Limited-Time Offer: Enjoy 50% Savings! Coupon code: 50OFF Use it at checkout
Skip to content

Free CIPS Managing Contractual Risk L5M3 Exam Questions

Last updated: · 12 practice questions with answers and explanations

Page: 1 / 12 Total 120 questions

Want more questions? Get Premium Access.

Question 1

New Single answer

Topic: Understand the legal and process issues relating to the formation of contracts

Skill tested: Assesses contract formation risks when an acceptance changes the supplier's offer.

A public-sector buyer issues a purchase order for specialist equipment, incorporating its standard terms. The supplier's quotation had stated that its own terms would apply, including a different warranty period and a liability cap. The supplier replies, "We accept the order, subject to our quoted warranty and liability terms," and begins manufacturing. The buyer needs the equipment urgently but has not acknowledged the qualification. Which action should the buyer take first to reduce uncertainty about the governing terms?

Correct Answer: C. Confirm in writing that the supplier's response is not accepted and obtain an unqualified agreement to clearly identified terms before proceeding.
Explanation:

The supplier's response expressly qualifies its purported acceptance by changing important terms. It may therefore operate as a counter-offer rather than an unqualified acceptance, leaving uncertainty about whether a contract has formed and which terms apply. The buyer should reject or resolve the qualification and record an unambiguous agreement before further performance. The purchase order does not automatically prevail merely because the buyer issued it, and waiting until a dispute arises increases risk. A revised order without clear agreement may perpetuate the exchange-of-forms problem rather than resolve it.

Question 2

New Multiple answers

Topic: Understand the legal and process issues relating to the formation of contracts

Skill tested: Evaluates document precedence and controlled processes for agreeing contractual variations.

A facilities-management contract comprises a signed agreement, a service specification, a supplier proposal and the buyer's standard conditions. The documents contain inconsistent response times and different reporting requirements. During a service review, both parties agree to add a new monthly report and change one response time. The contract requires changes to be signed by authorised representatives but says nothing about which existing document prevails if terms conflict. Which TWO actions best reduce the risk of later disagreement? Select TWO.

Correct Answer: B. Use an agreed order-of-precedence clause to identify which document governs each conflict.; C. Record the agreed changes in a signed variation that identifies the affected provisions and confirms the continuing terms.
Explanation:

An express precedence clause gives the parties a predictable method for resolving inconsistencies among the signed agreement, specification, proposal and standard conditions. The agreed operational changes should also be captured in a signed variation that identifies what changes and what remains in force, consistent with the stated amendment procedure. Recency or greater detail does not necessarily determine priority unless the contract says so. Informal meeting minutes or unilateral implementation may fail to satisfy the contract's authority and signature requirements.

Question 3

New Single answer

Topic: Understand the legal and process issues relating to the formation of contracts

Skill tested: Assesses allocation and verification of supplier insurance risk against contractual exposure.

A buyer is sourcing maintenance work at a high-value production site. The draft contract requires the supplier to indemnify the buyer for specified third-party injury and property-damage claims caused by the supplier's negligence. The supplier provides a certificate showing public liability insurance, but it expires shortly before the proposed contract term ends. The buyer cannot accept uninsured exposure and does not want to assume that an insurance certificate proves every indemnity is covered. What is the best next step before award?

Correct Answer: A. Require the supplier to maintain appropriate insurance for the contract period, verify relevant coverage and limits against the risks, and provide renewed evidence as required.
Explanation:

The buyer should align the supplier's insurance obligations with the contract risks and duration, and verify that the evidence is current and relevant. A certificate is evidence of insurance at a point in time; it does not itself establish that every contractual indemnity is insured or that cover will remain in force. Removing the indemnity changes the risk allocation, while relying on an assumed automatic extension is unsafe. The buyer's own insurance may be prudent, but it does not replace appropriate supplier coverage and contractual verification.

Question 4

New Single answer

Topic: Understand the legal and process issues relating to the formation of contracts

Skill tested: Assesses balanced force majeure drafting and the distinction from ordinary supplier difficulty.

A manufacturer supplying a critical component requests a broad force majeure clause covering any event beyond its control, including shortages, increased costs and failure of its subcontractors. The buyer can tolerate temporary interruption only if it receives prompt notice, mitigation and reliable recovery information; prolonged unavailability would require an exit route. Which drafting approach best manages this risk?

