Free PMI Risk Management Professional PMI-RMP Exam Questions

Last updated: · 12 practice questions with answers and explanations

Page: 1 / 20 Total 289 questions

Want more questions? Get Premium Access.

Question 1

New Single answer

Topic: Risk Strategy and Planning

Skill tested: Assigns preliminary risk-document review responsibilities and selects relevant historical sources.

A transit agency is preparing a risk management approach for a new fare-payment program. The delivery team includes agency staff and a systems integrator, and the program spans several related projects. The agency has completed two similar technology procurements, but their lessons learned are held by a separate operations group; the integrator also has industry benchmark data. The project manager is drafting the risk plan and wants the initial risk identification to use relevant evidence without assuming that every document applies. What should the project manager do FIRST?

Correct Answer: C. Assign accountable reviewers to gather and assess relevant historical lessons, benchmarks, and project documents, then establish which sources inform this project's risk process.
Explanation:

A preliminary document analysis should deliberately gather and review relevant sources, including prior lessons learned, historical data, benchmarks when available, and project-specific documents. Responsibility may be assigned to appropriate roles, but the project manager remains accountable for ensuring the review is useful and its outputs inform the risk process. The integrator alone may lack organizational and operational context; postponing the review loses useful evidence; and copying an old register assumes the previous project's risks, categories, and ratings apply unchanged.

Question 2

New Single answer

Topic: Risk Strategy and Planning

Skill tested: Selects a risk-planning approach that reflects delivery methodology, environment, and organizational risk appetite.

A medical-device company is planning a software-enabled product launch. Hardware certification follows fixed stage gates, while software features are delivered iteratively. Regulatory requirements are stable, but market expectations are changing quickly, and the executive committee has a low appetite for compliance risk but permits controlled experimentation in user-interface design. Several business units have different levels of experience with risk ownership. Which planning approach is MOST appropriate?

Correct Answer: D. Tailor a hybrid risk approach to the delivery methods and environment, establish category-sensitive thresholds aligned to appetite, and assess organizational risk culture when assigning engagement and governance.
Explanation:

The project has both predictive certification work and iterative software work, so risk planning should fit the methodology rather than impose one cadence on all components. Risk thresholds and response authority should reflect organizational appetite: low tolerance for compliance exposure does not preclude controlled experimentation in a different category. Assessing risk culture maturity also helps determine how much coaching, facilitation, and governance are needed. A uniform process or thresholds can mismanage distinct exposures, while deferring appetite until later leaves key planning decisions unsupported.

Question 3

New Single answer

Topic: Risk Strategy and Planning

Skill tested: Integrates stakeholder risk requirements and governance into a project risk management plan.

A regional utility is developing a risk plan for a grid-control upgrade involving an internal engineering group, a regulator, and a vendor. The project charter defines cost and commissioning targets, but it does not specify who may approve risk acceptance, how risk information should be escalated, or how often stakeholders need updates. The regulator requires traceable treatment of safety-related exposure, and the vendor uses a separate risk log. The project manager must establish a workable process before identification workshops begin. What is the BEST next action?

Correct Answer: B. Consult the relevant stakeholders and governance authorities to define risk roles, thresholds, escalation paths, reporting cadence, and integration of the vendor's risk information in the project risk plan.
Explanation:

The project risk plan should establish how risk work will be performed, including roles, authority, thresholds, escalation, reporting, and how relevant supplier information will be integrated. Stakeholder and regulatory requirements must be reflected while retaining appropriate project governance over commercial and schedule exposures. Adopting the vendor's process without tailoring may leave agency responsibilities unclear. Delegating all thresholds to the regulator exceeds its remit, and waiting to define ownership and escalation until risks emerge undermines consistent, timely management.

Question 4

New Single answer

Topic: Risk Identification

Skill tested: Facilitates structured risk identification using diverse stakeholder perspectives and project evidence.

A city is replacing its permitting platform. Early workshops attended only by the software team produced risks focused on interfaces and data migration. Permit reviewers later report seasonal workload peaks, while customer-service staff describe recurring address errors in submitted applications. The project has limited time for another broad workshop, but it must identify threats and opportunities across technical and operational work before the design baseline is approved. What should the risk manager do NEXT?

Correct Answer: D. Conduct targeted interviews or focus groups with the omitted operational stakeholders, review relevant service data and project evidence, and analyze the resulting statements in the permitting context.
Explanation:

Risk identification should draw on appropriate meetings, interviews, focus groups, subject-matter expertise, and relevant evidence. Targeted engagement is a practical way to address a known participation gap under time pressure; service data can help distinguish recurring conditions from isolated observations. The information must be interpreted in the business context and captured as threats or opportunities where appropriate. Limiting identification to technical staff omits operational exposure, while deferring until testing may make responses more costly or too late.

