Free Oracle Cloud Infrastructure 2025 Migration Architect Professional 1Z0-1123-25 Exam Questions

Last updated: · 14 practice questions with answers and explanations

Page: 1 / 6 Total 55 questions

Want more questions? Get Premium Access.

Question 1

New Single answer

Topic: Fundamentals of Cloud Migrations

Skill tested: Prioritizes migration discovery and workload dependency analysis before selecting a migration strategy.

A retailer plans to move 180 applications from two data centers to OCI over the next year. The infrastructure team has a server list and utilization exports, but application owners disagree about dependencies and outage tolerance. A small number of systems support payment processing, and the company will not approve cutovers until rollback and business impact are understood. What should the migration architect do FIRST to establish a defensible migration plan?

Correct Answer: B. Classify workloads using business criticality, dependency mapping, and migration readiness, then validate the findings with application owners.
Explanation:

A migration plan should begin with an evidence-based understanding of workload relationships, business criticality, readiness, and acceptable downtime. Validating dependency and business information with application owners helps define migration waves, cutover sequencing, and rollback requirements. Sizing from peak CPU alone does not establish architecture or business readiness. Grouping only by operating system can separate tightly coupled applications. Capacity estimates and proposed dates are premature when dependencies and outage tolerances remain unresolved.

Question 2

New Single answer

Topic: OCI Networking Services for Migrations

Skill tested: Selects private OCI connectivity and routing for a migration with predictable data-transfer needs.

A company is transferring several terabytes of application data from its headquarters to OCI. The transfer must use private connectivity, predictable bandwidth, and redundant paths. The organization already has a private WAN provider that can deliver a circuit to an Oracle FastConnect location; Internet-based VPN connectivity is not permitted for the bulk transfer. Which design best meets the requirement?

Correct Answer: B. Provision FastConnect through the provider, configure redundant circuits or paths, and use appropriate DRG and VCN routing.
Explanation:

FastConnect provides private connectivity between an organization and OCI, making it the appropriate choice when private, predictable-capacity data transfer is required. Redundant circuits or paths improve availability, while DRG attachments and route tables must direct traffic between the on-premises network and the target VCN. IPSec VPN uses Internet connectivity and conflicts with the stated prohibition. A public Object Storage endpoint does not satisfy the private-path requirement. Local peering gateways connect VCNs within OCI; they do not connect an on-premises network.

Question 3

New Multiple answers

Topic: Design and Implement Migrations Using Oracle Cloud Migrations Service

Skill tested: Plans discovery and assessment inputs needed to produce reliable OCI migration recommendations.

An enterprise is preparing an Oracle Cloud Migrations project for a VMware estate. Its existing inventory lists VM names and allocated vCPU and memory, but it omits actual utilization, storage consumption, and application relationships. The target team needs OCI recommendations that are appropriately sized and can be sequenced into migration waves. Which TWO actions should the architect take before treating the assessment as ready for planning? Select TWO.

Correct Answer: A. Collect relevant performance and storage metrics over a representative period, and validate workload relationships with application stakeholders.; E. Configure and run supported discovery and data collection for the source environment so the inventory includes observed workload information.
Explanation:

Useful assessment and planning depend on current source discovery data, including workload characteristics that allocated capacity alone cannot provide. Representative utilization and storage information improve sizing, while application-stakeholder validation supplies dependency and sequencing context needed for migration waves. Allocated resources are not a substitute for observed behavior. Replication order does not reveal application dependencies, and subnet membership is a target-network design choice rather than a reliable wave-planning method.

Question 4

New Single answer

Topic: Design and Implement Migrations Using Oracle Cloud Migrations Service

Skill tested: Troubleshoots migration readiness by checking source access and discovery configuration first.

A migration project has been configured to discover a VMware environment, but newly added VMs do not appear in the inventory. Existing discovered VMs remain visible. The VMware administrator confirms that the new VMs are powered on and reside in the same vCenter. Before changing target OCI networking or restarting migration execution, what is the most appropriate next step?

Correct Answer: A. Review the configured discovery scope and source credentials or permissions, then run discovery again and inspect its status.
Explanation:

When a subset of source VMs is absent from inventory, the first checks should focus on whether discovery covers their location and whether the service can access the source objects with the configured credentials and permissions. Rerunning discovery after correcting scope or access allows the inventory to update and exposes relevant status or errors. Target instances and target VCN rules do not make a source VM discoverable. Replication planning should follow, not precede, successful inventory and assessment.

Question 5

New Multiple answers

Topic: Design and Implement Migrations Using Oracle Cloud Migrations Service

Skill tested: Prepares AWS EC2 source access and network prerequisites for Oracle Cloud Migrations discovery.

A company wants to migrate EC2 instances into OCI using Oracle Cloud Migrations. Its security team requires least-privilege access, and the instances must be discovered before OCI target sizing is finalized. The AWS account contains instances across multiple regions, and the team has not yet validated which regions and resources are in scope. Which TWO preparation steps are appropriate? Select TWO.

