Question 1

New Single answer

Topic: Resource Management

Skill tested: Develops project staffing needs and allocates staff hours across scheduled phases.

A small architecture firm is beginning a municipal library project with a fixed fee and a 16-month schedule. The project includes programming, design, construction documents, bidding, and construction administration. The principal has approved the total labor budget, but the project manager must establish a staffing plan that exposes workload peaks before commitments are made. The firm has a project architect, two designers, and an administrative coordinator; structural, mechanical, electrical, and civil consultants will be retained separately. The project architect will lead design decisions, while the designers will produce and coordinate drawings. Which planning approach is MOST appropriate?

Correct Answer: D. Estimate phase-specific labor hours by role, map them against the schedule, and check consultant deliverables and internal coordination effort against those milestones.
Explanation:

A phase- and role-based staffing plan connects the work required to the people and hours available. Mapping estimated effort against the schedule reveals peaks, overlaps, and potential resource conflicts early; consultant milestones should also be coordinated with internal review and integration time. Equal allocation ignores changing phase demands, while concentrating effort in construction documents overlooks programming and design decisions that shape the documents. Waiting to define consultant scopes risks late coordination and does not provide a reliable basis for staffing or fee control.

Question 2

New Single answer

Topic: Project Work Planning

Skill tested: Uses critical-path reasoning to assess the schedule impact of delayed owner reviews.

A university project schedule shows that the owner's approval of the room data sheets is a predecessor to consultant design, which in turn precedes the next integrated design review. The owner's review has slipped by two weeks. The mechanical engineer says its work can start without the approved room data sheets, but doing so would require assumptions about occupancy and equipment loads. The owner has not authorized acceleration, and the completion date is contractually important. What should the project manager do FIRST?

Correct Answer: A. Update the schedule logic to show affected successor activities and float, then communicate the forecast impact and obtain a decision on recovery or revised inputs.
Explanation:

The project manager should first determine which successor tasks are affected, whether available float absorbs the delay, and how the critical path and milestones change. That updated analysis supports a factual discussion with the owner about decisions, revised inputs, or recovery measures. Proceeding on unapproved assumptions can cause redesign; moving a review does not resolve missing information. Adding construction-document staff before understanding the schedule logic may add cost without recovering a predecessor delay.

Question 3

New Multiple answers

Topic: Project Work Planning

Skill tested: Sequences project activities and identifies schedule dependencies and review hold points.

A nonprofit client is renovating an occupied clinic and requires completion before a fixed licensing inspection. The team has completed programming, but the client has not approved the final room layouts. Structural and MEP consultants need that approval before completing coordinated design, and the architect needs consultant backgrounds before issuing the next review package. The contract schedule includes client review periods, and the building must remain operational during construction. Which TWO actions best improve the work plan without treating unresolved prerequisites as complete? Select TWO.

Correct Answer: A. Identify long-lead decisions and occupied-building constraints as schedule risks, with decision dates and contingency or mitigation actions.; D. Show client approval, consultant design, and document coordination as linked activities with explicit review durations and responsible parties.
Explanation:

Linked activities make the approval-to-design-to-coordination dependencies visible and establish who must act and when. Explicit review durations help the team forecast whether the fixed inspection milestone remains achievable. Identifying long-lead decisions and occupied-building constraints makes risk response part of the plan rather than an afterthought. A single end milestone conceals dependency risk. Starting coordinated design on unapproved layouts invites rework, while deleting client review time hides a real schedule activity instead of managing it.

Question 4

New Single answer

Topic: Contracts

Skill tested: Applies owner-architect scope and additional-services provisions to a requested program change.

During design, an owner asks the architect to add a rooftop event space and a commercial kitchen that were not included in the approved program. The request changes occupancy assumptions, consultant work, code analysis, and the design schedule. The owner-architect agreement identifies the original program as the basis of basic services and describes additional services and fee adjustments. The owner says the architect should start immediately and "work out the fee later." What is the MOST appropriate response?

