Limited-Time Offer: Enjoy 50% Savings! Coupon code: 50OFF Use it at checkout
Skip to content

Free PMI Certified Associate in Project Management CAPM Exam Questions

Last updated: · 15 practice questions with answers and explanations

Page: 1 / 88 Total 1320 questions

Want more questions? Get Premium Access.

Question 1

New Single answer

Topic: Project Management Fundamentals and Core Concepts

Skill tested: Selects a predictive or adaptive lifecycle based on requirement stability and feedback needs.

A regional health network is replacing its appointment-booking service. Patient privacy rules and interfaces to existing clinical systems are documented and must pass formal approval before release. The user-facing booking workflow, however, is poorly understood; clinic staff expect to refine it after trying working screens. The network has a fixed regulatory launch date, and it cannot expose real patient data in prototypes. Which lifecycle approach best balances the stable compliance requirements with the uncertainty in the workflow?

Correct Answer: B. Use a hybrid lifecycle, planning and governing compliance interfaces predictively while iteratively refining the workflow with safe prototypes.
Explanation:

A hybrid approach fits the different levels of uncertainty. Stable privacy, integration, and approval requirements can be baselined and governed predictively, while staff can evaluate safe prototypes and refine the booking experience iteratively. A fully predictive approach underuses feedback where requirements are uncertain; a fully adaptive approach does not remove the need to establish and verify compliance controls. Reversing the lifecycle choices in D assigns adaptive planning to the least flexible requirements and predictive planning to the uncertain workflow.

Question 2

New Single answer

Topic: Project Management Fundamentals and Core Concepts

Skill tested: Distinguishes project work from ongoing operations when classifying organizational initiatives.

A logistics company has asked a coordinator to classify four proposed efforts before assigning governance. One effort will create a new regional distribution center and then close after handover. A second will process customer orders every day using an established procedure. A third will periodically update the standard order-processing procedure as regulations change. The fourth will operate a temporary pilot to test an unproven delivery model and deliver recommendations. Which classification is most accurate for the temporary pilot?

Correct Answer: C. It is a project because it is temporary and produces a unique result, even if that result is recommendations.
Explanation:

A project is a temporary endeavor undertaken to create a unique product, service, or result. The pilot has a defined temporary purpose and produces a unique result - recommendations about an unproven model - so it is a project. Routine order processing is ongoing operations. Periodic procedure updates may be managed as operational work depending on their nature, but that does not make the pilot an operation. Potential influence on future work does not by itself make an effort a program or portfolio.

Question 3

New Multiple answers

Topic: Project Management Fundamentals and Core Concepts

Skill tested: Applies progressive elaboration and change control to manage an evolving project scope baseline.

A municipal facilities project has an approved scope baseline for renovating a public library. During construction, the librarian identifies an accessibility feature that appears necessary, while the contractor also proposes a material substitution to address a supply delay. The project manager has authority to assess changes but cannot approve changes to the baseline alone; the project's designated change control body decides those requests. The team has not yet established whether either proposal affects cost, schedule, or compliance. Which TWO actions should the project manager take next? Select TWO.

Correct Answer: B. Record both proposals as change requests and analyze their impacts against the approved baselines and applicable requirements.; D. Submit the accessibility feature and substitution to the designated change control body for disposition after impact analysis.
Explanation:

Proposed changes should be documented and analyzed for effects on scope, schedule, cost, quality, and relevant compliance obligations. The project manager then submits them through the established change control process; the authorized body decides whether to approve, reject, or defer them. Schedule pressure does not authorize an uncontrolled substitution, and alignment with the project's purpose does not authorize the project manager to revise the baseline independently. A baseline can be changed through approved change control, so automatic rejection is also inappropriate.

Question 4

New Single answer

Topic: Project Management Fundamentals and Core Concepts

Skill tested: Uses stakeholder analysis to tailor engagement actions to influence, interest, and project impact.

A project coordinator is supporting a citywide waste-collection redesign. The chief operating officer has substantial decision authority but has attended only one meeting and says the redesign is not a current priority. Neighborhood representatives have little formal authority but are highly interested because collection routes will change near their homes. A regulatory liaison has both high influence and high interest in whether service obligations are met. The team has limited time for individual meetings. Which engagement approach is most appropriate?

