Question 1

New Single answer

Topic: Objective 1: Understand key concepts relating to PRINCE2

Skill tested: Applies continued business justification when project forecasts change.

A public-sector agency is modernizing a grant application service. Its business case was approved on the expectation that the new service would reduce processing costs by 20%. During delivery, a regulatory change requires additional controls and revises the forecast reduction to 8%. The project remains within its approved time and cost tolerances, and the delivery team can still produce the agreed outputs. The senior user considers the reduced savings disappointing, while the executive asks the project manager to continue without revisiting the business case because no tolerance has been breached. What is the most appropriate response?

Correct Answer: D. Update the business case forecast and have the appropriate governance authority assess whether the project remains desirable, viable, and achievable.
Explanation:

PRINCE2 requires continued business justification throughout the project, not merely at approval. A material change in forecast benefits should be reflected in the business case and considered by the appropriate governance authority, even when time and cost remain within tolerance. Staying within tolerance does not establish that the project is still worthwhile, and a reduction in benefits does not automatically require closure. Removing mandatory controls to preserve a forecast would be inappropriate; the decision should use a credible, current business case.

Question 2

New Single answer

Topic: Objective 1: Understand key concepts relating to PRINCE2

Skill tested: Distinguishes project governance accountability from day-to-day management responsibilities.

A regional insurer is delivering a customer claims portal through several agile teams. Executives want rapid feedback from users, but they also need clear accountability for project direction and for accepting the completed product. The project manager coordinates plans, dependencies, and reporting, while the teams organize their own work. A product specialist has been asked to provide detailed acceptance feedback. Which arrangement best preserves PRINCE2 accountability while supporting this delivery model?

Correct Answer: D. The project board retains overall direction and key project decisions, while the project manager manages within delegated authority and the senior user represents user interests and acceptance.
Explanation:

PRINCE2 separates direction from day-to-day management. The project board provides overall direction and makes decisions within its responsibilities; the project manager manages the project within delegated authority. The senior user represents those who use the products and is accountable for specifying user needs and confirming that products meet them, with appropriate delegation possible for detailed acceptance. Agile self-management changes how teams organize delivery, not the need for clear project-level accountability.

Question 3

New Single answer

Topic: Objective 2: Understand key concepts relating to projects and PRINCE2 Agile

Skill tested: Uses PRINCE2 Agile flexibility to protect quality while adapting scope and delivery detail.

A logistics company is replacing an internal dispatch application. A fixed regulatory launch date cannot move, the budget is capped, and agreed quality and safety controls are mandatory. Initial user research suggests that several requested reports may be less valuable than expected. The sponsor wants the team to preserve all requested functionality by reducing testing and documentation effort. The organization is open to refining lower-priority scope as it learns, but it cannot accept a noncompliant release. Which approach best fits PRINCE2 Agile?

Correct Answer: B. Fix the launch date, budget, and required quality criteria; use prioritization and controlled scope flexibility to deliver the most valuable compliant scope.
Explanation:

PRINCE2 Agile uses the PRINCE2 controls while enabling an agile approach to delivery. Fixing time and cost and allowing scope to flex through prioritization is appropriate when lower-priority requirements can change. Quality criteria, particularly mandatory regulatory and safety controls, must not be traded away to preserve feature count. Moving the fixed date or budget conflicts with the stated constraints, while freezing all requirements would discard the intended ability to learn and reprioritize.

Question 4

New Multiple answers

Topic: Objective 2: Understand key concepts relating to projects and PRINCE2 Agile

Skill tested: Selects complementary project control and iterative delivery practices for a hybrid initiative.

A university is replacing its student enrollment service. The project board needs stage-level forecasts, exception escalation, and traceability to the business case. Users need to review working service increments frequently, and the delivery team wants to adapt detailed requirements based on feedback. Procurement has already fixed the overall contract ceiling and the date by which the service must be operational. Which TWO practices best combine PRINCE2 governance with agile delivery without undermining those controls? Select TWO answers.

Correct Answer: C. Demonstrate usable increments regularly and reprioritize lower-value requirements within the agreed time, cost, and quality constraints.; D. Use stage boundaries to review the business case, progress, and next-stage plan, escalating forecasts that exceed delegated tolerances.
Explanation:

Stage boundaries provide a governance checkpoint to assess progress, continuing justification, and authorization of the next stage; forecasts outside delegated tolerances require escalation through the defined control route. Regular demonstrations and reprioritization make use of feedback while preserving agreed project constraints. Deferring all governance removes necessary control, and neither every request nor a team preference automatically changes an authorized baseline or the project board's tolerances.

