Free CIPS Advanced Negotiation L5M15 Exam Questions

Last updated: · 14 practice questions with answers and explanations

Page: 1 / 9 Total 88 questions

Want more questions? Get Premium Access.

Question 1

New Single answer

Topic: Examine the key stages of the negotiation process

Skill tested: Selects preparation actions that establish objectives, limits and negotiation authority.

A procurement manager is preparing to renew a critical logistics contract. Operations wants improved service levels, Finance has set a firm affordability ceiling, and the supplier has signalled that capacity is constrained. The manager has historical cost data and service-performance evidence, but internal stakeholders disagree about which service improvements are essential. The negotiation meeting is scheduled in ten days, and the manager cannot commit the organisation beyond delegated authority. What should the manager do FIRST to prepare effectively?

Correct Answer: C. Agree internal priorities, distinguish essential outcomes from tradeable issues, set a walk-away position, and confirm approval limits.
Explanation:

Effective preparation begins by aligning the buying team on objectives, priorities, acceptable limits and authority. This gives the negotiator a coherent mandate and supports disciplined decisions when trade-offs arise. The supplier's proposal may inform the discussion, but using it to settle internal disagreement risks allowing the supplier to frame the negotiation. Revealing the affordability ceiling weakens the buyer's position unnecessarily. A concession sequence is premature until the team has established which issues are essential and which can be exchanged.

Question 2

New Single answer

Topic: Examine the key stages of the negotiation process

Skill tested: Uses opening offers and supporting evidence to establish a credible negotiation range.

A buyer is negotiating a three-year facilities-management agreement. The supplier's indicative price is 12% above the buyer's should-cost estimate, while recent market evidence shows that comparable contracts have varied according to site complexity. The buyer has verified the cost drivers but does not want to damage the relationship with an unrealistic opening position. The supplier has asked the buyer to state its proposal first. Which opening approach is MOST appropriate?

Correct Answer: A. Present a defensible, ambitious proposal with its assumptions and evidence, while inviting discussion of the associated service scope.
Explanation:

A credible, ambitious opening can anchor the bargaining range while maintaining legitimacy when supported by relevant evidence and clear assumptions. Linking price to scope also allows the parties to explore value rather than treating a number as detached from delivery requirements. The lowest observed market price may reflect different complexity and is not automatically comparable. Refusing to make a proposal forfeits an opportunity to influence the range. An unsupported take-it-or-leave-it target is likely to reduce constructive discussion and does not explain the basis of the offer.

Question 3

New Multiple answers

Topic: Examine the key stages of the negotiation process

Skill tested: Plans reciprocal concessions and protects the value of exchanged terms.

A manufacturer is negotiating a supply agreement with a component supplier. The buyer can offer a longer contract term and a more predictable forecast, but only if the supplier improves unit pricing and guarantees a recovery plan for disruptions. The buyer must avoid granting benefits without receiving value, and its internal approval permits only a limited number of changes to the proposed commercial terms. Which TWO actions best support a disciplined concession strategy? Select TWO.

Correct Answer: B. Prioritise concessions by value and importance, and retain lower-cost issues that can be exchanged for higher-priority gains.; E. Trade each proposed buyer concession for a clearly identified supplier commitment, and record the relationship between the two.
Explanation:

Reciprocal, explicitly linked concessions prevent the buyer from giving away value without a corresponding commitment. Prioritising concessions also preserves useful bargaining currency and helps the negotiator exchange lower-priority items for outcomes that matter more, such as price and continuity. Unconditional early concessions can create expectations rather than reciprocity. A supplier's acceptance of a longer term does not itself establish entitlement to a price reduction; the exchange should be negotiated explicitly. Forecast reliability can have commercial value and should not be excluded automatically.

Question 4

New Single answer

Topic: Examine the key stages of the negotiation process

Skill tested: Recognises when bargaining has reached an impasse and selects a constructive next move.

