Question 1
Topic: Data center operations
Skill tested: Schedules preventive maintenance around operational risk, redundancy, and approved change windows.
A colocation facility must service a cooling-water strainer serving one of two redundant chilled-water trains. Both trains currently support the full critical load, but the planned work will make the serviced train unavailable for several hours. A seasonal heat event is forecast during the proposed window, and the tenant requires that maintenance not reduce cooling resilience below the approved operating limit. The maintenance team has prepared a work procedure, but no capacity or risk review has been recorded. What should the operations manager do before approving the work?
Maintenance planning must account for the system's degraded configuration, forecast conditions, critical load, and the facility's approved resilience limit. Deferring the work and validating capacity and risk before rescheduling protects availability while still retaining a planned maintenance path. Normal-condition capacity alone, as in A, does not establish that the surviving train can safely support peak demand. Portable fans do not replace the designed cooling train, and a tenant load reduction without an agreed assessment does not substitute for an operational risk review.