Correct Answer: A. Define the AWS regions and EC2 resources in scope, then configure the required discovery integration for those regions.; D. Provide the migration integration with the required AWS permissions to inspect the in-scope EC2 resources, following least privilege.
Explanation:

EC2 migration discovery must be scoped to the intended AWS regions and resources, and the integration must be able to read the source information required for inventory and assessment. Defining scope first avoids overlooking workloads or collecting unnecessary data. Least-privilege permissions are preferable to unrestricted administrator access. Converting instances to OCI images is not a prerequisite for discovery, and opening workload security groups to the Internet is both unnecessary for inventory and an unsafe security change.

Question 6

New Single answer

Topic: Design and Implement Migrations Using Oracle Cloud VMware Solution (OCVS)

Skill tested: Sizes an OCVS target using source inventory, capacity needs, and migration prerequisites.

A financial-services firm intends to move a VMware application estate to OCVS with minimal guest changes. Source discovery shows substantial reserved CPU and memory, but measured utilization is much lower. The company must keep its VMware-based operating model and has a fixed maintenance window for the final transition. Which planning approach is MOST appropriate before ordering the OCVS environment?

Correct Answer: C. Size the OCVS cluster from observed demand and growth, while validating VMware compatibility, storage needs, networking, and the required migration capacity.
Explanation:

OCVS planning should be based on discovered source requirements and validated against the target design, including compute demand, growth, storage, networking, compatibility, and capacity for migration and steady-state operation. This preserves the VMware operating model while avoiding blind replication of overallocated resources. Matching allocations exactly may waste capacity, while low utilization does not negate the stated requirement to retain VMware compatibility. A constrained cutover window is not an appropriate time to discover fundamental capacity or connectivity deficiencies.

Question 7

New Multiple answers

Topic: Design and Implement Migrations Using Oracle Cloud VMware Solution (OCVS)

Skill tested: Chooses HCX migration methods according to workload downtime and source-target connectivity constraints.

An organization has established OCVS and HCX connectivity to its on-premises VMware environment. One application can tolerate only a brief outage, while a large noncritical VM can be unavailable during a scheduled maintenance period. The team wants to avoid assuming that every workload should use the same HCX migration method. Which TWO planning decisions are appropriate? Select TWO.

Correct Answer: C. Consider a bulk migration method for the VM that can tolerate a planned outage, and schedule its final switchover accordingly.; D. Evaluate an HCX live migration method for the workload requiring very low downtime, subject to its compatibility and resource prerequisites.
Explanation:

HCX provides different migration approaches with different downtime and operational characteristics. A live migration method is a candidate for the low-downtime workload when the specific source, target, and resource prerequisites are satisfied. A bulk approach can suit a workload that allows a planned maintenance and switchover window. Cold migration requires downtime and therefore is not appropriate for both workloads. HCX does not eliminate the need to validate network behavior or application connectivity, and disk size alone is insufficient for method selection.

Question 8

New Single answer

Topic: Migrate Containerized Applications to OCI

Skill tested: Designs a secure container image promotion path from OCI Registry to OKE.

A software company is moving a Kubernetes application to OKE. Its build pipeline currently pushes images to a private registry, and production clusters must pull only approved, versioned images. The team wants to keep the image source under OCI control and avoid granting broad tenancy permissions to worker nodes. Which approach best satisfies these requirements?

Correct Answer: D. Push approved images to a private OCI Container Registry repository and configure narrowly scoped access for the OKE workload to pull them.
Explanation:

OCI Container Registry is the OCI service intended to store and distribute container images. Using a private repository and granting only the required image-pull access supports controlled promotion of approved, versioned artifacts without broad permissions. A public repository exposes images beyond the intended audience. Object Storage is not a container registry endpoint for Kubernetes image pulls. Building separately on worker nodes undermines reproducibility and requires excessive access, contrary to the stated security constraints.

Question 9

New Single answer

Topic: Migrate Infrastructure Workloads Between OCI Regions

Skill tested: Distinguishes Object Storage replication from object copy for cross-region data movement.

A media company must keep a destination-region bucket current as new and changed objects arrive in the source region. The destination is used for regional recovery, and the company wants ongoing automatic propagation rather than a one-time transfer. Both buckets are in OCI Object Storage, and the destination region is different from the source region. Which mechanism is the best fit?

Correct Answer: C. Configure Object Storage replication from the source bucket to the destination bucket in the other region.
Explanation:

Object Storage replication is designed to asynchronously propagate eligible source-bucket objects to a destination bucket, supporting ongoing regional data protection as objects are added or updated. A one-time object copy is useful for a discrete transfer but does not provide the requested continuing replication behavior. Block Volume replication protects block volumes, not buckets, and File Storage replication applies to file systems rather than Object Storage.

Question 10

New Multiple answers

Topic: Migrate Infrastructure Workloads Between OCI Regions

Skill tested: Implements block volume replication while accounting for cross-region recovery and activation.