Correct Answer: D. Define qualifying events and exclusions, require timely notice and reasonable mitigation, set out the effect on affected obligations, and provide an appropriate termination right for prolonged disruption.
Explanation:

A workable clause defines the circumstances that qualify, identifies exclusions such as ordinary commercial difficulty where appropriate, and establishes notice, mitigation and consequence requirements. A time-limited termination mechanism protects the buyer if disruption persists. A broad automatic excuse can transfer excessive supply risk to the buyer, while an absolute no-excuse obligation may be impractical and may not address legal impossibility. Subcontractor failure should not automatically excuse the prime supplier; its treatment should be expressly negotiated.

Question 5

New Single answer

Topic: Understand the impact of breach of contract and approaches for managing breach.

Skill tested: Distinguishes anticipatory repudiation from an actual failure to perform and selects a measured response.

A supplier is due to deliver a production line in six weeks. In a formal letter, it states that it will not deliver unless the buyer accepts a substantial price increase that is not permitted by the contract. No delivery date has yet passed. The buyer has a replacement source but needs time to secure it and wants to preserve its legal position. What is the most appropriate immediate response?

Correct Answer: A. Document the statement, obtain legal advice, and issue a clear response reserving rights while assessing whether to affirm the contract or accept the repudiation and terminate.
Explanation:

A clear advance statement that the supplier will not perform on the agreed terms may amount to anticipatory repudiation. The buyer should preserve the evidence and make an informed decision about whether to affirm the contract or accept the repudiation, considering replacement supply and contractual notice requirements. Simply waiting may squander mitigation time. Accepting an unauthorised increase sacrifices the agreed position, while public accusations or immediate litigation may escalate matters without improving the buyer's options.

Question 6

New Multiple answers

Topic: Understand the impact of breach of contract and approaches for managing breach.

Skill tested: Selects proportionate negotiation, evidence and mitigation steps following repeated service failure.

A logistics provider has missed several agreed collection windows. The failures have caused production disruption, but the service agreement includes a cure process, service credits and a termination right for specified repeated failures. The relationship remains commercially valuable, and the buyer needs to protect its claim while seeking a stable recovery plan. Which TWO steps are most appropriate now? Select TWO.

Correct Answer: A. Maintain a dated record of missed windows, impacts, notices and the provider's responses, and calculate any credits using the agreed mechanism.; E. Issue the required formal notice and negotiate a time-bound recovery plan without waiving contractual rights.
Explanation:

A reliable evidence trail supports assessment of the failures, their impact and the service-credit calculation. The buyer should follow the agreed notice and cure process, while a time-bound recovery plan can address operational continuity without surrendering contractual rights. Immediate termination without checking the required procedure creates avoidable legal risk. Withholding all payments may itself breach the contract, and avoiding written records undermines both claim management and accountable negotiation.

Question 7

New Single answer

Topic: Understand the impact of breach of contract and approaches for managing breach.

Skill tested: Evaluates mediation as a non-binding dispute-resolution route before adversarial proceedings.

A buyer and supplier disagree about whether a series of delivery delays qualifies for contractual liquidated damages. Both want to preserve the commercial relationship, and senior managers believe a negotiated settlement may be possible. The contract provides for mediation before litigation, but does not make the mediator's outcome binding. The buyer needs a process that can facilitate settlement without handing decision-making authority to a third party. Which approach best fits?

Correct Answer: B. Use mediation under the contractual process, with both parties retaining control over whether to settle.
Explanation:

Mediation uses a neutral facilitator to help the parties explore settlement, but the parties retain control and are not bound to accept a proposal unless they agree to a settlement. This suits the stated aim of preserving the relationship and the contract's process. Arbitration ordinarily involves a third party deciding the dispute, while a mediator does not impose a binding award. Litigation is not automatically required simply because a disagreement has arisen, particularly where the contract calls for mediation first.

Question 8

New Single answer

Topic: Understand the impact of breach of contract and approaches for managing breach.

Skill tested: Assesses lawful mitigation through substitute supply while preserving contractual claims.

A supplier has failed to provide a specialist service after receiving the contractually required notice to remedy. The buyer must maintain operations and has identified another provider. The replacement provider needs access to the incumbent's work records and equipment, some of which are subject to contractual restrictions. The buyer also intends to claim losses caused by the failure. What is the best course?

Correct Answer: A. Review the contract and legal position on termination, records and access; document reasonable mitigation costs; and arrange a properly authorised transition while preserving claims.
Explanation:

The buyer should mitigate operational loss while respecting contractual rights and procedures governing termination, information, equipment and transition. A documented, reasonable substitute-supply arrangement can help limit losses and support a later claim, but access and transfer rights must be established rather than assumed. Delay may increase loss, whereas unverified transfer could create additional liability. Novation generally requires agreement of the relevant parties; it cannot simply be imposed unilaterally.