Question 5

New Single answer

Topic: Risk Identification

Skill tested: Evaluates assumptions and constraints for cascading effects on project objectives.

A data-center migration plan assumes that the source-system owner will provide test data within five business days of each request. The owner has not formally committed, and its team observes a two-week shutdown every summer. The migration schedule contains only three days of float before a contractual cutover date. The project team has treated the five-day turnaround as a planning fact and has not linked it to any risk. What is the MOST appropriate action during identification?

Correct Answer: D. Challenge and validate the assumption with the system owner, assess the probability and consequences of delay including the shutdown cascade, and document the associated risk and trigger.
Explanation:

An unconfirmed assumption should be challenged with the stakeholder who controls the dependency, then assessed for uncertainty and its consequences. Here, slow data delivery could consume the small schedule float, and the seasonal shutdown could delay testing enough to threaten the contractual cutover. Documenting the risk and a useful trigger enables timely monitoring and response planning. An assumption does not become a constraint merely because it appears in a schedule; removing it hides uncertainty, while blanket padding avoids analysis and may misallocate contingency.

Question 6

New Multiple answers

Topic: Risk Identification

Skill tested: Documents risk causes, uncertain events, effects, triggers, and escalation thresholds.

A logistics company is identifying risks for a warehouse automation rollout. The conveyor supplier has not yet completed endurance testing, and a pilot has shown intermittent sensor faults. The agreed identification format requires a cause-event-effect statement, a monitorable trigger, and an escalation threshold where one is established. The team must distinguish evidence that signals a possible event from the event's impact, so owners can act before the delivery date is threatened. Select TWO actions that best meet this requirement. How many answers should you select?

Correct Answer: C. Write a statement linking incomplete endurance evidence to the possibility of an automation outage and its schedule or throughput effect, and identify the relevant risk owner.; D. Use a measurable sensor-fault rate or missed endurance-test milestone as a trigger, and define escalation when the agreed tolerance is crossed.
Explanation:

A useful risk statement distinguishes the cause, uncertain event, and effect; the incomplete endurance evidence is a cause or condition, while a possible outage is the event and delay or reduced throughput is an effect. A measurable fault rate or missed milestone can signal that the risk is becoming more likely, and a threshold supports consistent escalation. The supplier's test status alone is not the event, and impact is not a trigger. Observed faults do not make a future outage certain, nor does receipt of a report by itself resolve exposure.

Question 7

New Single answer

Topic: Risk Analysis

Skill tested: Prioritizes risks using agreed probability-impact criteria, urgency, and risk categories.

A public-sector program has completed qualitative analysis of four risks. Its approved matrix defines ratings consistently, and its risk management plan requires consideration of urgency as well as probability and impact. A compliance threat has moderate probability and severe impact with an imminent regulatory decision date; a technical opportunity has high probability and moderate benefit but cannot be exploited until a later release; a supplier threat has high probability and moderate impact with a response window closing this week. Executives want a defensible order for near-term attention without confusing category labels with priority. What should the risk manager do?

Correct Answer: C. Use the agreed matrix and definitions to classify and prioritize each risk, then incorporate urgency and response timing when sequencing action.
Explanation:

Qualitative analysis should apply the agreed probability and impact definitions and matrix, with risk categories used consistently rather than as automatic priority rankings. Urgency matters: a high-probability supplier threat with a closing response window may require immediate action, while the compliance threat's imminent decision date also raises urgency. The team can make a defensible priority decision using the approved criteria and timing. Probability alone ignores impact, category alone imposes an unsupported rule, and quantitative estimates are not required to complete this qualitative prioritization.

Question 8

New Single answer

Topic: Risk Analysis

Skill tested: Uses sensitivity analysis to identify which uncertain input most affects project cost exposure.

A construction project faces uncertainty in three cost drivers: steel price, the number of foundation redesigns, and the duration of a required environmental review. The sponsor has asked which driver most strongly affects the current cost forecast so that the team can focus further analysis. The project has reliable ranges for all three inputs and a cost model that can recalculate the forecast while varying one input at a time. The team is not being asked to estimate the probability of a specific completion date or to compare all possible combined outcomes. Which analysis is MOST appropriate?

Correct Answer: A. Sensitivity analysis that varies each input across its range and compares its effect on the cost forecast.
Explanation:

Sensitivity analysis is suited to identifying which uncertain input has the greatest effect on a selected outcome. The scenario provides reliable ranges and a model that can vary one cost driver at a time, directly answering the sponsor's question. A probability-impact matrix supports qualitative prioritization, not comparative cost sensitivity. A decision tree requires decision alternatives and branch outcomes, while a Monte Carlo schedule simulation addresses schedule probability rather than the requested influence on the cost forecast.