During a negotiation for a specialist maintenance contract, the supplier rejects the buyer's requested response time, and the buyer rejects the supplier's proposed premium. Both parties repeat their positions, although they agree that a prolonged outage would be costly. The meeting has become tense, and neither side has authority to change its position without understanding the operational consequences. The buyer wants to make progress without weakening its minimum requirements. What is the MOST appropriate next move?

Correct Answer: C. Explore the assumptions and costs behind both positions, then develop and evaluate possible service-and-price packages.
Explanation:

When positional bargaining stalls, exploring underlying interests and assumptions can reveal options that meet the buyer's operational need while addressing the supplier's cost concern. Package development makes trade-offs visible without abandoning the buyer's minimum requirement. Simply repeating a demand is unlikely to change the other party's assessment. Moving immediately to final offers can harden positions before the parties understand the issues. Removing the response-time requirement trades away a potentially essential outcome without first determining whether a less costly service design could work.

Question 5

New Single answer

Topic: Examine the key stages of the negotiation process

Skill tested: Secures explicit agreement and verifies implementation details before closing negotiations.

A buyer and supplier have reached verbal agreement on price, service levels, transition support and a revised payment schedule for an outsourced service. The supplier's account director says the terms are settled and suggests ending the meeting. The buyer's legal adviser is not present, and the organisation requires agreed changes to be documented and approved before commitment. What should the buyer do before treating the negotiation as closed?

Correct Answer: C. Confirm each agreed term, outstanding approval, responsible owner and implementation date, then document the agreement through the organisation's approval process.
Explanation:

Closure requires more than agreement on headline price. The parties should verify the full scope of agreed terms, identify remaining conditions and approvals, assign implementation responsibilities, and capture the result in the authorised documentation process. This reduces the risk of differing interpretations and ensures the negotiator does not exceed delegated authority. Treating the verbal exchange as sufficient conflicts with the stated approval requirement. Reopening settled price without a reason can undermine trust, while leaving material service terms unresolved invites disputes and delivery problems.

Question 6

New Single answer

Topic: Examine the key stages of the negotiation process

Skill tested: Uses a walk-away position to evaluate whether a negotiated outcome is acceptable.

A buyer is negotiating with the only currently qualified provider of a regulated testing service. Switching providers would require time and approval, but the buyer has identified a compliant alternative that could be qualified within several months. The supplier's latest proposal meets the buyer's minimum service requirement but exceeds the approved cost ceiling. The supplier says the offer expires today. The buyer has no authority to exceed the ceiling. What is the MOST appropriate response?

Correct Answer: B. Explain that the proposal is outside authority, request a short extension or a revised package, and pursue the qualification of the alternative.
Explanation:

The buyer must respect its authority limit and use its credible alternatives to avoid accepting an unauthorised outcome under artificial time pressure. Requesting an extension or a revised package preserves the possibility of agreement, while advancing qualification of the compliant alternative strengthens the buyer's future position. Signing first and seeking approval later bypasses governance. An unsupported threat of immediate termination is not credible given the switching lead time. Deferring the price until invoicing does not resolve the unaffordable commitment and creates avoidable dispute risk.

Question 7

New Multiple answers

Topic: Influence of relationships and ethics on the process

Skill tested: Protects confidentiality and fairness while managing supplier-provided information.

A supplier representative gives a procurement manager a draft pricing schedule that appears to belong to a competitor and says it was obtained by a former employee. The manager is running a competitive sourcing process in which all bidders must receive equivalent information. The schedule could help the organisation challenge the incumbent's pricing, but its origin and permission for use are unclear. Which TWO actions are MOST appropriate? Select TWO.

Correct Answer: A. Assess whether the information may be handled lawfully and ethically, and continue the competition using properly obtained, fairly shared information.; B. Secure the material, avoid using or circulating it, and seek guidance from the organisation's legal or ethics function.
Explanation:

The manager should not exploit or distribute potentially confidential competitor information of uncertain origin. Securing it and escalating for appropriate legal or ethics guidance protects the organisation while the permissibility of any further action is assessed. A fair competition should rely on information properly obtained and shared in accordance with the process rules. Using the schedule privately still exploits potentially improper information. Asking for the same details orally does not cure the concern, and distributing the document to all bidders does not make its acquisition or use legitimate.

