New Single answer

Topic: Logistics concepts and link to supply chain efficiency

Skill tested: Evaluates service, cost and volume measures when assessing logistics performance trade-offs.

A food wholesaler ships 18,000 cases monthly to independent retailers. Its logistics dashboard reports a declining cost per case, but customer complaints and emergency redeliveries have increased. The decline followed a decision to consolidate deliveries into fewer, larger weekly drops. Retailers have limited storage, and some products have short shelf lives. Senior management wants to determine whether the apparent unit-cost improvement represents better supply chain efficiency rather than a transfer of cost or risk to customers. Which measurement approach would provide the most useful assessment?

Correct Answer: B. Track cost per case alongside on-time, in-full delivery, damage and emergency-delivery costs, using the same volume and service period.
Explanation:

A balanced measure set connects cost and volume with the service outcomes affected by consolidation. Cost per case can fall while stockouts, damage, emergency deliveries or customer handling costs rise; on-time, in-full performance and exception costs reveal that trade-off. Measuring transport spend alone (A) excludes consequential costs and service failures. Truck utilization (C) is useful but cannot show whether customers receive the required service. A raw year-on-year comparison (D) is not like-for-like when frequency and volume have changed.

Question 2

New Multiple answers

Topic: Logistics concepts and link to supply chain efficiency

Skill tested: Assesses selection of logistics KPIs that expose service and cost consequences of delivery consolidation.

A distributor is considering changing from daily deliveries to three deliveries per week for a group of urban customers. The change is expected to improve vehicle utilization and lower driver hours. Several customers operate with little backroom space, and the distributor has historically incurred costs for failed deliveries and short-notice replenishment. The operations director asks for a short evaluation dashboard that can show whether the change improves total logistics efficiency without concealing service deterioration or shifting work to customers. Which TWO measures should be included? Select TWO.

Correct Answer: A. Total logistics cost per successfully delivered unit, including failed-delivery and urgent-replenishment costs.; C. On-time, in-full delivery performance for the affected customers.
Explanation:

Total cost per successfully delivered unit captures the intended transport savings while also including costs caused by failure and urgent replenishment. On-time, in-full performance checks whether customers continue to receive the required service under the lower-frequency plan. Fill rate alone (B) rewards fuller vehicles without accounting for outcomes. Order count (D) does not measure fulfillment or logistics cost. Driver hours (E) may be informative, but excluding waiting and redelivery can conceal operational consequences and it does not directly measure customer service.

Question 3

New Single answer

Topic: Logistics concepts and link to supply chain efficiency

Skill tested: Evaluates the use of total logistics cost and service metrics to identify cost shifting.

A manufacturer introduces a policy requiring larger minimum order quantities to reduce picking and dispatch activity. Warehouse cost per unit falls, but distributors report higher inventory, more obsolescence and greater working-capital pressure. The sales team argues that the manufacturer's warehouse efficiency has improved, while the supply chain director questions whether the change created a genuine system-level benefit. Which analysis should the director request first?

Correct Answer: C. Assess total relevant costs and service across the supplier-distributor relationship, including inventory carrying, obsolescence, handling and order fulfillment.
Explanation:

A system-level assessment identifies whether savings in picking and dispatch are outweighed by additional inventory, obsolescence and handling costs elsewhere in the chain, while also checking service effects. Warehouse productivity alone (A) is a local measure and cannot establish total benefit. Supplier transport cost (B) likewise excludes the reported cost transfer. Immediate reversal (D) is premature: the policy may still be beneficial for some products or customers, but that requires evidence across relevant costs and service.

Question 4

New Single answer

Topic: Logistics concepts and link to supply chain efficiency

Skill tested: Assesses how delivery frequency and shipment size affect inventory, transport and service trade-offs.

A regional spare-parts supplier serves maintenance contractors across a wide territory. Its current policy dispatches every order the same day, including low-value items in partially filled vehicles. Transport cost is high, but some contractors need critical parts quickly to avoid equipment downtime. The supplier can identify critical items and customer locations, but it cannot afford to provide same-day service for every order. Which policy best balances logistics efficiency and customer need?

