Limited-Time Offer: Enjoy 50% Savings! Coupon code: 50OFF Use it at checkout
Skip to content

Free CIPS Strategic Programme Leadership L6M5 Exam Questions

Last updated: · 15 practice questions with answers and explanations

Page: 1 / 9 Total 83 questions

Want more questions? Get Premium Access.

Question 1

New Single answer

Topic: Understand contracting for programmes

Skill tested: Compares client-coordinated delivery with single-point EPC responsibility for major programmes.

A public utility is planning a new treatment plant with a fixed capacity and a well-defined performance specification. Its engineering team can produce a complete design before tender, but the organization has limited capacity to coordinate multiple contractors and wants one party accountable for integrating design, procurement and construction. Early contractor involvement is desirable but not essential. Which approach best fits these requirements?

Correct Answer: C. An EPC contract with the contractor responsible for integrated design, procurement and construction
Explanation:

An EPC arrangement places responsibility for engineering, procurement and construction integration with a single contractor, matching the utility's limited coordination capacity and desire for a single point of accountability. A client-coordinated model and construction management leave the client coordinating separate contracts. Management contracting provides management of works packages but does not offer the same integrated EPC responsibility. A mature design can support several approaches, but it does not outweigh the stated integration requirement.

Question 2

New Multiple answers

Topic: Understand contracting for programmes

Skill tested: Distinguishes NEC compensation-event mechanisms from conventional variation and claims processes.

A transport authority is selecting a contract for a multi-year station programme with evolving interfaces and substantial uncertainty. The sponsor wants emerging risks discussed promptly, forecasts updated as events arise, and changes handled through a defined contractual process rather than accumulated into end-of-project disputes. It also wants the contract to support collaborative administration without assuming that all uncertainty can be removed before award. Which TWO features most directly support these aims? Select TWO.

Correct Answer: A. Use NEC early warning procedures to raise matters that could affect cost, time or performance and discuss mitigation.; B. Use the NEC compensation-event process to assess qualifying events and implement their effects on forecast cost and time.
Explanation:

NEC early warning procedures encourage timely notification and collaborative consideration of actions to avoid or reduce adverse effects. The compensation-event process provides a defined route for assessing qualifying events and their impact on forecast cost and time. These processes address emerging risk without relying on retrospective settlement. Deferring all change negotiation or replacing contract procedures with informal consensus weakens timely control. A fixed price does not itself eliminate uncertainty and would contradict a deliberate, transparent allocation of risk.

Question 3

New Single answer

Topic: Understand contracting for programmes

Skill tested: Selects an appropriate contract form by aligning risk allocation with design maturity and performance responsibility.

A consortium is procuring a process facility whose output quality and energy consumption are central to the business case. The consortium has defined output requirements but wants the supplier to complete the detailed design and build the facility. The consortium will operate the asset itself and does not want to transfer long-term operating responsibility or ownership to the supplier. Which form of contract most closely matches this allocation?

Correct Answer: C. A design-and-build or EPC arrangement with defined performance requirements and client operation after completion
Explanation:

Design-and-build or EPC lets the client specify required outcomes while the supplier develops detailed design and delivers the facility. The client can retain responsibility for operation after handover, as the scenario requires. Design-bid-build keeps detailed design with the client, contrary to the desired responsibility allocation. A design-build-operate-transfer form and a private finance partnership extend private-party responsibilities into operations, ownership or financing that the consortium expressly does not want.

Question 4

New Single answer

Topic: Understand contracting for programmes

Skill tested: Evaluates the risk and control trade-offs of fixed-price and cost-reimbursable programme pricing.

A procurement director is choosing a pricing mechanism for a project package. The scope, site conditions and acceptance criteria are sufficiently mature to price with reasonable confidence. The sponsor has a firm funding ceiling and wants the supplier to bear the risk of its own cost overruns, while retaining a contractual process for client-approved scope changes. Which mechanism is the best starting point?