Correct Answer: B. Document the requested change, assess its effects on scope, fee, schedule, and consultant services, and obtain the required written authorization before proceeding with the additional work.
Explanation:

A material program change can alter both the architect's and consultants' required services and can affect fee and schedule. The architect should document the request, determine its consequences, and follow the agreement's authorization process for additional services before undertaking that work. A verbal request does not necessarily amend contractual scope or establish compensation. The request is not inherently prohibited, but initiating it without agreement creates avoidable scope and payment disputes; consultant redesign should not be commissioned informally either.

Question 5

New Multiple answers

Topic: Contracts

Skill tested: Distinguishes owner-contractor change administration from architect-consultant scope coordination.

On a renovation, concealed conditions require rerouting ductwork and adding fire protection work. The contractor submits a proposed change with cost and time effects. The architect's mechanical consultant will need to revise its design documents, and the owner asks the architect to issue a directive today so field work can continue. The owner-contractor agreement contains a defined change process, while the architect-consultant agreement requires services to be coordinated through the architect. Which TWO actions are most appropriate? Select TWO.

Correct Answer: B. Review the contractor's proposal for consistency with the design intent and contract documents, and follow the agreement's required change authorization process before directing changed work.; C. Coordinate with the mechanical consultant to define the needed additional design services and obtain any required authorization under its agreement.
Explanation:

The contractor's proposed change must be evaluated and administered using the owner-contractor agreement's procedures; reviewing a proposal alone is not authorization to change the contract sum, time, or work. Separately, revised engineering design may be additional consultant service, so the architect should define and coordinate that scope under the architect-consultant agreement and obtain any required approval. The contractor's process does not automatically amend the consultant agreement, and bypassing the architect undermines the agreed coordination path.

Question 6

New Single answer

Topic: Contracts

Skill tested: Interprets contractor submittal review responsibilities under construction contract documents.

A contractor submits a shop drawing for a custom exterior sunshade. The architect's review reveals that the proposed attachment geometry differs from the contract documents and could affect the façade appearance. The contractor's transmittal says the submittal is "for approval," and the contractor has not identified the deviation in writing. The owner asks the architect to verify every dimension and certify that the assembly will perform safely. What is the architect's MOST appropriate response under typical construction contract administration responsibilities?

Correct Answer: A. Review the submittal for conformity with the design concept and contract-document information, note the apparent deviation, and require the contractor to identify deviations and obtain design-team evaluation as appropriate.
Explanation:

Architectural submittal review is generally for the limited purpose of checking conformance with the design concept and information in the contract documents, not verifying every dimension, fabrication method, or contractor-controlled safety responsibility. The unreported attachment deviation must be brought to the contractor's attention and evaluated through the appropriate design and change process. Approving all calculations would exceed the usual review role; refusing all review is not appropriate, and a transmittal label does not authorize a deviation.

Question 7

New Single answer

Topic: Project Execution

Skill tested: Analyzes estimate variance and selects a documented, client-approved scope adjustment.

At the end of schematic design, the estimator's current projection is 12 percent above the owner's approved construction budget. The largest variance comes from the selected stone façade and a complex roof form; the owner has said that the building's public image matters, but has not ranked those features against interior finishes or the project's usable area. The architect's basic-services scope covers the current approved program, and no redesign direction has been issued. What should the project manager do NEXT?

Correct Answer: C. Present the variance and its principal cost drivers, develop feasible alternatives with associated cost and design effects, and obtain the owner's direction before revising scope.
Explanation:

The project team should make the budget gap and its drivers transparent, then provide alternatives that allow the owner to make an informed scope decision. The owner's priorities are not yet sufficiently defined to justify unilateral removal of a prominent feature or reduction of usable area. Across-the-board allowance cuts do not demonstrate that the design can be built for the target budget. Continuing without addressing the variance risks avoidable redesign and does not support responsible project execution.

Question 8

New Multiple answers

Topic: Project Execution

Skill tested: Documents scope changes and evaluates their fee, schedule, and budget consequences.

An owner directs the team to add a separate imaging suite after the design-development milestone. The addition requires revised space planning, structural coordination, electrical capacity analysis, and a longer equipment procurement schedule. The owner wants the original completion date preserved and asks the architect to begin while the fee amendment is being prepared. The project manager has authority to coordinate the design team but not to waive contractual change procedures. Which TWO actions best protect the project and maintain clear execution records? Select TWO.

