Limited-Time Offer: Enjoy 50% Savings! Ends in 00h 00m 00s Coupon code: 50OFF
Skip to content

Free Huawei HCSP-Field-Data Center Facility V1.0 H20-923_V1.0 Exam Questions

Page: 1 / 6 Total 60 questions

Want more questions? Get Premium Access.

Question 1

In a data center power distribution architecture, what is the primary function of a Static Transfer Switch (STS) for critical single-cord loads?

Correct Answer: B. Provide fast switching between two independent AC power sources to maintain continuity
Explanation:

Huawei data center power distribution design prioritizes continuity for critical loads. For single-cord IT equipment that cannot accept dual inputs, an STS provides a practical high-availability approach by connecting the load to two independent AC sources (often A and B feeds) and transferring the load to the healthier source when abnormalities occur. The key value is speed and coordination: the STS detects voltage/frequency deviations or source failure and performs a rapid transfer to minimize or eliminate interruption seen by the load. This supports O&M strategies where upstream systems (UPS, PDUs, distribution boards) are maintained or isolated without forcing downtime on single-cord devices. In routine operations, STS status, transfer logs, alarms, and source quality parameters are monitored to prevent nuisance transfers and to ensure correct upstream selectivity and grounding. Correct commissioning also ensures the two sources meet synchronization conditions and that bypass/maintenance procedures are standardized, improving safety and reducing operational risk.


Question 2

Which of the following control modes can be used for temperature and humidity control of smart cooling products?

Correct Answer: A. Cold aisle; B. Supply air; C. Return air
Explanation:

Smart cooling temperature and humidity control is based on where the control ''reference point'' is measured and regulated. Supply air control uses the unit outlet sensor as the main reference, so the system directly regulates the temperature (and humidity when configured) of the air delivered to the IT area. This provides stable supply conditions and is widely used for predictable airflow organization. Return air control uses the unit inlet/return sensor as the reference, reflecting the heat absorbed from IT loads; it helps the unit respond to real load changes and maintain stable operation when room mixing or load distribution varies. Cold aisle control uses sensors placed in the cold aisle (near rack inlets) as the reference, aligning control with the most critical point for IT reliability---server intake conditions---especially in contained aisle scenarios. Hot aisle is generally not used as a primary temperature-and-humidity control mode because hot aisle conditions are intentionally high and variable (driven by load and containment), and controlling to hot aisle targets can conflict with ensuring stable rack inlet temperature and proper dehumidification behavior. Therefore, A, B, and C are valid control modes.


Question 3

Which of the following statements is false about the advantages of the free cooling solution for data centers?

Correct Answer: A. The current technology is not mature enough and should be used with caution.
Explanation:

Free cooling is a mainstream energy-saving concept in data center cooling design, used to reduce chiller compressor runtime by leveraging low outdoor temperatures (air-side) or low cooling-water temperatures (water-side) during suitable seasons. Therefore, describing the technology as ''not mature enough and should be used with caution'' is the false statement when discussing its advantages. In practice, free cooling has broad industry adoption and is considered a proven approach when applied with correct engineering, such as proper filtration, anti-condensation control, heat exchanger selection, and automatic control strategies. Its advantage is that it can directly utilize the outdoor ''cold source'' to remove heat, which significantly reduces cooling power consumption compared with full mechanical refrigeration, improving overall energy efficiency and supporting lower PUE targets. It also makes full use of seasonal and day-night temperature differences: the system dynamically switches among free cooling, partial free cooling, and mechanical cooling to balance reliability and efficiency. The key point is maturity: the benefit of free cooling comes from well-established principles and widely implemented architectures, not experimental technology.


Question 4

In IT scenarios, which of the following are the power supply and distribution components of the FusionDC1000A?

Correct Answer: A. SmartLi; B. Power PDB; C. Integrated UPS
Explanation:

In the FusionDC1000A IT scenario, the power chain is built around an AC input, conditioned backup power, energy storage, and final distribution to the IT racks. Integrated UPS is the core power-conditioning component, providing voltage and frequency stabilization and uninterrupted supply during mains disturbances. The UPS works together with SmartLi, Huawei's lithium battery system, which serves as the energy storage unit to sustain the load during outages and to support controlled shutdown or generator switchover. After UPS output, power is delivered to the IT loads through the Power PDB, which performs downstream distribution, branch protection, and organized cable termination toward rack PDUs or IT equipment feeders. By contrast, an AC/DC power system is typically associated with DC bus supply used in telecom-oriented or dedicated DC load scenarios, not the standard IT scenario architecture of FusionDC1000A that is centered on UPS plus battery plus AC distribution. Therefore, the correct components for IT scenarios are SmartLi, Power PDB, and Integrated UPS.


Question 5

Which of the following are main components of Huawei indirect evaporative cooling system?

Correct Answer: B. Air filter; C. Water pump; D. Spray system; E. Heat exchanger; F. Fan
Explanation:

Huawei's indirect evaporative cooling system is designed to use the outdoor air as a ''free'' cold source while keeping the data hall supply air isolated from outdoor contaminants and moisture. Its core is the heat exchanger, where heat from the indoor (return) air side is transferred to the outdoor working air side without mixing the two air streams. To enhance heat removal on the outdoor side, a spray system wets the evaporation media or spray section, and a water pump circulates water to maintain uniform wetting and stable evaporation performance. Fans drive airflow through the indoor and outdoor paths to ensure sufficient heat transfer and maintain the required air volume and pressure. Because outdoor air is involved on the working-air side, air filters are required to reduce dust and protect the heat exchanger and internal airflow channels, improving reliability and reducing maintenance. A compressor is not a main component of indirect evaporative cooling because the system primarily relies on evaporation and heat exchange rather than mechanical refrigeration.