Correct Answer: C. Fixed lump sum for the defined scope, with an agreed process for priced changes
Explanation:

A fixed lump sum is suited to a sufficiently defined scope and gives the sponsor greater price certainty, with the supplier bearing ordinary cost-overrun risk for that scope. A variation mechanism can still address client-approved changes without undermining the baseline. Cost reimbursement and time-and-materials expose the client to actual expenditure. Target cost shares overrun risk through its pain/gain arrangement, which conflicts with the stated preference that the supplier bear that risk.

Question 5

New Multiple answers

Topic: Understand contracting for programmes

Skill tested: Assesses how payment schedules and security instruments manage programme delivery and counterparty risk.

A buyer is preparing payment and security terms for a long-lead equipment package. The supplier must place substantial deposits with its own manufacturers, while the buyer wants evidence that payments correspond to delivered value and wants protection if the supplier fails before delivery. The buyer can accept staged payments but cannot rely on an unsecured advance. Which TWO contractual measures best balance these requirements? Select TWO.

Correct Answer: C. Use milestone payments tied to objectively verifiable design, manufacture, inspection or delivery evidence.; E. Where an advance is justified, require an appropriate advance-payment guarantee and define how it reduces as the advance is recovered.
Explanation:

Evidence-based milestone payments connect cash flow to demonstrable progress and provide the buyer with control over what has been earned. If commercial conditions justify an advance, an advance-payment guarantee can protect the buyer if the supplier fails to repay it; the guarantee's reduction should track recovery of the advance. An unsecured full advance transfers excessive risk. Withholding all payment until commissioning may be commercially unworkable, while unlinked overhead payments do not establish delivered value.

Question 6

New Single answer

Topic: Understand contracting for programmes

Skill tested: Matches public-private partnership structures to lifecycle responsibility and risk transfer.

A local authority needs a new civic facility but faces a constrained capital budget. It is considering a long-term arrangement under which a private partner would arrange finance, design and build the facility, then maintain it to specified service standards. The authority wants to retain public-service policy and control over service outcomes; it does not require the private partner to deliver the authority's core public service. Which arrangement is most consistent with these requirements?

Correct Answer: B. A private finance partnership with lifecycle obligations and service-performance requirements, while the authority retains policy control
Explanation:

A private finance partnership can combine private financing, design and construction with long-term maintenance or service obligations, subject to an agreed risk allocation and performance regime. The authority can retain policy responsibility and define service outcomes without transferring its core public function. Traditional direct funding does not meet the financing constraint and separates lifecycle responsibilities. Full privatization transfers more than required, while construction management does not provide the proposed integrated finance and maintenance structure.

Question 7

New Single answer

Topic: Understand contracting for programmes

Skill tested: Applies open-book costing and consortium governance to control a multi-supplier programme budget.

Several public agencies are procuring a shared digital infrastructure programme through a consortium. The work includes uncertain integration effort and common enabling services, and each agency needs confidence that pooled costs are allocated fairly. The consortium wants to retain the benefits of joint buying but must prevent disputes over overhead, savings and supplier charges. Which procurement control is most appropriate?

Correct Answer: D. Require open-book cost records, agree allocation and audit rules in advance, and establish joint governance for sourcing decisions.
Explanation:

Open-book records make cost components visible, while agreed allocation and audit rules provide a consistent basis for distributing shared costs and reviewing charges. Joint governance gives consortium members a legitimate process for sourcing decisions and oversight. Equal allocation without disclosure may be inequitable, and unilateral control undermines consortium participation. Separate contracts can sacrifice shared-buying benefits. A fixed price may be appropriate in some settings, but a blanket prohibition on reviewing assumptions or changes does not resolve the stated transparency and allocation concerns.

Question 8

New Multiple answers

Topic: Understand programme leadership approaches

Skill tested: Uses variance analysis and corrective control actions to manage programme cost and schedule performance.

A programme review shows that expenditure is below the approved profile, yet two critical deliverables are late and the forecast final cost has increased. Managers are proposing a budget cut because current cash outflow is low. The sponsor needs to understand performance before deciding whether to intervene, and the reporting system can provide planned value, earned value, actual cost and schedule forecasts. Which TWO actions should the programme leader take first? Select TWO.