Correct Answer: C. Record the owner's request and evaluate its effects on architectural and consultant scope, fee, schedule, budget, and required approvals.; E. Prepare a written change or additional-services proposal identifying assumptions, deliverables, compensation, and schedule implications, and seek the authorization required by the agreement.
Explanation:

The project manager needs a documented impact assessment spanning the architect, consultants, budget, and schedule; new equipment and added coordination can affect both cost and completion. A written proposal clarifies assumptions, services, compensation, and timing before work proceeds, subject to the agreement's authorization requirements. Meeting minutes alone do not necessarily amend the contract. Requiring consultants to absorb undefined work obscures scope and fee, and guaranteeing the original date without schedule analysis creates an unsupported commitment.

Question 9

New Single answer

Topic: Project Quality Control

Skill tested: Establishes interdisciplinary review checkpoints for coordinated design documents.

A design team is preparing a permit and pricing package for a mid-rise office building. During an internal review, the architect finds that a plumbing riser conflicts with a primary beam, while the reflected ceiling plan does not show a duct crossing a rated corridor enclosure. The issue log contains several open consultant questions, but the package is scheduled for issue in three days. The client does not permit a schedule extension without documented justification. What is the BEST quality-control action?

Correct Answer: C. Hold a focused interdisciplinary coordination review, assign responsibility and due dates for the conflicts, verify affected code and rated-assembly information, and document any remaining issue and its disposition before issue.
Explanation:

A targeted coordination checkpoint addresses both physical clashes and life-safety documentation before the package is issued. Assigning owners and deadlines creates accountability, while checking the rated corridor information prevents a coordination response from obscuring code requirements. The architect should not unilaterally revise consultant systems, and transferring known conflicts to the contractor is not an effective quality-control process. Removing required fire-resistance information would create a more serious documentation and compliance risk.

Question 10

New Multiple answers

Topic: Project Quality Control

Skill tested: Reviews submittal responses for appropriate scope, clarity, and preservation of design intent.

A contractor submits a product data package for a specified roof membrane and proposes a substitution because the specified product is unavailable within the contractor's requested procurement period. The package omits a required warranty detail and shows a flashing condition that differs from the details. The project architect can review design conformance but is not responsible for the contractor's means and methods or independent verification of field dimensions. Which TWO response practices are most appropriate? Select TWO.

Correct Answer: A. Evaluate the proposed substitution against the contract requirements and design intent, requesting supporting information or required owner/design-team approval as applicable.; B. Record the review status and clearly identify the missing warranty information and the apparent deviation that must be resolved before the submittal can be accepted.
Explanation:

A useful review response states the disposition and identifies the missing warranty information and visible deviation so the contractor can provide a complete, conforming submittal. A proposed substitution requires evaluation against specified performance and design intent; schedule pressure alone does not establish equivalence or approval. The architect's review does not certify installation means, methods, or field measurements. Vague comments leave the contractor without actionable direction and weaken the project record.

Question 11

New Single answer

Topic: Project Quality Control

Skill tested: Prioritizes code and constructability checks before issuing coordinated permit documents.

A firm's quality plan calls for a code review and interdisciplinary document review before permit issuance. On a healthcare clinic project, the internal review identifies an accessible route that appears to narrow below the project's documented requirement where it passes a reception counter. The electrical consultant's plan also places a panel in the same area, and the architect's floor plan is already marked "issued for permit" in the document-control system but has not been transmitted. The permit deadline is tomorrow. What should the project architect do?

Correct Answer: B. Pause transmission, coordinate the accessible-route and panel conflict with the relevant disciplines, verify the applicable requirement, and complete the required review and issue-control steps.
Explanation:

The review has identified a potential accessibility compliance issue and an interdisciplinary conflict, so the package should not be transmitted as though quality checks were complete. The architect should verify the applicable requirement, coordinate the panel location with the electrical consultant, and document the resolution through the firm's review and document-control process. A system status label is not a substitute for completed review. Unilateral consultant edits or deferral of a known accessibility issue create avoidable compliance and constructability risks.