Question 8

New Single answer

Topic: Influence of relationships and ethics on the process

Skill tested: Responds ethically to conflicts of interest and protects procurement decision integrity.

A procurement lead is evaluating bids for a long-term packaging contract. One shortlisted supplier is owned by a close family member of the lead, although the lead believes the supplier offers the best technical solution. The procurement timetable is tight, and replacing the lead would require another evaluator to review the submissions. The organisation's policy requires disclosure of actual or perceived conflicts and independent management of the process. What should the lead do?

Correct Answer: A. Disclose the relationship promptly and follow the prescribed conflict-management process, including recusal if required.
Explanation:

Prompt disclosure allows the organisation to assess the conflict and apply its established safeguards, such as independent evaluation or recusal. This protects both the integrity and perceived fairness of the award decision, even if the lead believes they can remain impartial. Delayed disclosure prevents proper governance during the evaluation. Keeping the relationship private does not satisfy the policy and exposes the process to challenge. Asking the supplier to withdraw informally avoids rather than manages the conflict and may itself compromise the process.

Question 9

New Single answer

Topic: Influence of relationships and ethics on the process

Skill tested: Balances relationship value against short-term savings and supplier continuity risks.

A long-standing supplier has consistently met quality and delivery requirements and has collaborated on several process improvements. A new bidder offers a lower price but has limited experience with the buyer's specialised production environment. The business can tolerate a short transition, but a prolonged disruption would be costly. The incumbent is willing to discuss cost reductions if the buyer shares a credible volume outlook and reviews avoidable specification complexity. What is the BEST procurement approach?

Correct Answer: C. Compare total value and transition risk, test the new bidder's capability, and negotiate evidence-based improvements with the incumbent.
Explanation:

A sound decision considers total value, delivery continuity, capability and transition exposure rather than treating either the lowest price or the existing relationship as decisive. Testing the challenger's ability to perform reduces uncertainty, while sharing credible demand information and reviewing specifications can support a constructive, evidence-based discussion with the incumbent. Immediate award on price ignores qualification and disruption risks. Automatic retention may overlook competitive opportunities. Disclosing confidential bid information improperly compromises the competition and is not necessary to negotiate effectively.

Question 10

New Multiple answers

Topic: Influence of relationships and ethics on the process

Skill tested: Uses trust-building behaviours without compromising fairness or commercial accountability.

A procurement team is negotiating with a strategic supplier after a disruption exposed weaknesses in both parties' planning. The supplier has proposed a joint improvement programme and wants earlier demand visibility. The buyer wants to rebuild trust, maintain a competitive relationship and avoid making promises that operations cannot deliver. Which TWO behaviours best support a durable and ethical relationship? Select TWO.

Correct Answer: A. Agree measurable joint actions, owners and review points, and report progress candidly when assumptions change.; B. Share relevant, accurate planning assumptions through agreed channels while clearly distinguishing forecasts from firm commitments.
Explanation:

Trust grows when information is accurate and its status is clear: a forecast should not be represented as a binding order. Joint actions with owners, measures and review points make collaboration accountable, while candid updates enable both parties to respond to change. Promising unapproved volumes creates an unauthorised commitment and damages credibility if demand does not materialise. Concealing relevant constraints undermines informed problem-solving. Benchmarking can support accountability and improvement; it need not imply a lack of trust when applied transparently and fairly.

Question 11

New Single answer

Topic: Methods and behavioural factors which can influence others

Skill tested: Uses evidence, framing and calibrated questions to persuade a supplier on value.

A supplier is resisting a proposed packaging redesign, arguing that the change will add cost. The buyer has evidence that the redesign could reduce transit damage and disposal costs, but the benefits depend on handling practices at both organisations. The supplier's commercial lead is focused on unit price and is sceptical of projected savings. The buyer wants to influence the supplier without overstating uncertain benefits or relying on authority. Which approach is MOST likely to be effective?