Correct Answer: A. Keep the chief operating officer satisfied, engage neighborhood representatives with focused impact information, and manage the regulatory liaison closely.
Explanation:

Stakeholder engagement should reflect both influence and interest, while communication should address each stakeholder's concerns. A high-influence stakeholder with lower current interest should be kept satisfied; a low-influence, high-interest group should receive timely, relevant information about local impacts; and a stakeholder high in both dimensions should be managed closely. The uniform-report approach ignores these differences. The other mappings misclassify at least one stakeholder and risk either overlooking regulatory needs or over- or under-engaging groups.

Question 5

New Multiple answers

Topic: Project Management Fundamentals and Core Concepts

Skill tested: Chooses governance and escalation actions appropriate to a project issue and delegated authority.

An assistant project manager on a warehouse automation project learns that a vendor's test results show a repeated safety interlock failure. The operations team wants to continue testing because the planned opening is only six weeks away. The project management plan assigns safety acceptance to the sponsor and prohibits production use before acceptance; the assistant project manager cannot waive that requirement. The schedule impact is not yet known. Which TWO actions are most appropriate? Select TWO.

Correct Answer: B. Document the failure as an issue, preserve the evidence, and assess immediate exposure with the appropriate technical and safety leads.; C. Escalate the safety acceptance decision promptly to the sponsor or designated authority, including the known facts and uncertainty.
Explanation:

A failure already observed is an issue, not merely a possible future risk. The team should document it and assess exposure with qualified leads, while promptly escalating the acceptance decision because the assistant project manager lacks authority to waive a safety gate. Waiting for a complete schedule analysis delays a potentially important safety decision. Continuing in production mode without authorization or deleting the requirement would bypass governance rather than resolve the issue.

Question 6

New Single answer

Topic: Project Management Fundamentals and Core Concepts

Skill tested: Applies tailoring by adapting project practices to risk, complexity, and organizational constraints.

A small internal team is delivering a low-risk reporting enhancement using familiar technology. The organization's project policy requires an approved charter, a named sponsor, and documented acceptance criteria, but it allows other project practices to be tailored. The team proposes weekly steering committee meetings, a detailed multi-level risk register, and separate formal sign-offs for each minor report change. The sponsor wants sufficient control without imposing unnecessary overhead. What should the coordinator recommend?

Correct Answer: D. Retain the mandatory charter, sponsor, and acceptance criteria, then tailor reporting, risk documentation, and change handling to the project's low risk and complexity.
Explanation:

Tailoring means selecting and adapting practices to suit the project while still complying with mandatory organizational requirements. The charter, sponsor, and acceptance criteria remain required; meeting cadence, risk documentation depth, and change procedures can be proportionate to the project's low risk and complexity. Applying every heavyweight practice adds overhead without a demonstrated benefit. Conversely, small size does not justify removing required governance, and an adaptive lifecycle does not inherently eliminate governance or acceptance criteria.

Question 7

New Single answer

Topic: Project Management Fundamentals and Core Concepts

Skill tested: Selects an appropriate project success measure by considering deliverables, benefits, and stakeholder expectations.

A nonprofit's donor portal replacement is delivered on its approved date and within its cost limit. The team also meets all agreed technical acceptance criteria. Three months later, donor retention has not improved, but the business case stated that improved retention was a benefit to be measured over the following year. The sponsor asks the project coordinator to report whether the project was successful. Which response is most appropriate?

Correct Answer: A. Report that the project met its delivery and acceptance objectives, while tracking the longer-term benefit realization separately against its measures.
Explanation:

Project delivery performance and realization of intended benefits are related but distinct. The project met its stated delivery constraints and technical acceptance criteria, while donor retention is a longer-term outcome that the business case expects to measure over a year. The coordinator should report both facts and ensure benefit tracking continues through the appropriate ownership and governance arrangements. Declaring failure before the measurement period ends is premature; ignoring the benefit or automatically extending the project confuses delivery with ongoing benefits realization.

Question 8

New Single answer

Topic: Predictive, Plan-Based Methodologies

Skill tested: Calculates schedule variance from earned value and interprets whether work is ahead or behind schedule.

