Free PRINCE2 MSP Practitioner, 5th edition Exam MSP-Practitioner Exam Questions

Last updated: · 11 practice questions with answers and explanations

Page: 1 / 8 Total 75 questions

Want more questions? Get Premium Access.

Question 1

New Single answer

Topic: Programme Management

Skill tested: Selects the appropriate transformational flow when programme outcomes require staged delivery and review.

A regional health organization has approved a programme to reduce avoidable hospital admissions. The blueprint identifies several interdependent changes to clinical pathways, workforce skills and digital services. The executive team wants an early, controlled release in two districts so that operational evidence can inform later deployment, while retaining the ability to stop or reshape the remaining work if outcomes are not promising. Which approach best aligns programme delivery with this requirement?

Correct Answer: B. Structure the programme into tranches, using each tranche review to assess progress, continued viability and readiness for the next stage.
Explanation:

Tranching provides controlled stages in which the programme can coordinate related projects and change, review progress and continued justification, and make an informed decision about proceeding. It supports the organization's need to learn from an early deployment before committing to later rollout. A single tranche removes that intended decision point; isolated project lifecycles do not provide the required programme-level review. Beginning benefits realization before defining the target operating model reverses the necessary logic of shaping the change.

Question 2

New Multiple answers

Topic: Stakeholder Engagement

Skill tested: Chooses targeted engagement methods to resolve conflicting stakeholder expectations and sustain commitment.

A national service transformation depends on regional directors adopting a shared operating model. Several directors publicly support the programme, but local managers privately fear losing decision authority, and frontline staff say the proposed consultation sessions do not address daily workflow concerns. The sponsor requests a rapid communications campaign to secure visible support before the next governance meeting. The programme team has limited capacity and cannot hold large-scale events in every region. Which TWO actions are most appropriate? Select TWO.

Correct Answer: C. Map stakeholder interests, influence and concerns, then tailor engagement to the groups whose commitment or concerns could affect adoption.; E. Work with regional leaders and representative frontline staff to explore concerns and shape practical responses through two-way engagement.
Explanation:

Stakeholder engagement should be based on understanding relevant interests, influence and concerns, then selecting proportionate, two-way approaches. Mapping enables limited capacity to be focused where commitment and adoption are at risk. Direct discussion with regional leaders and frontline representatives can surface practical barriers and inform responses. A uniform presentation is communication, not sufficient engagement; sponsor pressure may suppress concerns without resolving them. Excluding hesitant groups risks resistance and weakens adoption.

Question 3

New Single answer

Topic: Governance and Control

Skill tested: Aligns programme decision rights, assurance and escalation with governance accountability.

A programme's board has delegated routine coordination to the programme manager but reserved major scope changes and continuation decisions to itself. A project manager has identified a proposed design change that would improve usability but increase cost beyond the project tolerance and alter a programme-level benefit measure. The project manager has asked the supplier to begin the change immediately to avoid delay. What should the programme manager do FIRST?

Correct Answer: D. Stop the unapproved commitment, assess the change and its effects through the established change and escalation arrangements, and submit it to the authorized decision-maker.
Explanation:

The change exceeds project tolerance and affects a programme-level benefit, so it must be assessed and routed to the decision authority defined by governance. The programme manager should prevent an unauthorized commitment while establishing effects on cost, schedule, scope and benefits, then escalate appropriately. The programme manager cannot assume authority merely because the benefit is programme-level. Assurance provides independent confidence, not authorization. Proceeding during review creates uncontrolled commitment and undermines accountability.

Question 4

New Multiple answers

Topic: Benefits Realization

Skill tested: Defines accountable benefit ownership, measurement baselines and post-transition realization arrangements.

A finance transformation programme will introduce a new procurement process and supporting system across several business units. The business case forecasts lower purchasing costs, but the forecast depends on managers consolidating demand after deployment. Project teams will deliver the system and training; operational managers will control purchasing behavior after transition. The sponsor wants benefits reported at programme closure, although savings may take a year to emerge and the baseline data currently use inconsistent category definitions. Which TWO actions should the programme establish? Select TWO.