Question 6

After the battery module is installed, the torque and insulation should be checked according to the specified requirements.

Correct Answer: A. True
Explanation:

This statement is true because post-installation verification is a mandatory acceptance step for battery systems in data centers. After a battery module is installed, torque verification ensures that all power terminals, interconnect bars, and grounding points meet the specified tightening requirements. If torque is too low, contact resistance increases, which can cause abnormal heating, voltage drop, nuisance alarms, and even connector damage during high current charge/discharge. If torque is too high, threads, lugs, or busbars can be damaged, creating hidden reliability risks. Insulation testing confirms that the battery circuit has no unintended leakage paths to chassis or ground and that cable routing, connector seating, and protective covers are correct. This is especially important for lithium battery cabinets where high DC voltage and large fault current capability demand strict electrical isolation. Performing torque and insulation checks after installation reduces early-life faults, improves safety, and ensures the cabinet can pass commissioning tests and enter stable service under UPS charge/discharge control.


Question 7

The default port number for logging in to the NetEco is

Correct Answer: C. 31943
Explanation:

In Huawei NetEco access design, the Web client is reached using HTTPS to protect credentials and management data in transit. During initial deployment and commissioning, engineers access the NetEco login page by entering the server IP address followed by the default HTTPS service port. Huawei's standard login method specifies that users open a browser and enter https://NetEco server IP:31943 to access the NetEco login interface. This port is therefore treated as the default Web login port in typical on-premises NetEco deployments, and it is the baseline value referenced in installation and login guidance. Other ports may appear in specific tools, customized scenarios, version variants, reverse-proxy deployments, or when security policy requires port changes, but those are exceptions driven by planning or product packaging. For exam and commissioning purposes, the correct default login port is the one used by the NetEco Web client entry point under the standard deployment model: 31943.


Question 8

Which of the following conditions will not cause the wizard startup commissioning to fail?

Correct Answer: D. The water leakage rope is not installed.
Explanation:

Wizard startup commissioning is designed to verify that the unit's key controllable subsystems can be started, regulated, and protected correctly. Conditions that prevent a subsystem from operating normally will directly cause commissioning failure. If the condensate pump is stuck, the drainage function cannot be validated and water may accumulate in the drain pan, which is treated as a functional fault during commissioning. If indoor fan 2 drive is faulty, the fan system cannot meet airflow requirements or redundancy expectations, so the fan commissioning item fails. If the electronic expansion valve (EEV) is not opened, refrigerant flow and cooling control cannot be established, so the cooling system commissioning fails because the unit cannot build a stable refrigeration cycle or reach expected operating parameters.

In contrast, the water leakage rope is a protective detection accessory used for leak sensing and alarming. While it is important for site safety and recommended for operation, its absence typically does not block the unit from completing the functional commissioning steps for fans, cooling, and drainage; it mainly affects leak detection coverage and related alarms rather than the basic startup commissioning pass/fail.


Question 9

What are the colors of indicators on the LCD panel of the MDU?

Correct Answer: A. Yellow; B. Green; C. Red
Explanation:

On Huawei UPS systems (such as the UPS5000 series), the MDU LCD panel includes status indicators designed to provide an immediate visual understanding of the UPS operating condition and alarm severity. The indicator system uses three standard colors: green, yellow, and red. Green indicates the UPS is operating normally and the power supply path is healthy. Yellow is used to show abnormal conditions that require attention, such as warnings or non-critical alarms, where the UPS can typically continue supplying power but O&M personnel should inspect and handle the issue within the required timeframe. Red indicates serious or critical conditions, such as major faults or alarms that may threaten continuous power supply or require urgent action according to operating procedures. These three colors align with the common Huawei alarm severity presentation logic on the UPS display and help technicians quickly judge whether the situation is normal, warning-level, or critical-level without entering deeper menus. Orange is not used as an MDU indicator color in this context.


Question 10

If the startup password authentication for a smart module is not complete, the ECC800-Pro WebUI and app cannot be used for commissioning.

Correct Answer: A. True
Explanation:

In Huawei smart module commissioning and O&M workflows, startup password authentication is a mandatory security initialization step for the controller and its management channels. The ECC800-Pro provides WebUI and mobile app access for tasks such as device discovery, parameter setting, site configuration, alarm verification, and functional commissioning. Before these commissioning functions are allowed, the system requires completion of startup authentication actions, typically including initial password setup or password change, confirmation of authentication policies, and activation of secure access control. This prevents unauthorized users from entering the management plane during the critical initial stage when default credentials or incomplete security settings could exist. If startup password authentication is not completed, the platform restricts access to commissioning pages and app-based commissioning features, ensuring that configuration changes, device binding, and control operations cannot be executed until the controller is placed into a compliant, secured state. This design aligns with data center facility management best practices where commissioning must begin only after management access is hardened and auditable.