A predictive office-relocation project has a planned value of $240,000 and an earned value of $210,000 at its monthly status date. The project manager reports that actual cost is $205,000, but the sponsor asks specifically whether the amount of work accomplished is ahead of or behind the schedule baseline. The team uses earned value management and defines schedule variance as earned value minus planned value. Which conclusion should the coordinator report?

Correct Answer: D. Schedule variance is negative $30,000, so the project is behind schedule.
Explanation:

Schedule variance is EV - PV, or $210,000 - $240,000 = -$30,000. A negative schedule variance indicates that the value of work accomplished is less than the value planned by the status date. Actual cost is not part of the SV calculation; using it would produce the cost variance, EV - AC = $5,000, which does not answer the sponsor's schedule question. The positive $30,000 result reverses the subtraction and therefore reverses the interpretation.

Question 9

New Single answer

Topic: Predictive, Plan-Based Methodologies

Skill tested: Determines the critical path from activity durations and precedence relationships in a project network.

A facilities project has the following activities, with durations in workdays and finish-to-start dependencies: A (3) begins first; B (4) and C (2) both follow A; D (5) follows B; E (6) follows both C and D; and F (2) follows E. There are no resource constraints or lags. The project manager needs the earliest possible completion time and the controlling sequence before evaluating a proposed schedule compression. Which sequence is the critical path, and what is its duration?

Correct Answer: C. A-B-D-E-F, 20 workdays
Explanation:

The paths through the network are A-B-D-E-F, with duration 3 + 4 + 5 + 6 + 2 = 20 days, and A-C-E-F, with duration 3 + 2 + 6 + 2 = 13 days. Since E must wait for both C and D, it cannot begin until the longer predecessor branch through D finishes. The longest path controls the earliest project completion, so the critical path is A-B-D-E-F at 20 workdays. The other listed sequences either omit a required dependency or are shorter.

Question 10

New Multiple answers

Topic: Predictive, Plan-Based Methodologies

Skill tested: Builds a deliverable-oriented WBS and distinguishes decomposition from schedule sequencing.

A predictive project will install a new customer-service center. The approved scope includes facility fit-out, network and telephony, staff training, and operational handover. The team needs a WBS that supports scope verification and later schedule development. The sponsor is concerned that a list of dates and activities may be mistaken for the scope baseline, and the coordinator must also ensure the WBS is decomposed to a useful level without prescribing sequence. Which TWO practices best meet these needs? Select TWO.

Correct Answer: A. Include the complete project scope in the WBS and use a WBS dictionary to clarify work-package content and boundaries.; B. Organize the WBS around project deliverables and subdeliverables, decomposing them until work packages can be estimated and assigned.
Explanation:

A deliverable-oriented WBS decomposes the total approved scope into manageable components, with work packages suitable for estimating, assigning, and monitoring. The WBS dictionary can clarify each work package's content, boundaries, and acceptance information. Together these support scope verification and provide a basis for schedule development. A WBS does not define sequence or dependencies; those belong in schedule planning. Organizing around people or stopping decomposition solely at individual assignment can obscure scope and produce packages that are not measurable or manageable.

Question 11

New Single answer

Topic: Agile Frameworks/Methodologies

Skill tested: Selects an adaptive iteration length that supports frequent feedback while allowing a usable increment.

A product team is building an online claims service. Policy rules change frequently, and claims specialists can attend review sessions every two weeks. A working increment can be demonstrated after roughly ten business days, but each deployment requires a separate security review that takes several days. The team has repeatedly lost useful feedback when it plans work for a full quarter. The organization does not require production deployment at the end of every iteration. Which iteration length is the best starting point?

Correct Answer: A. Two weeks, matching the available specialist feedback and the team's demonstrated increment cycle.
Explanation:

A two-week iteration aligns with the specialists' availability and the team's ability to produce a demonstrable increment, enabling regular inspection and adaptation. Iteration length should support a useful feedback cadence and a sustainable ability to complete work; it does not require a production release at every iteration. A one-week cycle may be possible but is not supported by the stated feedback and delivery evidence. Longer cycles delay learning, while security review can be planned without making quarterly iterations necessary.

Question 12

New Multiple answers

Topic: Agile Frameworks/Methodologies

Skill tested: Selects backlog planning units and refinement practices for uncertain, evolving requirements.

