Limited-Time Offer: Enjoy 50% Savings! Coupon code: 50OFF Use it at checkout
Skip to content

Free EC-Council ICS/SCADA Cyber Security ICS-SCADA Exam Questions

Last updated: · 10 practice questions with answers and explanations

Page: 1 / 8 Total 75 questions

Want more questions? Get Premium Access.

Question 1

New Single answer

Topic: Introduction to ICS/SCADA Network Defense

Skill tested: Assesses ICS asset characterization and threat modeling for safety-critical control environments.

A water utility is documenting a recently acquired treatment plant before connecting it to its corporate security monitoring program. The plant contains PLCs, an HMI, an engineering workstation, and a historian; several controllers have undocumented serial links, and maintenance staff are unsure which devices can tolerate active probing. The utility must identify critical assets and likely attack paths without risking process availability. What should the security team do FIRST?

Correct Answer: A. Build an asset and communication inventory using passive observation, approved records, and interviews, then validate findings with control engineers.
Explanation:

A validated inventory is the foundation for system characterization and threat modeling. Passive observation and operational records can reveal assets, communication relationships, and dependencies without exposing fragile or safety-critical devices to active probes. Control-engineer validation is important because undocumented serial links and process dependencies may not appear in network data. Scanning first can disrupt equipment, while hardening before understanding dependencies can impair operations. PLCs commonly cannot host general-purpose endpoint agents, so that approach is not a reliable discovery method.

Question 2

New Single answer

Topic: TCP/IP 101

Skill tested: Evaluates TCP and UDP header interpretation for diagnosing ICS network communication failures.

During a controlled investigation, an IDS records repeated TCP SYN packets from an engineering workstation to a PLC, but no SYN-ACK or RST returns. A packet capture shows the requests leaving the workstation with the expected destination IP and service port. The PLC is known to be operating, and the network team must isolate the likely fault without changing the control device. Which next step is MOST appropriate?

Correct Answer: C. Inspect the return path and intervening ACLs or firewall state for dropped or misrouted responses.
Explanation:

A TCP connection normally progresses from SYN to SYN-ACK and then ACK. If the request is observed leaving but no response returns, the return path, routing, or an intervening filtering device is a logical focus; the trace does not establish that the PLC itself is the fault. Window sizing applies after a connection is established, and changing to UDP does not solve a TCP service's reachability problem. Disabling sequence validation would not address the missing response and would weaken security.

Question 3

New Multiple answers

Topic: Introduction to Hacking

Skill tested: Assesses safe scoping and authorization decisions for penetration testing of operational control systems.

A manufacturer authorizes a security assessment of its production ICS. The signed scope permits review of perimeter rules, passive protocol analysis, and testing against a nonproduction replica. It expressly excludes disruptive testing on live controllers, and a plant engineer must approve any activity that could affect process communications. The assessment team discovers a remotely reachable vendor modem and wants to determine whether it creates an exploitable path to the control network. Which TWO actions best comply with the scope and reduce operational risk? Select TWO.

Correct Answer: C. Review modem configuration and access records with the authorized owner, then document any discovered path for validation.; D. Capture and analyze traffic on the approved monitoring point to identify modem-related sessions and reachable zones.
Explanation:

Passive traffic analysis and an authorized configuration review can establish whether the modem provides a path toward control zones while respecting the explicit restrictions. General assessment authorization does not override the scoped prohibition on disruptive live testing or the requirement for engineering approval. Aggressive scanning, password guessing, and live exploitation can affect availability or exceed scope. If active validation is necessary, it should be performed only within the approved replica or after the required approval and change controls.

Question 4

New Single answer

Topic: Vulnerability Management

Skill tested: Evaluates risk-based vulnerability prioritization using asset criticality and operational exposure.

A vulnerability team reports two findings at a plant. A corporate historian has a high CVSS score but is isolated behind a tightly controlled boundary and has a tested maintenance window next month. A lower-scored flaw affects a legacy gateway that bridges a business network to a control zone; the gateway is reachable from a compromised office segment, and the vendor has no immediate patch. Production cannot tolerate an untested change. Which response is MOST appropriate?

Correct Answer: A. Prioritize the gateway for compensating controls and risk treatment, validate a remediation plan in a representative environment, and track residual risk.
Explanation:

Vulnerability management should combine technical severity with exposure, asset criticality, exploitability, and operational consequences. The gateway's position between business and control networks makes its lower-scored flaw a pressing risk even without a patch. Segmentation, restrictive rules, monitored access, and a tested remediation plan can reduce exposure while avoiding an untested production change. CVSS is useful input, not an automatic priority rule. Deferring all action leaves risk unmanaged, and disabling monitoring reduces visibility without addressing the vulnerability.

Question 5

New Single answer

Topic: Standards and Regulation for Cybersecurity

Skill tested: Applies IEC 62443 zone-and-conduit concepts to structure industrial network security requirements.

A food-processing company is redesigning its plant network after an audit found that quality-control workstations, operator HMIs, and PLCs share a broad Layer 2 segment. The company wants a standards-based design that groups assets by security requirements and controls communication between groups. The redesign must preserve essential control flows and should not rely on a single perimeter firewall as its only safeguard. Which approach best aligns with IEC 62443?

Correct Answer: B. Define security zones based on common requirements, identify necessary conduits between them, and apply appropriate controls to those conduits.
Explanation:

IEC 62443 uses zones to group assets with comparable security requirements and conduits to represent controlled communication paths between zones. The organization can preserve required process communications while restricting unnecessary flows and applying controls proportionate to risk. A single broad zone does not provide meaningful segmentation, and VLANs alone do not enforce policy if routing remains unrestricted. IPsec can protect traffic in appropriate contexts, but encryption neither defines trust boundaries nor replaces access control and monitoring.