Correct Answer: B. Define consistent benefit measures and baselines, including when and how savings will be measured.; C. Assign operational benefit owners and document their accountability for realizing and reviewing the savings after transition.
Explanation:

Benefits depend on changes in operational behavior, so accountable operational owners must remain responsible after transition. Consistent measures and baselines are also necessary to distinguish actual savings from inconsistent categorization or unrelated changes. System acceptance and training are outputs or enabling conditions, not proof of realized benefits. The programme manager cannot replace line management ownership once operations take responsibility. Ending tracking at project completion would miss the stated realization period and weaken evidence.

Question 5

New Single answer

Topic: Resource Management

Skill tested: Resolves cross-programme resource contention using priorities, capacity visibility and governance escalation.

Two projects in a customer-service programme require the same small group of experienced process analysts during the next quarter. One project supports a regulatory deadline; the other supports an early benefit pilot, but its schedule has some flexibility. Both project managers claim their work is critical, and the analysts' functional manager has not agreed to release them full time. The programme cannot add contractors because onboarding and security checks would outlast the quarter. What is the best next step?

Correct Answer: D. Review integrated priorities, dependencies and actual analyst capacity with the relevant managers, then agree and communicate a feasible allocation through programme governance.
Explanation:

Programme resource management requires visibility of demand, capacity, priorities and dependencies across the component projects, with agreement from the managers who control the people. The regulatory deadline and pilot flexibility inform an evidence-based allocation, which should be recorded and communicated through appropriate governance. Informal competition leaves the conflict unresolved; an arbitrary equal split may make both commitments fail. Permanently transferring staff does not address the immediate capacity decision or respect existing management arrangements.

Question 6

New Single answer

Topic: Problem Solving

Skill tested: Uses structured analysis to distinguish symptoms from root causes before selecting corrective action.

A programme to modernize a utility's field operations is missing several deployment milestones. Project reports attribute the delays to supplier performance, but the supplier's delivery records show that equipment is arriving on time. Site teams report that they cannot schedule installation because local access permissions and outage windows are confirmed late. The programme board asks for a recovery plan by the end of the week, and the programme manager must avoid committing to additional supplier capacity before the cause is understood. What should the programme manager do NEXT?

Correct Answer: D. Compare milestone and dependency evidence across affected sites, identify where permission and outage-window decisions are delayed, and confirm the cause with responsible stakeholders.
Explanation:

The evidence points to a dependency and decision-timing problem rather than late equipment. The next step is to validate the pattern across sites and confirm the root cause with those responsible for access and outage approvals before choosing corrective action. Additional equipment would not remove the constraint, and replacing a supplier based on unverified reports risks cost and further delay. Reducing quality checks treats the symptom by creating new operational risk.

Question 7

New Multiple answers

Topic: Risk and Issue Management

Skill tested: Separates uncertain threats from realized issues and assigns appropriate responses, owners and controls.

A programme is preparing a staged launch of a new public benefits service. A security review identifies a credible possibility that a partner's interface will expose personal data if a planned configuration is not implemented correctly. Separately, testing has confirmed that a subset of migrated records already contains incorrect eligibility dates. The launch date is fixed by a statutory commitment, and the programme board requires both matters to be managed transparently. Which TWO actions are appropriate? Select TWO.

Correct Answer: C. Record the potential interface exposure as a risk, assign an owner, assess its likelihood and impact, and agree preventive or mitigating responses.; E. Manage the confirmed incorrect dates as an issue, assess the consequences and coordinate corrective action before affected records are used.
Explanation:

The possible exposure is uncertain and should be managed as a risk, with an accountable owner, assessment and planned response. Incorrect dates have already been found, so that condition is an issue requiring impact assessment and corrective action. Treating the confirmed defect as merely a future risk obscures its current status. A planned configuration does not eliminate exposure without implementation and verification. Suppliers may perform responses, but programme governance retains oversight and escalation responsibility.

Question 8

New Single answer

Topic: Tailoring

Skill tested: Tailors programme controls proportionately while preserving essential governance, accountability and assurance.

A small internal programme will consolidate three administrative services into one shared service. Its organization has little experience with formal programme methods, and the executive sponsor asks the team to remove all programme documentation and independent assurance to keep the approach lightweight. The change affects payroll and personal data, while the component projects are short and use established delivery controls. The programme needs to remain proportionate without losing control of important decisions and risks. What is the best tailoring approach?