A software group is developing a self-service tax-filing product. Regulations and user feedback cause frequent changes, so detailed specifications for the entire release would become stale. The product owner needs to maintain a prioritized view of desired outcomes while allowing the team to understand near-term work before committing to an iteration. The team also wants to avoid treating a high-level idea as ready for implementation. Which TWO practices fit this situation? Select TWO.

Correct Answer: B. Maintain a prioritized product backlog whose items can be refined as new information becomes available.; D. Use sufficiently refined user stories or other backlog items for near-term iteration planning, clarifying acceptance expectations with the product owner.
Explanation:

An adaptive team can manage changing needs through a prioritized product backlog and progressive refinement. Higher-level items may remain broad until they are closer to implementation; near-term work should be understood well enough for the team to plan and agree on expected outcomes. Freezing all criteria upfront undermines adaptation, while a comprehensive fixed breakdown assumes requirements will remain stable. Requiring detailed estimates for every future item creates waste and delays learning rather than improving near-term planning.

Question 13

New Single answer

Topic: Agile Frameworks/Methodologies

Skill tested: Uses iteration reviews and retrospectives to inspect product outcomes and improve team processes.

A team building a mobile inspection application finishes each two-week iteration with all planned work marked complete. Inspectors attend demonstrations, but the product owner has repeatedly found that the demonstrated features do not address the workflow problems raised in the previous review. The team also has recurring delays caused by unclear handoffs. There is no contractual need to lock the next iteration scope weeks in advance. What should the team do to improve both product alignment and its working process?

Correct Answer: D. Use the review to inspect the increment with stakeholders and adapt backlog priorities, then use a retrospective to identify and try improvements to team practices.
Explanation:

An iteration review provides an opportunity to inspect the product increment with stakeholders and adapt the product backlog based on feedback. A retrospective focuses on how the team worked and identifies experiments to improve collaboration and delivery, such as addressing unclear handoffs. Keeping plans fixed or lengthening iterations would delay feedback, which is already exposing a product-alignment problem. Reversing the purposes of review and retrospective also confuses product inspection with process improvement.

Question 14

New Single answer

Topic: Agile Frameworks/Methodologies

Skill tested: Adapts iteration planning and work selection when changing requirements exceed team capacity.

At the start of a three-week iteration, a team commits to a set of work based on its historical capacity. During the first week, a newly issued accessibility requirement makes one planned feature insufficient, and the product owner requests a different capability instead. The team cannot add people during the iteration, and the product owner has authority to order the backlog but not to require overtime. The iteration goal is still valuable, but the original item mix may no longer support it. What is the best next step?

Correct Answer: C. Have the team and product owner review the impact, renegotiate the iteration scope while preserving the goal where feasible, and reorder remaining backlog work.
Explanation:

Adaptive planning allows the team and product owner to respond to new information while respecting capacity and the iteration goal. They should assess the changed requirement, adjust the selected work where appropriate, and reorder backlog items; work should not be imposed through overtime or unilateral assignment. Adding scope without adjustment ignores the capacity constraint. A change does not automatically require cancellation if the goal remains useful, although the team and product owner should reconsider the iteration if that goal is no longer viable.

Question 15

New Single answer

Topic: Business Analysis Frameworks

Skill tested: Selects a communication channel based on urgency, audience, sensitivity, and need for dialogue.

A business analyst supporting a payroll system replacement discovers a likely defect that could cause the next payroll run to omit payments for a small group of employees. The payroll director must decide within an hour whether to delay the run. The evidence includes restricted employee details, and the director needs to ask questions before deciding. The organization requires sensitive data to be handled through approved channels and wants a durable decision record. Which communication approach is most appropriate?

Correct Answer: A. Contact the payroll director immediately through an approved secure, interactive channel, share only necessary evidence, and document the decision through the controlled project record.
Explanation:

The decision is urgent and requires two-way discussion, so a direct interactive channel is appropriate. Using an approved secure channel limits exposure of sensitive employee information, while recording the outcome in the controlled project record provides traceability. A broad email or general collaboration channel may disclose restricted details and can delay focused dialogue. Waiting for a monthly report or governance meeting misses the decision deadline. The communication should be targeted to the decision-maker, with only the information necessary to decide.