Correct Answer: D. Ask the supplier to explain its cost concerns, then propose a bounded pilot with shared measures for damage, cost and handling.
Explanation:

Calibrated questions uncover the supplier's underlying concern, while a bounded pilot turns uncertain claims into evidence that both parties can evaluate. Shared measures also connect the proposal to the supplier's cost focus without promising benefits that are not established. A threat may provoke resistance and does not address the economics. Presenting uncertain savings as guaranteed is misleading and unfairly transfers implementation risk. Delaying the conversation loses an opportunity to test value collaboratively and does not resolve the current concern.

Question 12

New Single answer

Topic: Methods and behavioural factors which can influence others

Skill tested: Adapts influence methods to the counterpart's decision criteria and evidence needs.

A supplier's technical director supports a proposed resilience investment, but the supplier's finance director has rejected it because the projected return is uncertain. The buyer has incident data showing the likely operational impact of failures and can provide a forecast of demand, but cannot guarantee volumes or reimburse all investment. The buyer wants the supplier to reconsider a staged resilience plan. Which influence strategy is MOST appropriate?

Correct Answer: A. Frame the discussion around the finance director's risk and return criteria, use the incident evidence, and explore staged investment with review gates.
Explanation:

Influence is more effective when it addresses the decision-maker's actual concerns. Incident data can clarify the cost of inaction, while staged investment and review gates limit exposure and allow the parties to assess evidence before proceeding further. Bypassing the finance decision-maker ignores the supplier's governance. An unauthorised volume guarantee creates material risk for the buyer. A moral appeal alone is unlikely to resolve a financial assessment and may be perceived as pressure rather than a reasoned business case.

Question 13

New Multiple answers

Topic: Methods and behavioural factors which can influence others

Skill tested: Applies active listening and reframing to uncover interests behind a supplier's position.

In a negotiation over a service-level agreement, a supplier repeatedly rejects the buyer's proposed penalties, calling them commercially unacceptable. The buyer's real concern is timely recovery after major incidents, not punishment for its own sake. The supplier has not yet explained which elements of the proposed mechanism create concern. The buyer needs a robust, measurable remedy but is open to alternatives that achieve recovery. Which TWO actions are MOST appropriate? Select TWO.

Correct Answer: D. Ask open questions about the supplier's concerns and listen for the operational or financial interests behind its position.; E. Reframe the discussion around the shared objective of rapid recovery, then invite proposals for measurable remedies that meet it.
Explanation:

Open questions and active listening can reveal whether the concern is about proportionality, measurement, liability or another underlying issue. Reframing the discussion around rapid recovery helps separate the buyer's operational interest from one particular penalty mechanism and invites alternatives that can be assessed against the required outcome. Repeating the clause keeps the parties focused on positions. Removing all remedies gives away protection without reciprocity. Assuming bad faith and escalating immediately can damage the relationship before the supplier's reasons are understood.

Question 14

New Single answer

Topic: Methods and behavioural factors which can influence others

Skill tested: Selects a principled response to time pressure and anchoring tactics.

A supplier presents a proposal near the end of a negotiation and says it is valid only if accepted before the meeting closes. The price is substantially higher than the buyer's evidence-based range, and the supplier has not explained the assumptions behind it. The buyer's team is concerned that delaying could jeopardise the sourcing timetable, but the offer also includes several changes to scope and risk allocation. The buyer cannot approve material changes without review. What is the MOST appropriate response?

Correct Answer: A. Acknowledge the proposal, request its assumptions and a reasonable review period, then assess the complete package against evidence and authority.
Explanation:

A high anchor and deadline should prompt disciplined evaluation, not an automatic acceptance or an emotional counter. Reviewing assumptions and the complete package is essential because scope and risk changes can alter the apparent price. The buyer should also respect its approval limits and seek adequate time for review. Accepting before examining material terms creates uncontrolled exposure. An arbitrary counter does not rely on evidence. Accusing the supplier of dishonesty without basis or ending the negotiation immediately discards the opportunity to clarify and assess the offer.