Question 1
Topic: Objective 1: Understand key concepts relating to PRINCE2
Skill tested: Applies continued business justification when project forecasts change.
A public-sector agency is modernizing a grant application service. Its business case was approved on the expectation that the new service would reduce processing costs by 20%. During delivery, a regulatory change requires additional controls and revises the forecast reduction to 8%. The project remains within its approved time and cost tolerances, and the delivery team can still produce the agreed outputs. The senior user considers the reduced savings disappointing, while the executive asks the project manager to continue without revisiting the business case because no tolerance has been breached. What is the most appropriate response?
PRINCE2 requires continued business justification throughout the project, not merely at approval. A material change in forecast benefits should be reflected in the business case and considered by the appropriate governance authority, even when time and cost remain within tolerance. Staying within tolerance does not establish that the project is still worthwhile, and a reduction in benefits does not automatically require closure. Removing mandatory controls to preserve a forecast would be inappropriate; the decision should use a credible, current business case.