Correct Answer: C. Tailor the scale and format of programme practices to the context, while retaining clear accountability, decision routes, benefits control and proportionate assurance for material risks.
Explanation:

Tailoring adapts the scale, formality and implementation of practices to the programme's context; it does not remove the controls needed to govern change. The personal-data and payroll impacts justify proportionate assurance and clear accountability, while short projects and established controls may allow leaner documentation and meetings. Applying a large-programme model unchanged is inefficient. Project controls alone do not manage cross-project outcomes and benefits, and informal updates provide inadequate traceability.

Question 9

New Single answer

Topic: Programme Management

Skill tested: Uses the blueprint and target operating model to sequence capability delivery and organizational change.

A logistics company's programme blueprint describes a future operating model with centralized inventory planning, redesigned depot roles and new forecasting capability. A project team proposes releasing the forecasting tool immediately because it is technically ready. However, depots have not agreed new decision rights, staff have not been trained, and the expected inventory benefit depends on planners using the tool within the centralized process. The board wants an early benefit but does not want a release that creates parallel ways of working. What is the MOST appropriate decision?

Correct Answer: C. Sequence the release with the required process, role and capability changes, using a controlled pilot only where the operating model can be applied and benefits measured.
Explanation:

The blueprint describes an interdependent future state; technical delivery alone will not produce the inventory benefit. Release should be sequenced with the decision rights, process and capability changes that enable the new way of working. A pilot can provide early evidence when it can operate under the intended model and measure outcomes. A broad immediate release risks parallel practices and poor adoption. Waiting for simultaneous completion sacrifices sensible staging, while redefining the benefit confuses an output with an outcome.

Question 10

New Multiple answers

Topic: Governance and Control

Skill tested: Establishes integrated assurance and escalation when delivery tolerances and strategic viability are threatened.

An infrastructure programme is delivering several projects under a board-approved mandate. A quality review identifies a recurring defect across multiple projects, while the integrated schedule forecast shows a likely breach of the programme's agreed time tolerance. The programme manager believes the overall strategic outcome remains achievable, but the board has not yet been informed. Project managers propose addressing defects within their own plans and revising local milestones. Which TWO actions should the programme manager take? Select TWO.

Correct Answer: A. Escalate the forecast tolerance breach to the authorized programme governance body, presenting its impact and viable responses for a decision.; D. Ensure the cross-project defect is assessed through appropriate assurance and control, with coordinated corrective action and evidence of resolution.
Explanation:

A recurring defect across projects requires coordinated control and assurance that the underlying cause and corrective actions are addressed, not merely separate local records. A forecast breach is a governance trigger: the programme manager should escalate it promptly with impact and options so the authorized body can decide. Independent milestone changes would conceal the integrated position. Waiting for an actual breach delays decision-making, and closing a finding without verifying resolution provides no reliable assurance.

Question 11

New Single answer

Topic: Benefits Realization

Skill tested: Plans benefit dis-benefit trade-offs and uses evidence to support continued programme investment decisions.

A customer-service programme forecasts reduced handling costs from moving routine requests to self-service. Its first pilot achieves the expected reduction in call volume, but it also increases complaints from customers who rely on accessible assisted service. The business case includes improved satisfaction as a separate outcome, and the next tranche would extend self-service to more customer groups. The sponsor argues that the cost benefit has been proven and requests automatic continuation. What is the best recommendation to the programme board?

Correct Answer: C. Review evidence against the full benefit profile, including the dis-benefit and satisfaction outcome, and decide whether to adapt, proceed or reconsider the tranche.
Explanation:

A programme's investment decision should consider the whole intended outcome profile, including benefits, dis-benefits and their measures - not just one favorable metric. The board needs evidence about the complaints and satisfaction impact before authorizing expansion, and may choose adaptation, continuation with controls, or a different course. Automatic rollout ignores a material consequence. Immediate cancellation assumes the trade-off is unacceptable without assessment. Removing a committed outcome to justify continuation weakens the business case rather than resolving the issue.