Correct Answer: B. Offer differentiated service: rapid delivery for agreed critical parts or urgent cases, with scheduled consolidated delivery for routine demand.
Explanation:

Differentiating service by criticality preserves rapid response where downtime justifies it while consolidating routine demand to improve vehicle utilization and control cost. A universal weekly service (A) disregards the operational impact of critical shortages. Continuing same-day service for every order (C) preserves an expensive policy even where urgency is low. Requiring broad customer stockholding and removing urgent capability (D) transfers inventory and risk to customers and fails to address genuinely time-critical needs.

Question 5

New Single answer

Topic: Logistics concepts and link to supply chain efficiency

Skill tested: Interprets logistics cost and service performance using comparable, appropriately normalized measures.

A retailer's logistics team reports that monthly distribution cost has risen by 8%. During the same period, shipped volume rose by 15%, the product mix shifted toward bulky goods, and the company added a new remote region. The board is considering an immediate network cost-cutting program. Before recommending action, the logistics manager needs to determine whether underlying performance has deteriorated or whether the increase reflects changed demand and service scope. What is the best next step?

Correct Answer: C. Normalize performance using relevant volume and mix measures, distinguish the new region's cost, and review service results over comparable periods.
Explanation:

The manager needs a like-for-like view: normalize cost against meaningful activity such as units, weight, cube or stops as appropriate, account for product mix and separate the new service scope. Service results should be reviewed alongside cost so lower cost is not pursued at unacceptable service levels. Total spend alone (A) cannot distinguish efficiency from growth. Cost per order (B) is distorted by changing order size and cube. Excluding the new region (D) may help a comparable analysis, but removing it from reporting hides actual performance rather than explaining it.

Question 6

New Single answer

Topic: Plans and designs for logistics improvement

Skill tested: Selects a distribution network design that balances delivery response, facility cost and demand geography.

A company supplying temperature-controlled products has one central distribution centre and serves customers across a large country. Demand is concentrated in two metropolitan regions, where customers require next-day delivery; remote demand is sporadic and can tolerate a longer lead time. The central facility is near capacity. A proposal would establish a small warehouse in every major city, but fixed facility costs and temperature-control compliance are significant. Which network approach is most appropriate to evaluate?

Correct Answer: C. Use a regional facility or cross-dock for dense metropolitan demand while serving sparse areas from the central facility, subject to cost and service analysis.
Explanation:

A selective regional design matches facility investment to concentrated demand and required response, while retaining central coverage for sparse areas that can accept longer lead times. Cross-docking may support flow without duplicating all inventory, depending on product handling and demand patterns. Warehousing in every city (A) adds substantial fixed and compliance costs. Central-only premium express (B) may be costly and does not address capacity. Accumulating remote orders into full truckloads (D) conflicts with sporadic demand and may create excessive delays.

Question 7

New Multiple answers

Topic: Plans and designs for logistics improvement

Skill tested: Compares transport modes against product value, urgency, shipment size and service requirements.

An importer moves components from an overseas supplier to a factory with limited line-side inventory. A recent demand forecast indicates regular, predictable replenishment, but occasional high-priority orders are needed to recover from supplier disruption. The components are valuable but not perishable. Air freight offers speed but is expensive; ocean freight is economical but has a longer and less flexible replenishment cycle. The company wants to lower average logistics cost without increasing routine stockouts. Which TWO planning actions are most appropriate? Select TWO.

Correct Answer: A. Use ocean freight for forecastable replenishment, with inventory and order timing planned around its longer lead time.; C. Reserve air freight for exceptional, justified recovery needs rather than making it the routine mode.
Explanation:

Predictable demand can be planned through the lower-cost ocean mode if lead time and inventory coverage are incorporated into replenishment decisions. Air is then a targeted contingency for exceptional recovery needs, avoiding the cost of using it routinely. All-air service (B) may reduce pipeline time but imposes high recurring transport cost. Freight rate alone (D) ignores stockout and inventory consequences. Unconditionally waiting for a full container (E) risks disrupting production and disregards the established replenishment plan.

Question 8

New Single answer

Topic: Plans and designs for logistics improvement

Skill tested: Evaluates route and mode choices against delivery windows, shipment density and total transport cost.

