Question 1

New Single answer

Topic: Exploring the RTE Role

Skill tested: Distinguishing the RTE's facilitation and servant-leadership accountabilities from line management.

A newly formed ART has missed several PI objectives. The business lead asks the RTE to assign work directly to teams and require daily status reports from each developer so that delivery becomes more predictable. Team members already have Product Owners and Scrum Masters, and the ART's teams are expected to remain self-managing. What should the RTE do to address the concern while staying within the RTE role?

Correct Answer: A. Help the ART identify impediments and improve planning, coordination, and transparency while enabling teams to manage their own work.
Explanation:

The RTE is a servant leader and ART-level coach who facilitates alignment, helps remove impediments, and improves the flow of value. The RTE can make progress and risks visible without taking over team-level decisions. Directing developers or assigning capacity undermines self-management and confuses the RTE role with line management. Product Management contributes to prioritization and the business context, but transferring all ART-level predictability concerns to that group does not address coordination or systemic impediments.

Question 2

New Single answer

Topic: Exploring the RTE Role

Skill tested: Using RTE coaching and facilitation to resolve cross-team conflict without imposing a solution.

During PI Planning, two teams disagree about an interface dependency. Each team proposes a plan that protects its own iteration commitments, but the combined plan leaves an integration gap late in the PI. The technical issue has no clear owner, and the RTE has no authority to dictate the architecture. The teams are capable of resolving the design if they can reach a shared understanding of the trade-offs. What is the most appropriate RTE response?

Correct Answer: A. Facilitate a focused discussion among the teams and relevant technical stakeholders to expose the dependency, evaluate options, and agree on ownership and timing.
Explanation:

The RTE should create the conditions for collaboration and help the ART make dependencies, risks, and decisions visible. A focused facilitation session lets the teams and technical stakeholders make the design decision while clarifying an integrated plan and ownership. Choosing an architecture without authority or sufficient context oversteps the RTE's role. Escalation may be appropriate for unresolved decisions, but it is premature when the teams can work through the trade-offs. Removing a feature avoids rather than resolves the underlying coordination problem.

Question 3

New Single answer

Topic: Applying SAFe Principles

Skill tested: Preparing PI Planning inputs so teams can plan against business context, priorities, and capacity.

An ART is preparing for PI Planning. The business context and draft vision are available, but several features still lack acceptance criteria, and Product Management has not resolved competing priorities. Teams have also reported that their capacity assumptions do not account for planned time off. The organization cannot extend the scheduled planning event. Which action should the RTE take before the event to improve the likelihood of effective planning?

Correct Answer: B. Coordinate with Product Management, Business Owners, and teams to refine planning inputs, clarify priorities and acceptance criteria, and surface realistic capacity assumptions before the event.
Explanation:

Effective PI Planning depends on preparation: stakeholders should clarify the business context and vision, prioritize and refine features sufficiently, and allow teams to use realistic capacity assumptions. The RTE coordinates readiness and helps expose unresolved decisions; the RTE does not own Product Management priorities or team estimates. Asking teams to commit despite missing information creates avoidable uncertainty, while a schedule imposed by the RTE suppresses collaborative planning rather than enabling it.

Question 4

New Multiple answers

Topic: Applying SAFe Principles

Skill tested: Facilitating PI Planning to make dependencies and risks visible and support shared planning.

A distributed ART has reached the second day of PI Planning. Team plans appear locally feasible, but dependency discussions have been scattered across private chat channels. Several risks remain unresolved, and Business Owners have not been asked to evaluate the draft objectives. The RTE wants the event to produce an integrated plan without taking planning authority away from teams. Which THREE actions are most appropriate? Select THREE.

Correct Answer: A. Ask Business Owners to review draft PI objectives and provide business-value input during the planning process.; D. Bring cross-team dependencies into visible planning discussions and ensure the teams identify owners and timing for the coordination.; E. Facilitate a risk review in which risks are made visible and addressed through an appropriate ROAM disposition.
Explanation:

An integrated PI plan requires dependencies to be visible and coordinated across teams, Business Owner participation in evaluating objectives, and explicit handling of risks. The RTE facilitates these activities rather than making all technical decisions. ROAM provides a shared way to resolve, own, accept, or mitigate risks. A centralized schedule imposed by the RTE would undermine team planning and self-management; delegating every technical risk to the RTE also prevents the people closest to the work from owning appropriate responses.

Question 5

New Single answer

Topic: Applying SAFe Principles

Skill tested: Applying economic prioritization to sequence ART work by value, urgency, and cost of delay.

