Free PRINCE2 PRINCE 2 Project Management Foundation (Version 7) PRINCE2-Foundation Exam Questions

Last updated: · 11 practice questions with answers and explanations

Page: 1 / 32 Total 476 questions

Want more questions? Get Premium Access.

Question 1

New Single answer

Topic: Learning outcome 1 -Understand key concepts relating to projects and PRINCE2

Skill tested: Distinguishes project characteristics from ongoing business operations and relates them to PRINCE2.

A regional utility is replacing its customer billing platform. The work has a defined start and end, requires coordinated contributions from operations and an external supplier, and will deliver a new platform and migrated customer records. After handover, the utility will run the platform as part of its normal service. The sponsor argues that because billing operations continue indefinitely, the initiative should be managed as routine operations rather than as a project. Which assessment best reflects PRINCE2 concepts?

Correct Answer: C. It is a project because it creates defined products through temporary, coordinated work; ongoing use of those products is operational work.
Explanation:

The initiative is temporary and organized to deliver specified products, so it has the characteristics of a project. Once the platform is handed over, operating the billing service is ongoing business activity; the operational lifetime of a product does not make its delivery work operational. Supplier ownership is not a defining condition, and a project does not have to change every aspect of performance. PRINCE2 manages project performance across scope, time, cost, quality, risk, and benefits, but that does not determine whether work is a project.

Question 2

New Multiple answers

Topic: Learning outcome 2 -Understand how the PRINCE2 principles underpin the PRINCE2 method

Skill tested: Applies continued business justification and manage-by-exception principles to changing project conditions.

A project is partway through a stage when a regulatory change makes one expected benefit unlikely and increases delivery cost. The forecast remains within the project manager's agreed cost and time tolerances, but the revised business case may no longer justify the investment. The project manager can continue the approved work without exceeding delegated tolerances. Which two actions best apply the PRINCE2 principles? Select TWO.

Correct Answer: B. Reassess the business justification and provide the Project Board with an updated view of viability.; C. Escalate the changed justification to the Project Board for a decision, even though tolerances are not forecast to be exceeded.
Explanation:

Continued business justification requires the project's viability to be kept under review, not merely checked at the start or at closure. A materially weakened business case must therefore be brought to the Project Board's attention so it can decide whether the project remains worthwhile. Manage by exception delegates routine decisions within tolerances, but it does not prevent escalation of a business-justification concern. Staying within tolerances does not make continuation automatic. A team manager does not authorize the project, and benefits being realized later is no reason to postpone reviewing whether the investment still makes sense.

Question 3

New Single answer

Topic: Learning outcome 3 -Understand the PRINCE2 themes and how they are applied throughout the project

Skill tested: Applies output, outcome, benefit, and dis-benefit distinctions in business justification.

A public transport authority commissions a project to install a passenger-information system. The project will deliver installed displays and an operating support procedure. The intended operational change is that passengers use real-time information to make better travel decisions. The authority forecasts shorter average journey delays and also anticipates temporary disruption during installation. Its business case must distinguish what the project creates from what changes afterward and from the resulting measurable effects. Which classification is correct?

Correct Answer: D. Displays and support procedure are outputs; passenger decision changes are outcomes; shorter delays are a benefit; installation disruption is a dis-benefit.
Explanation:

Outputs are the products delivered by the project, so the displays and support procedure are outputs. An outcome is the result of using those outputs - in this case, passengers making decisions differently. A benefit is a measurable improvement resulting from an outcome, such as reduced average journey delays. A dis-benefit is a negative consequence of the change that can be anticipated and assessed, so temporary installation disruption fits that category. Treating the disruption only as a risk would miss that it is an expected negative effect rather than merely an uncertain event.

Question 4

New Single answer

Topic: Learning outcome 3 -Understand how the PRINCE2 themes and how they are applied throughout the project

Skill tested: Assigns executive, senior user, and senior supplier accountability to the correct project interests.

A company is forming a Project Board for a warehouse automation project. The investment owner must be accountable for the project's business justification. Warehouse operations must define and confirm that the delivered capability meets their needs and can realize the expected benefits. A technology partner must provide the specialist equipment and confirm the solution is feasible. The company wants each interest represented clearly, while retaining one accountable executive. Which role allocation is most appropriate?

Correct Answer: D. The executive represents the business justification, the senior user represents user needs and benefits, and the senior supplier represents supplier capability.
Explanation:

The executive is accountable for ensuring that the project remains focused on business justification and represents the business interest. The senior user represents those who will use or be affected by the products, including the needs and expected benefits of the user community. The senior supplier represents the interests of those designing, developing, facilitating, or supplying the project products. The other allocations exchange these accountabilities or place project-level responsibility on the project manager. Clear representation does not require all three roles to approve every product individually.

Question 5

New Multiple answers

Topic: Learning outcome 3 -Understand how the PRINCE2 themes and how they are applied throughout the project

Skill tested: Selects minimum organization-theme controls for defining accountability and stakeholder communication.

A distributed project has internal users, an external delivery partner, and a regulator whose decisions may affect acceptance. The project manager discovers that team members are receiving conflicting instructions and that the regulator's communication needs are not documented. The Project Board wants the organization theme applied consistently without adding unnecessary management layers. Which TWO actions best address these issues? Select TWO.

