Question 1
Topic: Resource Management
Skill tested: Develops project staffing needs and allocates staff hours across scheduled phases.
A small architecture firm is beginning a municipal library project with a fixed fee and a 16-month schedule. The project includes programming, design, construction documents, bidding, and construction administration. The principal has approved the total labor budget, but the project manager must establish a staffing plan that exposes workload peaks before commitments are made. The firm has a project architect, two designers, and an administrative coordinator; structural, mechanical, electrical, and civil consultants will be retained separately. The project architect will lead design decisions, while the designers will produce and coordinate drawings. Which planning approach is MOST appropriate?
A phase- and role-based staffing plan connects the work required to the people and hours available. Mapping estimated effort against the schedule reveals peaks, overlaps, and potential resource conflicts early; consultant milestones should also be coordinated with internal review and integration time. Equal allocation ignores changing phase demands, while concentrating effort in construction documents overlooks programming and design decisions that shape the documents. Waiting to define consultant scopes risks late coordination and does not provide a reliable basis for staffing or fee control.