A service running on OCI compute uses a block volume that must be recoverable in another OCI region after a regional outage. The recovery team needs a current replica and a documented method to make the replica available for recovery. They understand that replication is asynchronous and that a replica is not simply a concurrently writable copy of the source. Which TWO actions should be included in the design? Select TWO.

Correct Answer: B. Document and test the recovery process for using the replica to create an available recovery volume in the destination region.; D. Enable block volume replication to a supported target region and monitor replication status and lag.
Explanation:

Block Volume replication provides asynchronous replication to a destination region, so the design should monitor replication health and lag rather than assume zero data loss. Regional recovery also requires a tested procedure to make the replicated data usable, including creating or activating a recovery volume as appropriate to the service workflow. The replica is not a concurrently writable mirror, Object Storage replication does not replicate block devices, and deleting the source based on a synchronous-mirror assumption would be unsafe.

Question 11

New Single answer

Topic: Migrate Infrastructure Workloads Between OCI Regions

Skill tested: Orchestrates cross-region recovery using Full Stack Disaster Recovery member groups and plans.

A company is designing OCI Full Stack Disaster Recovery for an application spanning compute instances, databases, and networking dependencies in two regions. During an outage, recovery must run in a controlled sequence: establish prerequisites, promote the database, and then bring up application services. The team also wants a repeatable failover operation instead of a collection of manual runbooks. What should the architect configure?

Correct Answer: B. Create a DR protection group and a disaster recovery plan with appropriately ordered groups and steps for the application stack.
Explanation:

Full Stack Disaster Recovery coordinates recovery through protection groups and disaster recovery plans. The plan should model the needed recovery sequence so prerequisites and database recovery occur before dependent application services. Object Storage replication protects objects but does not orchestrate compute and database startup. An unordered group cannot be relied on to infer the business dependency sequence. VCN peering provides network connectivity, not disaster recovery orchestration.

Question 12

New Single answer

Topic: Migrate Oracle Databases to OCI Database Services

Skill tested: Selects a database migration method based on database size, downtime, and source-target compatibility.

A business is moving a large Oracle Database to an OCI Database service. The source and target versions are compatible, the source can remain online during the bulk transfer, and the business permits only a short outage for final synchronization and cutover. The database must remain transactionally consistent, and the team wants to avoid a prolonged application outage. Which migration approach is MOST appropriate to evaluate?

Correct Answer: B. Use Oracle GoldenGate to maintain changes during migration, with an initial load and a controlled final switchover.
Explanation:

GoldenGate supports ongoing change replication, enabling an initial load followed by synchronization of subsequent changes and a short controlled switchover. That aligns with the large database, online source, and limited cutover window, assuming version, configuration, and licensing prerequisites are validated. Data Pump alone generally requires a suitable outage or additional change-capture strategy for this requirement. A raw file copy does not provide a consistent live migration method, and schema-only export omits the required data.

Question 13

New Multiple answers

Topic: Migrate Oracle Databases to OCI Database Services

Skill tested: Plans database migration validation and cutover controls for a minimal-downtime transition.

An insurer is preparing to migrate a production Oracle database to an OCI Database service using a low-downtime method. The source database will remain available during most of the migration. The change board requires evidence that the target is ready, that data changes are synchronized, and that the application can be returned to service safely. Which TWO controls should be part of the cutover plan? Select TWO.

Correct Answer: A. Validate database and application behavior on the target using agreed checks before declaring migration complete.; C. Define and rehearse a final synchronization and application cutover sequence, including a controlled point at which writes move to the target.
Explanation:

A low-downtime migration needs a clear final synchronization point and controlled transition of application writes so that the target does not become active before it is current. Target-side validation provides evidence that database and application behavior meet acceptance criteria before completion. Redirecting writes before synchronization risks missing transactions. An initial load does not prove that ongoing changes were applied or that the application works correctly. Removing the source immediately eliminates a potential recovery path before the migration is validated.

Question 14

New Single answer

Topic: Design and Implement Migrations Using Oracle Cloud Migrations Service

Skill tested: Sequences replication, target preparation, and execution to control migration cutover risk.

A migration team has completed discovery and assessment for a group of VMware workloads and approved OCI target recommendations. The business requires a repeatable migration with a short outage, a verified target before production traffic is redirected, and a recoverable source until acceptance. Which execution sequence is MOST appropriate?

Correct Answer: C. Prepare the target configuration, perform and monitor replication, execute the migration plan during the approved window, validate the target, and retain the source until acceptance.
Explanation:

A controlled migration proceeds from approved target preparation to replication and monitoring, then executes the planned cutover in the authorized window. The target should be validated before production traffic is redirected, and the source should remain available until acceptance and rollback criteria are satisfied. Cutting over before target creation or readiness reverses the required sequence. Deleting sources after assessment removes the recovery option, while ignoring replication status can lead to stale or incomplete target data.