Question 6

New Multiple answers

Topic: Securing the ICS/SCADA Network

Skill tested: Assesses secure segmentation and rule design while preserving required industrial control communications.

A plant is replacing an overly permissive firewall between its operations DMZ and a PLC control zone. A historian in the DMZ must receive process data from a designated control-zone server, and administrators must manage the DMZ from a hardened jump host. No direct inbound sessions from the corporate network to PLCs are required. The firewall supports stateful rules, and the plant must avoid disrupting established process flows during migration. Which TWO design actions are MOST appropriate? Select TWO.

Correct Answer: C. Allow only documented source, destination, protocol, and direction combinations required for the historian and jump-host workflows.; D. Establish and validate the required flows, then implement restrictive rules with logging and a controlled rollback plan.
Explanation:

A least-privilege rule set should specify the necessary endpoints, services, and direction rather than granting broad zone access. Validating existing dependencies and using a controlled migration with logging and rollback reduces the chance of interrupting operations. Allowing all DMZ traffic undermines segmentation, and direct corporate-to-PLC management creates an unnecessary path. An immediate blanket block may break the historian's required data flow; rule changes should be based on documented operational needs.

Question 7

New Single answer

Topic: Bridging the Air Gap

Skill tested: Evaluates secure monitoring and log aggregation across a controlled ICS-to-enterprise boundary.

A facility describes its control network as air-gapped, but operators routinely transfer historian reports to enterprise analysts and an external maintenance provider occasionally connects a laptop through a temporary gateway. Security leadership wants centralized alerting and incident investigation without creating an unrestricted route into the control network. Which design is the BEST next step?

Correct Answer: B. Inventory and control every transfer path, then send selected logs through a tightly controlled, monitored boundary using an approved one-way or brokered method where feasible.
Explanation:

An air gap is undermined by any data-transfer or maintenance connection, so those paths must be identified, governed, and monitored. A controlled logging path can support centralized detection while minimizing the ability to initiate traffic into the control environment; the appropriate one-way or brokered design depends on operational requirements. A broad bidirectional SIEM connection increases exposure, while ignoring transfers creates a visibility gap. Antivirus alone does not adequately control third-party access or prevent lateral movement.

Question 8

New Multiple answers

Topic: Introduction to Intrusion Detection Systems (IDS) and Intrusion Prevention Systems (IPS)

Skill tested: Assesses passive IDS deployment and alert triage for anomalous industrial protocol activity.

A power facility wants to detect unexpected Modbus writes and new engineering-workstation communications. Its production network carries time-sensitive control traffic, and the operators will not approve inline blocking until detections are validated. The security team has switch infrastructure that can provide a mirrored feed and a process engineer available to review alerts. Which TWO actions are MOST appropriate for the initial deployment? Select TWO.

Correct Answer: D. Establish a baseline of authorized hosts, normal protocol functions, and operating periods, then tune detections with process-owner input.; E. Deploy a passive IDS on a correctly configured mirrored feed and verify that it receives representative traffic in both directions.
Explanation:

A passive IDS observes traffic without placing an enforcement device in the control path, matching the facility's availability constraint. A correctly configured mirror is essential; an incomplete or one-direction feed can create misleading visibility. Baselines and process-owner review help distinguish unauthorized writes from legitimate maintenance or process behavior. Immediate inline blocking risks disrupting control, while trusted workstations can be compromised and should not be exempted. An IDS detects and alerts; rewriting traffic is not an appropriate IDS function.

Question 9

New Single answer

Topic: Introduction to ICS/SCADA Network Defense

Skill tested: Assesses selection of industrial security controls based on safety, availability, and threat exposure.

A chemical plant is reviewing a proposal to deploy a conventional IT endpoint protection agent across its control environment. The proposal covers operator stations, engineering workstations, and several legacy servers, but the vendor has not validated the agent on the plant's operating systems. The control vendor warns that resource-intensive scans could disrupt real-time applications, and the plant cannot schedule a full outage this quarter. What is the MOST defensible decision?

Correct Answer: D. Assess supported assets and operational risk, test the agent on representative systems in a nonproduction environment, and use layered compensating controls where deployment is unsuitable.
Explanation:

ICS security decisions must account for availability, safety, vendor support, and the specific capabilities of each asset. Testing a proposed agent on representative systems can reveal compatibility and performance issues before production deployment. Where agents are unsupported or unsuitable, compensating measures such as segmentation, application control where feasible, restricted administration, and monitoring can reduce risk. Immediate blanket deployment ignores the vendor warning, while rejecting endpoint controls universally is unjustified. PLCs are not generally suitable targets for conventional endpoint agents.

Question 10

New Single answer

Topic: Introduction to Hacking

Skill tested: Evaluates ethical footprinting methods for identifying external exposure without disrupting ICS operations.

An assessor has authorization to review a utility's external exposure but may not send probes to the production control network. Public records show that the utility uses a third-party maintenance provider, and leadership wants to know whether publicly visible information could reveal a path to operational assets. Which action is the best initial footprinting step within these constraints?

Correct Answer: B. Search public DNS, certificate transparency data, corporate disclosures, and provider documentation for exposed names and relationships, then report findings for authorized validation.
Explanation:

Passive footprinting uses publicly available information to map domains, certificates, organizational relationships, and possible third-party exposure without probing protected systems. Findings should be treated as leads and validated through authorized channels. High-rate scanning and direct protocol requests violate the no-probing constraint and could affect fragile services. Impersonation to obtain credentials is not an appropriate authorized assessment technique. This approach also helps prioritize later, explicitly approved testing.