A building-products supplier delivers heavy, low-value materials to construction sites. Customers book narrow delivery windows, and urban congestion makes missed appointments costly. Rail is cheaper per tonne for long-distance movement but requires extra handling and a terminal transfer; road vehicles can reach sites directly. A planner proposes using rail for every shipment because its line-haul rate is lower. What is the best way to decide the transport plan?

Correct Answer: B. Compare end-to-end cost and delivery reliability by lane, including transfers, site access, appointment performance and any required road legs.
Explanation:

The relevant comparison is the complete logistics solution, not a line-haul rate in isolation. Rail may be attractive on suitable lanes, but transfer costs, terminal access, additional handling, final-mile road delivery and the probability of meeting site appointments all affect total cost and service. Selecting rail solely on line-haul price (A) omits these factors. Road is not always cheaper (C), and scheduled speed alone (D) does not ensure reliable delivery within a customer window.

Question 9

New Multiple answers

Topic: Plans and designs for logistics improvement

Skill tested: Assesses facility-location proposals using demand patterns, service expectations and total network cost.

A health-products distributor is reviewing two possible locations for a new regional facility. One is close to a major customer cluster but has higher rent and labor costs; the other is cheaper but increases average outbound distance. Demand is uneven, product handling requires controlled storage, and the existing central site can continue serving low-volume territories. The proposal must be justified on service and economic grounds, not solely on property cost. Which TWO analyses should the team prioritize? Select TWO.

Correct Answer: A. Model demand by customer location and delivery frequency to estimate achievable response and transport requirements from each candidate.; C. Compare total relevant network costs, including facility operation, inventory positioning, transport and controlled-storage requirements.
Explanation:

Demand geography and delivery frequency determine whether a location can improve response and how much transport activity it may change. A total-cost comparison must include facility operation, inventory duplication or repositioning, transport and the required controlled storage. Lowest rent (B) can be outweighed by distance or operating costs. Locating solely near the largest customer (D) may produce a poor network for the wider customer base. First-year property cost alone (E) omits the principal operating and service consequences.

Question 10

New Single answer

Topic: Plans and designs for logistics improvement

Skill tested: Chooses a route plan that meets delivery constraints while managing mileage and operational risk.

A carrier must deliver to several customers in a rural area from a regional depot. Some roads restrict vehicle weight, two customers have fixed receiving windows, and the remaining deliveries are flexible. The dispatcher currently sends vehicles along the shortest-distance route generated by mapping software. Drivers report detours and missed windows. What is the most appropriate improvement to the routing process?

Correct Answer: B. Optimize routes using actual vehicle restrictions, customer time windows, stop service times and realistic travel times.
Explanation:

A useful route plan must be feasible, not merely short. Including weight restrictions, receiving windows, stop service times and realistic travel conditions addresses the causes of detours and missed appointments. Ignoring legal or operational restrictions (A) creates risk and may still fail to meet service requirements. Alphabetical sequencing (C) has no necessary relationship to efficient routing. A uniform mileage allowance (D) does not solve route feasibility or prioritize time-window commitments.

Question 11

New Single answer

Topic: Plans and designs for logistics improvement

Skill tested: Assesses consolidation and cross-docking suitability against shipment compatibility and delivery lead times.

A retailer receives frequent small consignments from suppliers and is considering a cross-dock to reduce storage and improve store replenishment. Products have stable demand, but some suppliers deliver unpredictably and several product lines require different handling conditions. Stores need deliveries on fixed days. The proposed design would send all inbound goods directly to outbound vehicles without intermediate storage. Which recommendation is best?

Correct Answer: C. Assess product and supplier suitability, synchronize reliable inbound flows with outbound schedules, and retain controlled exceptions where needed.
Explanation:

Cross-docking can reduce storage and handling when inbound arrivals, product characteristics and outbound requirements can be coordinated. Unpredictable suppliers, incompatible handling needs or fixed store schedules may require exceptions, buffers or conventional storage for selected lines. Applying it to everything (A) ignores synchronization and handling risk. Rejecting it categorically (B) is unjustified because multiple suppliers and destinations can be coordinated. Holding all stock until requested (D) describes storage rather than the intended direct-transfer flow.