A product group has more candidate features than the ART can reasonably deliver in the next PI. One feature supports a time-limited regulatory commitment, another enables a high-value customer capability, and a third is an internal enhancement with no identified deadline. Stakeholders are arguing for their own requests, and the RTE is asked to facilitate a fair prioritization discussion. What is the best approach?

Correct Answer: C. Facilitate prioritization using economic considerations such as value, time criticality, risk reduction or opportunity enablement, and job size, with accountable stakeholders making the trade-offs.
Explanation:

SAFe economic thinking supports explicit trade-offs using considerations such as value, time criticality, risk reduction or opportunity enablement, and job size. The RTE can facilitate a transparent discussion, while Product Management and relevant business stakeholders retain prioritization accountability. Submission order is arbitrary, and effort alone ignores the economic consequences of delay. Giving stakeholders equal allocations does not optimize value or resolve conflicts among competing business needs.

Question 6

New Single answer

Topic: Applying SAFe Principles

Skill tested: Facilitating structured problem-solving to address recurring ART impediments.

For three consecutive iterations, teams have reported that an integration environment is unavailable when needed. The issue has been mentioned in team retrospectives and ART sync meetings, but no lasting change has followed. Teams are now compensating with manual integration work, increasing delays and defects. The RTE can convene the affected teams and shared-services representatives, but cannot directly change the environment. What should the RTE do next?

Correct Answer: A. Facilitate a problem-solving discussion that examines the recurring cause, identifies an accountable owner and measurable countermeasures, and tracks follow-through.
Explanation:

A recurring systemic impediment calls for more than repeated reporting or local workarounds. The RTE can facilitate root-cause analysis, bring the responsible parties together, establish ownership and measurable improvement actions, and follow up on outcomes. Logging tickets may be part of the response but does not ensure prioritization or resolution. Padding plans hides the cost and preserves the cause, while dictating a technical design exceeds the RTE's authority and may not address the underlying problem.

Question 7

New Single answer

Topic: Executing the PI

Skill tested: Using iteration events and ART synchronization to detect execution risks and coordinate corrective action.

Halfway through a PI, a team's iteration review shows that a feature is unlikely to meet its acceptance criteria because a dependency from another team is late. The affected teams have not raised the issue in ART sync, and the Product Owner is considering reducing scope without consulting stakeholders. The feature remains important to a PI objective. What should the RTE do first?

Correct Answer: B. Use the ART's coordination mechanisms to make the dependency and objective risk visible, bring the affected parties together, and support an agreed recovery or scope decision.
Explanation:

ART execution depends on timely coordination, transparency, and collaboration across teams. The RTE should help surface the dependency and its effect on the PI objective, then facilitate a decision with the affected teams and appropriate stakeholders. The Product Owner should not silently change an important objective, and the RTE should not unilaterally reorder another team's work. Waiting until the system demo delays action when the risk is already known and may reduce the available recovery options.

Question 8

New Multiple answers

Topic: Executing the PI

Skill tested: Interpreting flow measures to identify bottlenecks and improve ART delivery throughput.

An ART's feature lead time has increased over several PIs. The RTE reviews flow data and sees that work frequently waits in a large analysis queue, while teams often start new items before finishing items already in progress. The organization wants improvement without adding headcount, and leaders are requesting a metric that identifies both delay and the point where work accumulates. Which TWO actions best address the situation? Select TWO.

Correct Answer: C. Encourage limiting work in process and finishing or unblocking existing work before starting additional items.; D. Use a cumulative flow view to identify where work is accumulating and discuss the queue with the relevant roles.
Explanation:

A cumulative flow view can reveal growing queues and bottlenecks across workflow states, making the analysis wait visible for investigation. Reducing work in process and emphasizing finishing work helps improve flow by limiting context switching and preventing further queue growth. Starting more items or optimizing individual utilization can increase congestion without improving end-to-end delivery. Removing an analysis step without understanding its purpose could compromise necessary quality or decisions rather than address the underlying delay.

Question 9

New Single answer

Topic: Executing the PI

Skill tested: Using the IP iteration for innovation, planning, learning, and preparation rather than routine scope overflow.

As an ART approaches its final iteration, a senior stakeholder proposes using the Innovation and Planning (IP) iteration as extra delivery capacity because several features are behind schedule. The ART also needs time for Inspect and Adapt, the next PI's planning preparation, and team-level learning. No committed delivery deadline requires the unfinished work to be completed during the IP iteration. What should the RTE recommend?