Question 5

New Single answer

Topic: Objective 3: Understand how PRINCE2 principles, themes, processes and management products are tailored and/or applied in an agile context

Skill tested: Tailors management by exception for an agile team's delegated decision-making.

A product team is delivering a customer identity service in short iterations. The project board has delegated authority to the project manager for a stage, with tolerances for time, cost, scope, and quality. The team discovers that one optional feature will not fit in the current release, but its proposed change would remain within the agreed tolerance and would not alter mandatory security criteria or the business case. Team members propose asking the board to approve every such backlog adjustment to ensure that governance remains involved. What should the project manager do?

Correct Answer: C. Use delegated authority to manage the adjustment within agreed tolerances, maintaining appropriate records and escalating if a tolerance is forecast to be exceeded.
Explanation:

Management by exception delegates decision-making within defined tolerances and focuses senior management attention on forecasts that exceed them. A change to optional scope that remains within authority and preserves mandatory quality and security criteria can be managed without referring every detail to the board. Delegation is not unlimited: a forecast tolerance breach or other matter outside authority must be escalated. Requiring board approval for each backlog adjustment would undermine effective delegation and agile flow.

Question 6

New Multiple answers

Topic: Objective 3: Understand how PRINCE2 principles, themes, processes and management products are tailored and/or applied in an agile context

Skill tested: Maintains useful project controls by tailoring plans and reports to iterative delivery.

A consulting firm has tailored PRINCE2 for a software project delivered through several short iterations. The project board needs a reliable view of stage progress and forecasts, while the team already tracks daily work and impediments on its board. The project manager is considering requiring the team to reproduce every task-board update in a detailed project schedule and daily narrative report. The contract does require visible stage commitments and prompt escalation of forecasts beyond tolerance. Which TWO actions are the best tailoring choices? Select TWO answers.

Correct Answer: A. Retain the project-level plan and stage controls needed for commitments, dependencies, and tolerance forecasts, linking them to the team's delivery information where useful.; D. Use concise highlight or exception reporting at the appropriate governance cadence, escalating material forecast deviations rather than reproducing daily task details.
Explanation:

Tailoring should preserve information needed for project direction and control while avoiding unnecessary duplication. The project-level plan and stage controls support commitments, dependencies, and forecasts; team-level information can inform them without copying every task update. Concise reporting at the agreed cadence and prompt exception escalation meet the stated governance needs. A team board alone does not necessarily show project-level accountability or authorization, and demonstrations do not replace stage-end decisions or continued business justification.

Question 7

New Multiple answers

Topic: Objective 4: Understand the agile ways of working, key terms and techniques

Skill tested: Applies Scrum roles and events to strengthen feedback and remove delivery impediments.

A financial services team is adopting Scrum to build an internal case-management feature. A department head currently assigns tasks directly to developers during each iteration and changes priorities in response to individual stakeholder requests. The team rarely demonstrates its work until the end of the quarter, and blockers are often left unresolved. The organization wants an empirical, iterative approach, but regulatory acceptance criteria must remain visible and stakeholders cannot directly rewrite the team's commitments mid-iteration. Which TWO changes most appropriately apply Scrum practices? Select TWO answers.

Correct Answer: B. Use Sprint Reviews to inspect the increment with stakeholders and adapt the Product Backlog based on feedback.; D. Have the Product Owner order the Product Backlog and clarify priorities, with changes considered through the backlog rather than direct task assignment by stakeholders.
Explanation:

The Product Owner is accountable for effective Product Backlog management, including ordering work, while the Developers organize how to accomplish the Sprint work. Stakeholders can provide feedback, but do not directly assign tasks or rewrite commitments at will. Sprint Reviews create a regular opportunity to inspect the increment and adapt the backlog. The Scrum Master serves the Scrum Team and helps address impediments; the role is not a task-assigning manager or substitute Product Owner.

Question 8

New Single answer

Topic: Objective 4: Understand the agile ways of working, key terms and techniques

Skill tested: Uses MoSCoW prioritization to manage scope against a fixed delivery constraint.

A health charity is preparing a volunteer scheduling service for a fixed seasonal launch. The team has identified 30 requirements, but its latest forecast indicates that not all can be completed without risking the date. A small set is legally required for safe operation; several features are valuable but have workable manual alternatives for the first release; others are enhancements with no launch dependency. The sponsor asks the project manager to prioritize transparently and preserve a usable release rather than lower acceptance standards. Which approach is most appropriate?