Question 9

New Single answer

Topic: Risk Analysis

Skill tested: Interprets quantitative schedule-risk output to support realistic contingency and management decisions.

A rail modernization project uses a quantitative schedule model that includes identified threats, dependencies, and activity uncertainty. The deterministic schedule meets the required opening date, but the modeled completion distribution shows only a 35% chance of meeting it. The sponsor asks the team to recommend a defensible date and identify where schedule contingency is needed. The model has been reviewed for assumptions, and management wants a confidence-based forecast rather than another deterministic critical-path calculation. What should the risk analyst do?

Correct Answer: D. Use the modeled completion distribution to recommend a target at the agreed confidence level, examine schedule drivers, and plan contingency or responses accordingly.
Explanation:

A quantitative schedule-risk model combines uncertainty and dependencies to produce a distribution of possible completion dates. Using an agreed confidence level provides a more defensible target than relying on a deterministic date with only a 35% modeled likelihood. Reviewing the influential schedule drivers also helps direct response actions and contingency. The deterministic calculation does not represent the modeled exposure, choosing the earliest outcome ignores uncertainty, and summing every threat assumes all occur and affect the same path.

Question 10

New Multiple answers

Topic: Risk Response

Skill tested: Selects response strategies and accountable owners that directly address prioritized risks.

A cloud-migration project has two high-priority risks. First, a legacy application may fail to meet a mandatory data-residency rule; the sponsor has authority to remove the application from the migration scope, and no compliant hosting option is currently verified. Second, a performance test may reveal that the chosen database cannot meet peak throughput; a specialist can test an alternative indexing design before the architecture is frozen. The team must choose strategies that address the underlying exposure and assign people who can execute the response. Select TWO actions that best fit the situation. How many answers should you select?

Correct Answer: C. Mitigate the throughput threat by testing and validating the alternative indexing design, with the database specialist owning the action.; D. Avoid the data-residency threat by removing the application from the migration scope, with the sponsor accountable for the scope decision.
Explanation:

Removing the application from scope avoids the residency exposure when no compliant hosting option has been verified and the sponsor has authority to make that decision. Testing an alternative indexing design reduces the likelihood or impact of failing the throughput requirement, so mitigation is appropriate and the specialist is positioned to carry out the action. Acceptance does not address either identified exposure, and a scheduler lacks the relevant authority or expertise. Contractual transfer does not establish compliance, while enhancing is a strategy for opportunities, not threats.

Question 11

New Single answer

Topic: Risk Response

Skill tested: Assesses response effectiveness against risk objectives and project cost-schedule trade-offs.

A chemical-processing project has a credible risk of a prolonged outage if a critical pump fails. The proposed mitigation adds a standby pump and automated switchover. Engineering estimates that it will substantially reduce outage impact, but it adds capital cost, maintenance work, and two weeks to commissioning. The sponsor's objectives permit moderate capital investment but do not permit the commissioning date to move. Before approving the response, what should the risk manager do?

Correct Answer: D. Evaluate the expected risk reduction and residual exposure against cost, schedule, maintenance, and project objectives, then adjust or select a response that preserves the date.
Explanation:

Response effectiveness is not measured only by a reduction in probability or impact. The proposed standby pump may reduce outage consequences, but its commissioning delay conflicts with an explicit project objective; its cost and ongoing maintenance also matter. The team should assess the trade-offs and residual risk, then determine whether the design can be changed, another response is preferable, or acceptance is justified within appetite. Automatic approval ignores the schedule constraint, while rejecting any cost or dropping monitoring is not a reasoned response decision.

Question 12

New Multiple answers

Topic: Monitor and Close Risks

Skill tested: Monitors response effectiveness and residual or secondary risks using performance evidence.

A manufacturing expansion team implemented a mitigation for a risk that a new cooling system would not meet production demand. The response added a bypass line and changed the control sequence. Initial test results show adequate capacity, but the bypass may increase energy use, and the main production baseline has not yet incorporated the revised commissioning sequence. The risk owner reports the original risk as resolved. The project manager must verify the response, account for new exposure, and keep governance information current. Select TWO actions that should be taken. How many answers should you select?

Correct Answer: A. Monitor performance data against the baseline and response criteria, assess the remaining cooling exposure, and document the residual risk.; C. Identify and assess increased energy use or control-sequence effects as potential secondary risks, then communicate material impacts.
Explanation:

A successful initial test is evidence, not proof that the response is fully effective across operating conditions. Monitoring performance against the baseline and response criteria helps determine whether exposure remains and supports accurate residual-risk documentation. The bypass and changed control sequence can create secondary risks, including energy or commissioning impacts, which should be assessed and communicated. Immediate closure is premature, implementation does not itself approve a baseline change, and discarding response history weakens traceability and lessons learned.