Correct Answer: A. Compare earned progress with planned progress and actual cost, then investigate the causes of the schedule and cost variances.; C. Update the estimate at completion and schedule forecast using verified performance and remaining-work assumptions.
Explanation:

Low expenditure alone does not indicate good performance: it may reflect delayed work. Comparing earned progress, planned progress and actual cost exposes whether the programme is behind schedule or experiencing cost inefficiency. An updated estimate at completion and schedule forecast then supports a realistic decision about remedial action. Cutting budget before understanding remaining work risks making the shortfall worse. Deferring review ignores warning signs, and replacing the baseline without proper change control obscures performance rather than managing it.

Question 9

New Single answer

Topic: Understand programme leadership approaches

Skill tested: Applies value engineering to reduce whole-life cost without compromising required programme outcomes.

A hospital redevelopment programme is over its affordability threshold. A design review identifies a high-cost façade specification that exceeds the client's stated requirements for weather resistance, maintainability and energy performance. The clinical areas and statutory requirements must not be compromised, and the client expects the team to consider operating costs as well as construction costs. What is the best next step?

Correct Answer: A. Conduct a structured value-engineering review of façade functions and whole-life costs, then approve an alternative only if it meets required performance.
Explanation:

Value engineering examines the functions that matter and identifies alternatives that deliver those functions at lower whole-life cost. A structured review can compare capital cost, maintenance, energy performance and compliance before a change is approved. Simply removing performance requirements risks an unsuitable or noncompliant asset. Delaying decisions can increase change costs and disrupt delivery. Across-the-board clinical scope reductions are unrelated to the identified cost driver and may damage essential outcomes.

Question 10

New Single answer

Topic: Understand programme leadership approaches

Skill tested: Selects a fair and contractually defensible response to consequential loss and delay damages.

A supplier's late delivery of a critical module delays a programme, but the client also suffers lost downstream revenue. The contract contains a negotiated daily delay-damages rate for late completion, expressly stated to be the client's remedy for that delay, subject to applicable law. The client has no separate express indemnity for lost revenue. Before asserting a further consequential-loss claim, what should the programme leader do?

Correct Answer: C. Review the contract's remedy, exclusion and limitation provisions, establish causation and loss evidence, and obtain legal advice before claiming beyond the agreed remedy.
Explanation:

The agreed delay-damages provision and any related exclusions or limitations determine the contractual position, subject to applicable law. A further consequential-loss claim should not be assumed: the client must assess the contract, causation, evidence and the scope of the agreed remedy, with legal advice where needed. Automatically stacking lost revenue onto a remedy expressly stated to be exclusive may be inconsistent with the contract. Withholding the module's full value and immediate termination also ignore earned value and contractual conditions.

Question 11

New Multiple answers

Topic: Understand programme leadership approaches

Skill tested: Selects proportionate closeout controls for warranties, final accounts, records and residual obligations.

A programme is approaching handover of a complex facility. The asset can enter service after acceptance testing, but several minor defects remain, final accounts are not agreed, and warranty periods will begin under different package contracts. The operating team needs usable records and clear routes for future claims. The sponsor wants to close the programme responsibly without treating every residual obligation as a reason to delay beneficial use. Which TWO actions are most appropriate? Select TWO.

Correct Answer: A. Record and assign outstanding defects, acceptance status, warranty dates, claim routes and responsible owners in a controlled closeout register.; B. Complete handover with validated operating and maintenance information, and retain contract records needed to manage residual obligations.
Explanation:

A controlled closeout register makes residual defects, acceptance conditions, warranty periods and claims responsibilities visible, reducing the chance that rights are missed. Validated operating information and retained records allow the operator to use and maintain the facility while the organization manages continuing obligations. Immediate release of all security may prejudice unresolved matters. Waiting for warranties to expire is unnecessary, and rights should not be assumed to transfer automatically without checking the relevant contracts and documenting arrangements.

Question 12

New Single answer

Topic: Understand programme leadership approaches

Skill tested: Chooses proportionate remedial action using critical-path impact and verified supplier recovery evidence.