Question 9

New Single answer

Topic: Understand the legal implications of contractual non-conformance in procurement and supply

Skill tested: Distinguishes service credits from damages and applies the agreed performance remedy mechanism.

A managed-service contract measures monthly availability and provides a service-credit schedule for shortfalls. In one month, availability falls below the threshold and the buyer's finance team proposes deducting its full estimated business interruption loss from the invoice. The contract does not expressly state that service credits are the buyer's exclusive remedy, and it contains separate provisions on liability and claims. What should procurement do first?

Correct Answer: D. Apply the service credit according to the contract, then assess any additional loss under the relevant liability and claims provisions rather than assuming either automatic exclusivity or an unrestricted deduction.
Explanation:

The buyer should apply the remedy expressly provided for the measured performance failure, then interpret it alongside the contract's liability and claims provisions. A service credit may be the agreed adjustment for a service-level shortfall, but exclusivity should not be assumed where the contract does not say so. Nor does a breach automatically entitle the buyer to deduct an unverified estimate of all interruption losses; recoverability, limitations and claims procedures must be considered. Termination also depends on the contractual trigger and process.

Question 10

New Multiple answers

Topic: Understand the legal implications of contractual non-conformance in procurement and supply

Skill tested: Assesses enforceable liquidated damages design and notice-based administration for delay.

A buyer is drafting a contract for a time-critical installation. Delay is likely to cause measurable costs, but the amount will be difficult to prove precisely after the event. The buyer wants a pre-agreed delay remedy that is commercially defensible and administratively clear. Which TWO drafting or administration practices best support that aim? Select TWO.

Correct Answer: D. Set the amount by reference to a reasonable pre-contract estimate of the loss likely to result from delay and document the basis for it.; E. Define the delay trigger, calculation method, applicable cap or duration where appropriate, and any required notice or assessment process.
Explanation:

A defensible liquidated-damages provision should be agreed in advance and relate to a reasonable assessment of likely loss, rather than being designed as a punishment. Clear triggers, calculation rules and administration requirements make the remedy predictable and reduce disputes about when and how it applies. An arbitrary amount risks being treated as an unenforceable penalty under applicable law. A remedy cannot sensibly apply when its trigger has not occurred, and deferring the amount until after completion defeats the purpose of pre-agreement.

Question 11

New Single answer

Topic: Understand the legal implications of contractual non-conformance in procurement and supply

Skill tested: Selects a procedurally sound termination notice and distinguishes termination from rescission.

A supplier has repeatedly failed a critical quality requirement. The contract permits termination for specified repeated failures after written notice and an opportunity to remedy, and requires the notice to identify the breach and the effective termination date. The buyer's operations team wants to send an email stating that the contract is "cancelled immediately" and stop all payments. What should the buyer do?

Correct Answer: A. Verify the failure record and notice history, then issue a notice that meets the contractual grounds, content, delivery and timing requirements before taking termination steps.
Explanation:

Termination rights are exercised according to the contract's triggers and notice procedure. The buyer should verify that the required repeated failures and cure steps are established, then issue a notice that identifies the breach and effective date and is delivered as required. An informal cancellation email may be ineffective or itself expose the buyer to a claim. Termination generally ends future obligations subject to accrued rights; it does not automatically reverse all prior performance as rescission might in some legal contexts. Stopping performance without a valid termination risks buyer breach.

Question 12

New Multiple answers

Topic: Understand the legal implications of contractual non-conformance in procurement and supply

Skill tested: Evaluates termination consequences, accrued claims and transition obligations after supplier default.

A buyer validly terminates a supplier contract for persistent non-performance. The agreement contains an express handover obligation, confidentiality provisions, a liability cap, and rights to recover specified transition costs. The supplier disputes the buyer's loss calculation, while a replacement supplier must take over within two weeks. Which TWO actions best manage the legal and operational consequences? Select TWO.

Correct Answer: B. Follow the handover and confidentiality terms, secure records and assets needed for continuity, and document the transition.; E. Assess recoverable damages against the contract's remedies, exclusions, caps and evidence requirements, keeping disputed and undisputed amounts distinct.
Explanation:

Termination does not automatically erase accrued rights or the contract's surviving provisions. The buyer should carry out the agreed handover and protect confidential information while enabling service continuity. Any damages claim should be assessed against the contractual allocation of risk, including applicable caps, exclusions, specified remedies and evidence. Releasing accrued claims is not required merely because termination occurred. Public disclosure could breach confidentiality, and a handover obligation may expressly survive termination or be necessary to complete the agreed exit.