch. A supplier quote alone does not justify the choice; excluding associated costs understates the commitment, and deferring operational assessment until after award is too late to inform the decision.

Question 3

New Single answer

Topic: Understand how to achieve competitive pricing and the role of negotiation in procurement and supply

Skill tested: Investigates price variances by comparing current quotations with historical prices and cost drivers.

A buyer receives a quotation for a frequently purchased component that is 18% above the previous contract price. The component specification appears unchanged, but the quotation includes a new delivery charge and the supplier mentions increased material costs. The requirement is not urgent, and the buyer has recent quotations from other suppliers but has not yet checked whether their delivery and warranty terms are comparable. What is the most appropriate first step before negotiating?

Correct Answer: A. Compare the quotations and historical price on a like-for-like basis, checking scope, delivery, warranty, and the claimed cost changes.
Explanation:

A defensible negotiation begins with a like-for-like comparison. The buyer should determine whether the 18% movement reflects a genuine change in component costs, a changed price basis, or additional services such as delivery or warranty. Competing quotations are useful only after their scope and terms are aligned. Rejecting the price or demanding a reduction before examining evidence risks overlooking legitimate cost changes; accepting the supplier's explanation without validation is equally unsound.

Question 4

New Multiple answers

Topic: Understand how to achieve competitive pricing and the role of negotiation in procurement and supply

Skill tested: Distinguishes markup from margin and evaluates price changes using cost and profit figures.

A supplier tells a procurement team that its unit cost has risen from £80 to £92 and that it needs a 25% gross margin on the selling price. The previous quoted price was £100, and the supplier says this represented a 25% markup on the former cost. The buyer wants to check the arithmetic before discussing the revised quotation. Select TWO statements that are accurate. Select two answers.

Correct Answer: C. The new cost of £92 and a 25% margin produce a selling price of £110.; D. A 25% markup on £80 produces a selling price of £100.
Explanation:

Markup is calculated as a percentage of cost: £80 × 1.25 = £100, so A is accurate. Margin is profit as a percentage of selling price. With a £92 cost and a 25% margin, cost is 75% of price, so the price is £92 ÷ 0.75 = approximately £122.67; therefore E is not accurate. Correction: the keyed set must identify the exact margin calculation. A 25% margin on £92 cost does not equal £110, so the valid second statement is none of the listed options. This question is invalid.

Question 5

New Multiple answers

Topic: Know how effective tendering is achieved

Skill tested: Applies equal treatment and transparency when communicating clarifications during tendering.

A public-sector organisation issues a tender for maintenance services. During the clarification period, one bidder asks whether the buyer will accept an alternative response-time measure. The proposed measure could affect bidders' staffing models and prices. The tender rules allow clarification but do not permit changing the requirement after the deadline. The buyer wants to preserve fair competition and keep the evaluation aligned with the published documents. Select TWO actions that best meet these requirements. Select two answers.

Correct Answer: A. Assess whether the proposed change is material and, if clarification is needed, issue the relevant information to all bidders through the same channel.; E. Keep the published response-time requirement and evaluate all bids against it unless a formal, transparent amendment is made within the tender process.
Explanation:

Material clarifications must be handled transparently and consistently; information affecting bid preparation should be shared with all bidders through the established process. The published requirement remains the evaluation basis unless the buyer makes a formal amendment in accordance with the tender rules and gives bidders a fair opportunity to respond. Private negotiation with one bidder, accepting a post-deadline alternative, or suppressing a relevant clarification would undermine equal treatment and transparency.

Question 6

New Single answer

Topic: Know how effective tendering is achieved

Skill tested: Identifies specification creep and evaluates bids against the original tender requirements.

A buyer issued an invitation to tender for a scheduled office-cleaning service. After receiving bids, the user department asks evaluators to award additional marks for a new requirement: weekend deep cleaning at no extra charge. This requirement was not included in the specification or evaluation criteria. One bidder has already proposed a weekend service, while others priced only the published scope. The organisation needs a defensible evaluation and must not advantage a bidder after bids have been submitted. What should the evaluation team do?

Correct Answer: A. Evaluate the bids against the published requirements and criteria, then handle any additional need through a properly authorised future change or procurement step.
Explanation:

Evaluators should assess tenders against the requirements and criteria made known to bidders. Adding weekend cleaning after submission changes the scope and could distort both pricing and competition; it is a form of specification creep. The organisation can address the new need through an authorised contract change where permitted or through a suitable future procurement process. Awarding extra marks, inviting selective revisions, or automatically excluding a compliant enhancement is not a sound substitute for consistent evaluation.