Question 12

New Single answer

Topic: Plans and designs for logistics improvement

Skill tested: Evaluates whether a logistics network redesign supports demand variability and customer service commitments.

An online retailer is planning its peak-season distribution network. Orders are geographically dispersed outside the main city, and demand forecasts have wide uncertainty. A proposal would move most inventory into a new urban facility to provide same-day delivery to metropolitan customers. The existing national facility has spare capacity and supports next-day service elsewhere. The investment has a long lease commitment, and peak demand may not recur at the forecast level. Which planning approach is most defensible before committing?

Correct Answer: B. Evaluate scenarios for demand, service value and total network cost, including the cost and risk of duplicated inventory and long-term capacity.
Explanation:

Scenario analysis tests whether the urban site creates sufficient service value under plausible demand levels to justify its fixed commitment, operating cost and inventory duplication, while accounting for effects on other regions. Same-day service is not automatically worth its cost (A). A blanket rejection of regional facilities (C) ignores the specific metropolitan demand profile. Moving all inventory to the city and expediting distant orders (D) would undermine the existing national service and may raise transport cost and risk.

Question 13

New Single answer

Topic: Processes and systems for controlling logistics

Skill tested: Selects inventory controls that balance availability, replenishment lead time and working capital.

A wholesaler has frequent stockouts of fast-moving items and excess inventory of slow-moving lines. Its current replenishment process applies the same review interval and target stock level to every SKU. Supplier lead times and demand variability differ substantially, and the company has reliable historical transaction data. The logistics manager wants to improve availability without increasing total inventory investment. Which control is the best starting point?

Correct Answer: B. Segment items by demand and business importance, then set replenishment parameters using demand variability, lead time and service requirements.
Explanation:

Differentiated inventory control aligns review and replenishment settings with each item's demand pattern, lead time, variability and service importance. This can improve availability for critical fast movers while avoiding blanket investment in slow lines. Raising safety stock universally (A) may reduce some shortages but increases total inventory without targeting the causes. Reordering at zero (C) ignores replenishment lead time. Fixed monthly quantities (D) disregard actual consumption and differing supplier conditions.

Question 14

New Multiple answers

Topic: Processes and systems for controlling logistics

Skill tested: Identifies transport execution controls that improve shipment visibility and exception resolution.

A logistics coordinator manages deliveries through several contracted carriers. The company frequently learns about missed collection slots and delivery delays only after customers complain. Shipment information is entered manually into a spreadsheet, and carrier performance is reviewed quarterly. Management wants practical controls that allow staff to intervene earlier and create a dependable performance record. Which TWO actions are most appropriate? Select TWO.

Correct Answer: A. Define shipment milestones and require timely status updates, with exception alerts for missed collection or delivery events.; D. Maintain a consistent shipment record linking order, carrier, milestones, proof of delivery and exception resolution.
Explanation:

Milestone visibility and exception alerts give coordinators time to contact carriers, revise plans or inform customers before a failure becomes a complaint. A consistent record linking the order to carrier events, delivery evidence and resolution supports operational control and meaningful performance review. Quarterly-only investigation (B) is too late for intervention. Recording only final delivery (C) conceals where a delay arose. Inconsistent event labels (E) undermine comparison unless they are mapped to a common set of milestones.

Question 15

New Single answer

Topic: Processes and systems for controlling logistics

Skill tested: Applies receiving and inventory record controls to resolve discrepancies and protect stock accuracy.

A distribution centre's system frequently shows more stock than staff can locate in pick faces. Investigations find that some receipts are posted before quantities and condition are checked, and damaged goods are occasionally put away as saleable stock. The operation cannot pause receiving, but it can revise its process and system permissions. Which control change would most directly address the root cause?

Correct Answer: A. Require receipt verification against the delivery and purchase records, record damage or quantity variances, and restrict available stock status until disposition.
Explanation:

Verification at receipt, documented variance handling and a controlled stock status prevent unverified or damaged goods from being treated as available inventory. This addresses both inaccurate on-hand records and inappropriate availability. Inflating balances (B) worsens the discrepancy. Unexplained adjustments (C) weaken traceability and do not establish the correct quantity or condition. Posting expected stock as available before receipt (D) creates false availability and can generate avoidable picking failures.