Question 1

As a TAE you are evaluating a functional test automation tool that will be for several projects within your organization. The projects require that tool to work effectively and efficiently with SUT's in distributed environments. The test automated tool also needs to interface with other existing test tools (test management tool and defect tracking tool.) The existing test tools subject to planned updates and their interface to the test automated tool may not work property after these updates.

Which of the following are the two LEAST important concerns related to the evaluation of the test automation in this scenario?

Is the test automation tool able to launch processors and execute test cases on multiple machines in different environments?

Does the test automation tool support a licensing scheme that allows accessing different sets?

Does the test automation tool have a large feature set, but only part of the features will be sets?

Do the release notes for the planned updates on existing specify the impacts on their interfaces to other tools?

Does the test automation tool need to install specific libraries that could impact the SUT?

Correct Answer: C. B and E

Question 2

Consider a TAS that exclusively uses the APIs of a SUT. To make this work, significant changes have been required to the SUT by adding a set of dedicated test interfaces to the APIs. All the automated tests will use these test interfaces when interacting with the SUT. Assume that you are currently verifying the correctness of the automated test environment and test tool setup.

Which of the following would you expect to be the MOST specific risk associated with this scenario?

Correct Answer: D. False alarms, that are unlikely to occur in the real world, will be observed during testing

Question 3

Which of the following statements BEST describe aspects of the SUT to consider when designing a TAA?

Correct Answer: A. All the interaction between SUT and TAS should be logged with the highest level of detail

Question 4

Which of the following metrics could suggest, under certain condition that an automated regression test suite has NOT been updated for new functionalities added to the SUT?

Correct Answer: B. The SUT code coverage provided by the execution of the regression test suite.

Question 5

You are evaluating several test modelling tools and are wanting to automatically generate test cases within the tool where many different combinations of input data are created.

You are then wanting to export the test cases into a csv file which can then be read by a functional test execution tool using a data-driven or keyword-driven scripting method.

You have investigated several tools and there is only one tool that provides all the necessary features defined by your team with the exception of the export facility. It does not provide an export into either .xls or .csv formats.

What would be the BEST next step regarding the selection of this tool?

Correct Answer: C. Ask the vendor and use forums to see if a solution is available or going to be available in the future.

Question 6

You are the TAE for an Agile project which has six sprints for the current release. Sprint five is underway and the automated regression suite is due to start later today.

You have re-examined the results from the automated regression runs for the past four sprints. You notice that two test cases both reported a pass for sprints 1 and 4 but a fail for sprints 2 and 3. The failures have gone undetected and are therefore unexplained. Both test cases are closely coupled with other tests in the suite.

What course of action SHOULD you take?

Correct Answer: C. Quarantine the test cases, run the regression suite without them, and perform root cause analysis on the test cases in parallel.

Question 7

What is NOT a factor in considering when you are asked to ensure an effective transition from manual to automated tests?

Correct Answer: C. The look and feel of the SUT

Question 8

You are currently designing the TAA of a TAS. You have been asked to adopt an approach for automatically generating and executing test cases from a model that defines the SUT. The SUT is a state-based and event-driven that is described by a finite-state machine and exposes its functionality via an API. The behavior of the SUT depends on hardware and communication links that can be unreliable.

Which of the following aspects is MOST important when designing the TAA in this scenario?

Correct Answer: C. Looking for tools that allow performing setup and teardown of the test suites and the SUT.

Question 9

You have been asked to implement test automation for a project that is not meeting its deadlines. After further analysis you discover that the manual testers are not able to keep up with the new feature testing because the regression testing is taking 75% of their time. As a result, the new features are being released with many defects and customers are complaining about the quality.

Given this information, what metric SHOULD you be tracking to show the value of test automation for this project?

Correct Answer: B. Equivalent Manual Test Effort for the automated tests.

Question 10

Which of the following CORRECTLY describes how automation SHOULD be applied to confirmation testing?

Correct Answer: C. Confirmation tests can be automated and incorporated into an automated regression suite to show whether defects that were previously fixed reoccur