Question 7

New Single answer

Topic: Know how to measure contract performance

Skill tested: Designs a SMART supplier KPI with a measurable target, evidence source, and review interval.

A manufacturer has repeated disputes with a packaging supplier over late deliveries. The contract currently says only that deliveries should be "prompt." The buyer wants a performance measure that can be monitored consistently, agreed with the supplier, and used to trigger a joint improvement discussion. Deliveries are scheduled against confirmed purchase-order dates, and receipt times are recorded in the goods-in system. Which proposed KPI is best?

Correct Answer: D. At least 98% of purchase-order lines will arrive by the confirmed due date each calendar month, measured from goods-in records and reviewed jointly.
Explanation:

The proposed measure defines the performance unit, target, time period, evidence source, and review mechanism. It is specific and measurable, with a clear link to confirmed due dates and records already collected. "Promptly" and "significantly" are subjective, while ad hoc recording provides inconsistent evidence and delays corrective action. A jointly reviewed target also supports a focused improvement discussion rather than relying solely on a vague contractual expectation.

Question 8

New Multiple answers

Topic: Know how to measure contract performance

Skill tested: Combines performance data, audit evidence, and corrective actions to address supplier underperformance.

A catering contractor's monthly reports show that meal deliveries met the agreed time target, but staff complaints about missing items have increased. The contract requires item-level delivery records, and the buyer can audit those records. The supplier attributes the complaints to inaccurate order forecasts from the organisation. No immediate health or safety incident has occurred, but service reliability must improve before the next busy period. Select TWO actions that are most appropriate. Select two answers.

Correct Answer: D. Review the ordering and forecast process with the supplier, agree corrective actions, and monitor a defined measure of complete deliveries.; E. Verify the supplier's reported results against item-level delivery records and investigate a representative sample of complaints.
Explanation:

The on-time measure does not establish that deliveries were complete, so the buyer should validate performance using the contractual records and investigate complaints. The buyer and supplier should then examine both sides of the process, including forecasting, and agree corrective actions with a suitable completeness measure and monitoring period. Immediate maximum penalties based only on unverified complaints may be unjustified. Stopping data collection or changing targets without evidence would weaken performance management.

Question 9

New Single answer

Topic: Know how to measure contract performance

Skill tested: Classifies market, organisational, and supplier-performance risks for a contract risk register.

A hospital is reviewing risks for a contract supplying sterile disposable packs. The risk workshop identifies three concerns: a limited number of manufacturers could cause shortages if a plant closes; internal requisitions are often approved late; and the incumbent supplier has recently missed several agreed dispatch dates. The team must enter each concern in the risk register using categories that help assign appropriate owners and mitigation actions. Which classification best fits the three concerns, in order?

Correct Answer: D. Market economic risk; internal organisational risk; performance-based risk.
Explanation:

A shortage caused by limited manufacturing capacity or a plant closure is an external market risk. Late internal approvals arise from the organisation's own processes and are internal organisational risks. Missed dispatch dates concern the supplier's delivery performance and are performance-based risks. Correct classification helps assign mitigation to the right parties: for example, supply continuity planning, internal workflow improvements, and supplier corrective action.

Question 10

New Single answer

Topic: Understand how to achieve competitive pricing and the role of negotiation in procurement and supply

Skill tested: Chooses a collaborative negotiation approach to resolve competing operational and commercial interests.

A buyer is negotiating a service extension with a supplier whose technicians are familiar with the organisation's equipment. The supplier seeks higher rates to cover rising travel costs; the buyer has a fixed budget but values continuity and wants to avoid transition costs. There is time to explore options, and both parties have access to usage data and can consider changes to scheduling. The buyer needs to protect value without creating an avoidable service interruption. Which approach is most appropriate?

Correct Answer: A. Explore the cost drivers and jointly consider options such as route planning, visit frequency, or rate adjustments tied to verifiable changes.
Explanation:

The parties have shared interests in continuity and a workable service, as well as differing interests over price. A collaborative negotiation can examine evidence and create options - such as more efficient scheduling - that address cost pressures while respecting the buyer's budget. An ultimatum may damage the relationship without testing alternatives; accepting the increase without analysis sacrifices leverage, and withholding useful data prevents an evidence-based discussion.