Limited-Time Offer: Enjoy 50% Savings! Ends in 00h 00m 00s Coupon code: 50OFF
Skip to content

Free EXIN Agile Scrum Foundation ASF Exam Questions

Page: 1 / 6 Total 59 questions

Want more questions? Get Premium Access.

Question 1

According to Agile principles, what should be the pace of development?

Correct Answer: C. Sustainable

Question 2

During the release planning meeting, it is difficult to agree on priorities.

Sales want to implement some new features to catch up with the competitors.

Marketing want to work on a mobile interface that can prove to be a competitive differentiator.

Customer support want better logging and auditing capabilities to improve maintainability.

What should be done to set the priorities?

Correct Answer: C. The Product Owner will set the priorities.

Question 3

Which of the following statements best expresses the role that the daily stand-up meeting plays in the monitoring of a Scrum project?

Correct Answer: B. The stand-up meeting gives the team insight into their progress and their issues.

Question 4

For a Sprint, progress is monitored in a burn-up chart with bars.

What makes the bar become longer?

Correct Answer: C. Work is deleted from the Sprint Backlog.

Question 5

What is the usual length of the time box for the complete Sprint Planning meeting?

Correct Answer: A. Four hours for a 30 day Sprint, one to two hours for a shorter Sprint.

Question 6

What should the Scrum Master advise the team to give their main focus, while working in a global distributed team?

Correct Answer: B. Place greater emphasis on team-building activities and cultural sensitivities.

Question 7

During a Sprint Planning session, the team argues about the work estimates for a particular story.

The Product Owner estimates five days.

The Lead Architect estimates two days.

The Scrum Master estimates eight days.

The team member working on it estimates seven days.

What value (in days) should be used for planning?

Correct Answer: C. 7

Question 8

What is the primary responsibility of a Scrum Master in order to keep a Scrum team working at its peak level of productivity?

Correct Answer: C. Supporting the team's decisions and resolving the team's issues.

Question 9

Who knows most about the progress towards a business objective or a release?

Correct Answer: A. The Product Owner

Question 10

The team determines that it has over-committed itself for a Sprint.

Who should be present when reviewing and adjusting the Sprint work?

Correct Answer: C. The team only. The Product Owner should be consulted.