Question 1
Topic: 1.0 Introduction
Skill tested: Assess deployment-plan sequencing and communication of implementation dependencies.
A financial services company is moving from a pilot Splunk Enterprise deployment to a production platform. The pilot has confirmed that a subset of application logs can be ingested, but the organization has not yet validated peak volume, retention, search concurrency, or recovery objectives. Several application teams expect a production cutover next month. The architecture team must present a deployment plan that establishes realistic milestones and prevents infrastructure decisions from being treated as final before requirements are known. Which approach is most appropriate?
A deployment plan should make requirements discovery, architecture, validation, implementation, and operational readiness explicit, with dependencies and acceptance criteria visible to stakeholders. The pilot is useful evidence, but it does not establish production peak load, retention, concurrency, or recovery needs. Freezing the pilot design or buying for an unvalidated maximum risks avoidable redesign and cost. Broadly deploying forwarders before defining data, index, and access requirements can create uncontrolled ingestion and complicate the later architecture.