Correct Answer: D. Prioritize requirements using MoSCoW, reserving Must Have for genuine release-critical needs and considering lower-priority scope for later delivery.
Explanation:

MoSCoW helps make scope trade-offs explicit: Must Have requirements are essential for a viable release, while Should Have, Could Have, and Won't Have this time can be prioritized according to value and constraints. This supports a usable, compliant release without pretending that all scope is equally essential. Treating everything as mandatory defeats prioritization; effort-only ordering ignores value and obligation; lowering acceptance standards compromises the required quality and safety.

Question 9

New Single answer

Topic: Objective 4: Understand the agile ways of working, key terms and techniques

Skill tested: Interprets a burn-up chart to distinguish completed work from changing scope.

A project manager is reviewing progress on an analytics product with the sponsor. The team uses a burn-up chart: one line shows cumulative completed work, and another shows total agreed scope. Across three reporting periods, the completed-work line rises steadily, while the scope line rises more sharply after users request additional reports. The sponsor sees that the team has completed more work than in the previous period but claims the product is now falling behind because the gap between the lines is larger. What is the most useful interpretation and response?

Correct Answer: C. The completed work is increasing, but scope has also grown; review the scope change and forecast the remaining work against the agreed date and priorities.
Explanation:

A burn-up chart displays cumulative completed work against total scope. The rising completed-work line indicates progress, while the rising scope line indicates that the amount of work to deliver has increased. The larger gap therefore warrants assessing the scope change and updating the forecast, not assuming a productivity decline or claiming the date is assured. Scope growth is not completed work, and reducing quality checks is not a sound way to respond.

Question 10

New Single answer

Topic: Objective 5: Understand the focus areas in an agile contex

Skill tested: Uses the Agilometer to assess and manage project agility risks.

A government agency is planning a records modernization project with an agile delivery team. The project manager uses the Agilometer to assess factors affecting the suitability of agile ways of working. The review identifies strong executive support and an experienced team, but also strict fixed-scope procurement terms, limited access to end users, and low organizational tolerance for changing plans. The sponsor proposes marking the project as suitable because the team has agile experience. What should the project manager do next?

Correct Answer: C. Use the assessment to identify and discuss the risks and improvement actions, such as improving user access and agreeing practical scope flexibility, before confirming how agile will be applied.
Explanation:

The Agilometer is a diagnostic aid for considering factors that affect the use of agile and identifying where action may improve the environment. It should inform discussion and tailoring, not provide a mathematically precise success probability or a binary approval rule. Team experience is valuable but does not erase constraints such as limited user access and rigid scope terms. Those constraints should be explored and managed; they do not automatically make every agile practice impossible.

Question 11

New Single answer

Topic: Objective 5: Understand the focus areas in an agile contex

Skill tested: Improves collaboration by establishing sustained, direct access to business representatives.

A utility company is delivering a customer self-service portal. Developers receive requirements through a weekly email relay from a business analyst who has limited authority to clarify policy questions. This creates several days of waiting and frequent rework. The project has a fixed regulatory review date, and senior business representatives cannot attend every team meeting. The project manager wants to improve collaboration and shorten feedback loops without removing formal governance or assuming that all stakeholders can be continuously available. What is the best first improvement?

Correct Answer: B. Establish a named, empowered business representative or user proxy with regular availability to clarify requirements and review increments.
Explanation:

Agile ways of working benefit from timely, direct collaboration with people who can explain needs and provide feedback. A named representative with appropriate authority and regular availability reduces the relay delay while recognizing that senior stakeholders cannot attend continuously. This arrangement complements rather than replaces formal governance. Asking developers to guess or making the project manager decide business policy risks incorrect outcomes, while adding email approvals increases handoffs instead of improving feedback.

Question 12

New Single answer

Topic: Objective 5: Understand the focus areas in an agile contex

Skill tested: Uses timeboxing and prioritization to protect quality and fixed delivery dates.

A retail organization is preparing a pricing update for a fixed seasonal release. The team is using timeboxed iterations, and its current forecast shows that the latest lower-priority interface enhancements may not fit. Core pricing calculations and required validation remain on track, and the release date cannot move because it is tied to a published campaign. A sales director asks the team to extend the iteration and skip regression checks to include every enhancement. What is the most appropriate response?

Correct Answer: B. Keep the timebox and required quality checks, then reprioritize or defer lower-priority enhancements while protecting the release-critical scope.
Explanation:

Timeboxing supports predictable delivery, and agile scope management uses prioritization to keep the most valuable and essential work within the available time. The fixed release date and required validation make extending the iteration or dropping regression checks unsuitable. Lower-priority enhancements can be deferred rather than compromising quality. Returning to detailed predictive planning does not resolve the immediate scope-versus-time decision and would discard useful iterative control.