A specialist contractor reports a three-week delay on a non-critical package. The programme controls team confirms that the package has four weeks of available float and that no interface milestone is currently threatened. The contractor proposes an expensive acceleration plan involving additional shifts, but it has not provided a resource-loaded recovery schedule or evidence that acceleration will reduce the overall programme completion date. What should the programme leader do next?

Correct Answer: C. Assess the delay against float and interfaces, require a substantiated recovery proposal, and monitor whether the forecast threatens a key milestone.
Explanation:

A three-week delay within four weeks of float does not, by itself, establish a delay to programme completion. The leader should verify the schedule logic and interfaces, obtain evidence that the proposed acceleration is feasible and beneficial, and monitor float consumption. Immediate acceleration could incur cost without improving the completion date. Termination would be disproportionate absent a demonstrated failure requiring it. Omitting the package from reporting would conceal a developing risk rather than control it.

Question 13

New Single answer

Topic: Understand contracting for programmes

Skill tested: Uses contract-compliant change control to assess a variation's scope, cost, time and authority.

During construction, an operational manager asks a contractor to add a new access route to improve future maintenance. The request was not in the approved scope, could affect permits and may alter the completion date. The contractor is willing to proceed on a verbal instruction and submit its cost later. The programme leader must preserve the opportunity while maintaining budget authority, auditability and control of contractual entitlement. What is the best response?

Correct Answer: C. Route the request through authorized change control, assess its scope, cost, schedule, risk and approvals, then issue a formal instruction under the contract if approved.
Explanation:

Formal change control allows the organization to assess the operational benefit alongside cost, time, permit and risk impacts, obtain the required budget authority, and issue an instruction through the contract's prescribed process. This preserves a clear audit trail and reduces dispute risk. A verbal instruction followed by retrospective pricing may create avoidable entitlement and cost uncertainty. Permanent rejection is premature before assessment, while asking the contractor to proceed at its own risk does not remove the client's potential contractual exposure.

Question 14

New Single answer

Topic: Understand contracting for programmes

Skill tested: Assesses termination and specific-performance responses against contractual remedies and continuity needs.

A supplier has repeatedly missed milestones for a bespoke control system. The system is essential to commissioning, but the contract includes a staged cure process, termination rights for specified default, and provisions governing delivery of work in progress and technical information on termination. The supplier claims it can recover if granted another month, while the client's replacement supplier warns that transition could cause a longer delay. What should the programme leader do first?

Correct Answer: C. Apply the contractual cure and escalation process, verify the supplier's recovery evidence and transition options, and prepare a documented termination decision if default remains.
Explanation:

The programme leader should follow the agreed cure and escalation provisions, assess whether the proposed recovery is credible, and evaluate continuity and transition risks using the contract's rights over work in progress and information. This supports a defensible decision on whether termination is proportionate and executable. Immediate termination without checking transfer rights may delay recovery. Informal demands do not replace contract administration, while an unpriced waiver removes leverage without reliable assurance.

Question 15

New Single answer

Topic: Understand contracting for programmes

Skill tested: Integrates programme closeout decisions with asset handover, residual liabilities and supply-chain relationships.

A regional infrastructure programme has delivered its final asset, but several suppliers still owe training, records and defect corrections. The operating authority is taking over the assets, while the programme team is due to disband next month. Senior leaders want to release staff and close governance without losing contractual rights or leaving the operator unable to manage suppliers. Which approach is most appropriate?

Correct Answer: D. Complete a controlled transition: assign residual obligations and supplier contacts, transfer verified records, maintain necessary oversight and close governance against defined exit criteria.
Explanation:

Programme closure should distinguish completion of delivery governance from the continuing life of contractual obligations. A controlled transition assigns owners for training, records, defects and claims, equips the operator with verified information, and retains proportionate oversight. This enables the programme team to close against clear criteria without abandoning responsibilities. Immediate disbandment risks lost rights and capability. Keeping the programme open until every warranty expires is unnecessarily broad, and releasing security or relying on voluntary completion weakens the client's position.