The three elements of the fire triangle are , and . (Choose three.)

Correct Answer: A. Oxygen; C. Heat; E. Fuel
Explanation:

The fire triangle is a simple model that illustrates the three elements that a fire needs to ignite and sustain: oxygen, heat, and fuel. Oxygen is the oxidizing agent that enables the combustion reaction, heat is the energy source that raises the temperature of the fuel to its ignition point, and fuel is the material that reacts with oxygen and releases heat and light. Removing any one of these elements can extinguish a fire. For example, water can reduce the heat and the oxygen, sand or soil can smother the fuel and the oxygen, and fire extinguishers can displace the oxygen or lower the temperature.


Question 2

The expected time to Recover/Repair from a system from a failure is defined as .

Correct Answer: D. MTTR
Explanation:

The expected time to recover or repair from a system from a failure is defined as MTTR (mean time to recovery or mean time to repair). MTTR is the average time it takes to restore a system or product to its normal operation after a failure. MTTR includes the time spent on detecting, diagnosing, and fixing the problem. MTTR is an important metric for measuring the reliability and availability of a system or product, as well as the efficiency and effectiveness of the incident management process. A lower MTTR indicates a faster and more reliable recovery or repair process.


* EPI Data Centre Professional (CDCP) Preparation Guide, page 17

* What is MTTR? | IBM

* Explained: All Meanings of MTTR and Other Incident Metrics

Question 3

Which one of the following is a factor that can affect Availability and Reliability?

Correct Answer: A. Inadequate Cooling
Explanation:

Availability and reliability are two important aspects of data centre performance that measure how often the system is operational and how dependable it is. According to the EPI Data Centre Framework, availability is the percentage of time that a system or component is in an operable state, while reliability is the probability that a system or component will perform its required function under given conditions for a specified period of time. Both availability and reliability can be affected by various factors, such as design, maintenance, human error, power supply, security, etc. One of the factors that can have a significant impact on both availability and reliability is cooling. Cooling is essential for maintaining the optimal temperature and humidity levels for the IT equipment and preventing overheating, which can cause failures, downtime, and reduced lifespan. Inadequate cooling can result from insufficient capacity, poor airflow management, faulty components, or environmental conditions. Inadequate cooling can reduce the availability and reliability of the data centre by increasing the risk of thermal stress, hot spots, performance degradation, and equipment damage. Therefore, cooling is a critical factor that can affect availability and reliability in a data centre.


* EPI Data Centre Framework1

* EPI Data Centre Training Framework2

* EPI Data Centre Competence Framework3

* Data Center Availability, Reliability Hinge On Numerous Factors4

* A Look at Data Center Reliability and Availability5

Question 4

Which Class of Fires involves cooking appliances?

Correct Answer: D. Class K
Explanation:

According to the EPI Data Centre Professional (CDCP) Preparation Guide, Class K fires involve cooking appliances that use combustible cooking media such as vegetable or animal oils and fats (page 28). Class K fires require special extinguishing agents that can suppress the high-temperature flames and prevent re-ignition. Class K fires are different from Class B fires, which involve flammable liquids such as gasoline, oil, or paint.


* EPI Data Centre Professional (CDCP) Preparation Guide, page 28

* Fire Classes and Extinguishing Agents | The Fire Equipment Manufacturers' Association

Question 5

What is the most cost-effective way to avoid EMF issues within the Computer room?

Correct Answer: A. Create a distance between the EMF source and the ICT equipment / copper network cabling
Explanation:

Physical separation is the most cost-effective method to minimize electromagnetic interference. Specialized shielding is more expensive and usually unnecessary if proper separation is maintained.


CDCP Exam Preparation Guide, EMF Section

Question 6

Which one of the following is an example of Indirect Cost?

Correct Answer: B. Damaged brand perception
Explanation:

Damaged brand perception is an example of an indirect cost because it is not directly related to a specific product or service, but rather to the overall reputation and image of the company. Damaged brand perception can result from various factors, such as poor quality, customer dissatisfaction, security breaches, or negative publicity. Damaged brand perception can affect the company's ability to attract and retain customers, partners, and investors, and thus reduce its profitability and competitiveness.


Learn more

1 indeed.com2 o

Question 7

Which one of the following represents the three elements (oxygen, heat and fuel) to interact in order for the fire to exist?

Correct Answer: C. The Fire Triangle
Explanation:

The fire triangle is a simple model that illustrates the three elements a fire needs to ignite: heat, fuel, and an oxidizing agent (usually oxygen). A fire naturally occurs when the elements are present and combined in the right mixture. A fire can be prevented or extinguished by removing any one of the elements in the fire triangle.


Question 8

What is a requirement for both CCTV cameras and recording equipment?

Correct Answer: C. Both must be connected to a UPS.
Explanation:

A UPS (Uninterruptible Power Supply) is a device that provides backup power to electrical equipment in case of a power outage or fluctuation. A UPS is essential for both CCTV cameras and recording equipment, as it ensures that the surveillance system can continue to operate and record without interruption or data loss. A UPS can also protect the CCTV cameras and recording equipment from damage caused by power surges or spikes. Connecting both CCTV cameras and recording equipment to a UPS is a requirement for data centres, as it enhances the security and reliability of the surveillance system.


Question 9

When dealing with glass door racks, cod air is injected into the rack from:

Correct Answer: A. The rear door in a downflow direction.

Question 10

What is the current recommended temperature for ICT equipment as described in the ASHREA TC 9.9 guideline?

Correct Answer: C. 18-27 C (64.4 - 80.6F)
Explanation:

The current recommended temperature for ICT equipment as described in the ASHRAE TC 9.9 guideline is 18-27 C (64.4 - 80.6F). This is the recommended range for the dry-bulb temperature at the inlet of the servers, which is the most critical parameter for ensuring the optimal performance and reliability of the ICT equipment. The recommended range is based on the thermal specifications of the majority of the ICT equipment in the market, as well as the energy efficiency and environmental considerations of the data centre cooling systems. The recommended range is suitable for Classes A1 to A4 of the ASHRAE thermal guideline classes, which cover different types and generations of ICT equipment.


1: 2021 Equipment Thermal Guidelines for Data Processing Environments - ASHRAE2, page 1, Table 2.1 3: ASHRAE TC9.9 Data Center Power Equipment Thermal Guidelines and Best Practices4, page 10, section 2.1 5: Does your Data Center Follow ASHRAE TC 9.9 Thermal Guidelines for Data Processing Environments?6, page 1, section 1