Correct Answer: B. Reserve the IP iteration for its intended innovation, learning, planning, and PI event purposes, and address unfinished feature scope through appropriate planning and stakeholder trade-offs.
Explanation:

The IP iteration provides capacity for innovation and exploration, continuing education, planning and preparation, and the Inspect and Adapt event. Treating it as a buffer for routine scope undermines these purposes and risks the next PI's readiness. The scenario has no mandatory deadline that justifies consuming the iteration for feature work. Canceling it or dividing teams into learning and delivery groups also disrupts shared ART activities and does not resolve the underlying planning trade-off.

Question 10

New Multiple answers

Topic: Executing the PI

Skill tested: Facilitating Inspect and Adapt to identify systemic causes and create measurable improvement actions.

At the end of a PI, the ART delivered most planned objectives, but the same cross-team integration delay appeared in multiple iterations. Teams have collected iteration and feature-flow data, and stakeholders have expressed different views about whether the delay is caused by late integration, unclear ownership, or insufficient capacity. The RTE is preparing the Inspect and Adapt event. Which TWO approaches best support meaningful improvement? Select TWO.

Correct Answer: B. Use objective delivery and flow information to establish a shared understanding of actual outcomes before selecting improvement actions.; D. Facilitate problem-solving that examines the recurring systemic issue and produces owned, actionable improvement items.
Explanation:

Inspect and Adapt combines reflection on actual results with structured problem-solving to improve the ART's systems and practices. Shared data helps prevent the discussion from relying solely on opinions, and owned improvement actions make follow-through possible. A preselected executive solution skips learning from evidence. Individual ranking is inconsistent with improving the system and can discourage transparency, while unowned notes are unlikely to change a recurring cross-team problem.

Question 11

New Single answer

Topic: Serving the ART

Skill tested: Clarifying ART role responsibilities so prioritization, value, and facilitation remain with accountable stakeholders.

During PI execution, a Business Owner asks the RTE to decide whether a lower-priority feature should be dropped to protect a regulatory feature. Product Management owns feature prioritization, teams own their iteration plans, and the Business Owner is available to explain the business impact. The ART needs a decision soon to reduce disruption. What should the RTE do?

Correct Answer: D. Facilitate a timely discussion among Product Management, the Business Owner, and affected teams so accountable stakeholders can make the trade-off and teams can adapt their plans.
Explanation:

The RTE serves the ART by enabling coordination and effective decision-making, not by taking over Product Management's prioritization or team planning responsibilities. Bringing the Business Owner's impact information together with Product Management and affected teams supports an informed, timely trade-off and allows plans to be adjusted coherently. The RTE should not decide unilaterally, leave teams to make conflicting independent choices, or defer a decision when the delay itself could disrupt execution.

Question 12

New Single answer

Topic: Serving the ART

Skill tested: Supporting Release on Demand by separating deployment readiness from business release decisions.

An ART has implemented a capability behind a feature toggle and has verified that the integrated solution meets its acceptance criteria. Operations confirms the deployment pipeline can place the capability into production, but the Business Owner has not approved making it available to customers because market timing is still under review. A delivery manager argues that completing development means the RTE should schedule an immediate customer release. What is the best response?

Correct Answer: A. Treat deployment and customer availability as separate decisions; support readiness and coordination while allowing the appropriate business stakeholders to decide when to release.
Explanation:

Release on Demand decouples the timing of releasing value to customers from development and deployment. A capability can be integrated and deployed while remaining unavailable through an appropriate control such as a feature toggle, subject to the organization's operational practices. Business stakeholders determine when customer availability best serves the market and business context. Immediate release is not required merely because development is complete, and the RTE does not acquire release authority by coordinating the ART.

Question 13

New Multiple answers

Topic: Serving the ART

Skill tested: Applying systems thinking and value stream mapping to improve end-to-end value flow across organizational boundaries.

A company's customer-facing feature takes months to reach production even though individual development teams report high utilization and meet local estimates. A value stream review shows repeated handoffs among business analysis, architecture, development, security review, and release approval. Leaders propose adding developers to the busiest team, but the delay appears distributed across the whole path. The RTE is asked to help the ART and stakeholders find a sustainable improvement. Which TWO actions are most appropriate? Select TWO.

Correct Answer: A. Map the current end-to-end value stream with the people involved, including queues, handoffs, and elapsed time, to locate systemic constraints.; E. Use the value stream view to identify improvement opportunities across organizational boundaries and coordinate experiments with the responsible stakeholders.
Explanation:

Systems thinking focuses on the behavior of the whole value-delivery system, not isolated team utilization. Mapping the end-to-end value stream makes handoffs, queues, and elapsed time visible so stakeholders can identify where improvement will have the greatest effect. The RTE can help coordinate cross-boundary experiments and follow their impact. Adding capacity to one team may simply increase downstream queues, while removing a control without evidence or relying on local velocity targets does not diagnose end-to-end delay.