Correct Answer: B. Define and communicate clear project roles, responsibilities, and reporting relationships.; E. Document how the project will communicate with stakeholders, including their information needs and timing.
Explanation:

The organization theme requires clear definition of the project management team's structure, roles, and responsibilities so people know who makes decisions and where direction comes from. A communication management approach records how and by whom information will be provided to relevant stakeholders, including the regulator and external partner. Putting every communication task on the project manager does not replace defined accountabilities. Multiple boards would create unnecessary and conflicting governance, while informal communication alone cannot reliably address differing stakeholder needs.

Question 6

New Single answer

Topic: Learning outcome 3 -Understand how the PRINCE2 themes and how they are applied throughout the project

Skill tested: Uses the benefits management approach to plan benefit measurement beyond project closure.

A project will deliver a new online licensing service before the end of the financial year. The primary benefit - reduced processing cost - is expected to emerge only after staff have adopted the service over the following year. The project manager is preparing initiation information, but the project team will disband at closure and cannot own ongoing measurement. Which approach best supports effective benefits management?

Correct Answer: C. Define how and when benefits will be measured, who will own post-project measurement, and how the approach will be maintained.
Explanation:

The benefits management approach sets out how benefits are identified, measured, and reviewed, including when measurement will occur and who is responsible. Because the cost reduction is expected after adoption and after the project team disbands, ownership and post-project review arrangements need to be planned during the project. Acceptance of the service confirms an output, not realization of the benefit. A supplier may deliver products but does not automatically own the organization's business benefits, and postponing measurement design risks losing a meaningful baseline and accountability.

Question 7

New Single answer

Topic: Learning outcome 3 -Understand how the PRINCE2 themes and how they are applied throughout the project

Skill tested: Tailors project controls and documentation to the project's environment while retaining PRINCE2 requirements.

A small internal project is delivered by a stable team using the organization's standard product templates and short approval cycles. The project manager proposes copying the full documentation set from a major infrastructure project, including separate registers and reporting layers that duplicate information already held in controlled corporate systems. The executive supports proportionate control but requires the project to remain a PRINCE2 project. Which recommendation is best?

Correct Answer: B. Tailor the application of PRINCE2 controls and documentation to the project, reuse suitable corporate systems, and retain the method's principles.
Explanation:

PRINCE2 is tailored to suit the project's size, complexity, importance, capability, and environment. Proportionate documentation and the reuse of controlled corporate systems can avoid duplication while preserving appropriate control. Tailoring does not mean abandoning the principles or removing essential governance such as business justification and defined accountability. Applying every large-project artefact unchanged would be inefficient, while leaving principle selection informal would undermine the method's requirement that all PRINCE2 principles underpin the project.

Question 8

New Single answer

Topic: Learning outcome 4 Understand the PRINCE2 processes and how they are carried out throughout the project

Skill tested: Distinguishes the project brief and initiation work used to authorize detailed project planning.

A board has received a proposal for a data-retention project. Senior management needs enough information to decide whether to initiate the project, but it does not want the team to spend heavily on detailed planning before that decision. The proposal currently identifies a possible business need and a preferred technical direction, but key assumptions, project approach, and outline controls remain uncertain. Which next step best follows the PRINCE2 process structure?

Correct Answer: A. Carry out Starting up a Project to prepare the project brief and initiation stage plan, then seek authorization to initiate.
Explanation:

Starting up a Project is a pre-project process that checks whether the project is worthwhile and viable enough to justify initiation. It produces the project brief, which provides the basis for the decision to initiate, and an initiation stage plan for the work needed to create the fuller project initiation documentation. Completing detailed plans before authorization would commit effort prematurely. Controlling a Stage applies after initiation and authorization, while Closing a Project is used at the end of an authorized project.

Question 9

New Multiple answers

Topic: Learning outcome 4 Understand the PRINCE2 processes and how they are carried out throughout the project

Skill tested: Identifies Project Board decisions and direction within Directing a Project.

A Project Board has authorized the first delivery stage. During that stage, a forecast shows that the next stage's risk exposure will exceed the approved project tolerance unless the scope is reconsidered. The project manager has prepared an exception report and needs direction before committing the organization to the next stage. The board also wants to keep its role at the management-by-exception level rather than supervise day-to-day work. Which TWO actions belong to Directing a Project? Select TWO.

Correct Answer: D. The Project Board provides ad hoc direction and makes decisions needed to keep the project viable.; E. The Project Board reviews the exception information and decides whether to authorize the next stage or request a revised plan.
Explanation:

Directing a Project is the Project Board's process for making key decisions, authorizing stages and plans, and providing direction while delegating day-to-day management to the project manager. A forecast beyond tolerance is escalated for board direction; the board can decide whether to authorize a proposed next stage or require replanning. Daily task assignment belongs to delivery management, not the board. The project manager prepares information and manages within delegated authority but does not authorize the project on the board's behalf. A team manager cannot change project tolerances.

Question 10

New Single answer

Topic: Learning outcome 4 Understand the PRINCE2 processes and how they are carried out throughout the project

Skill tested: Uses Managing Product Delivery to control team acceptance and delivery of authorized work.

A project manager has authorized a work package for a specialist team. The team manager confirms that the required products and quality criteria are understood, but the team has not yet agreed to the work or confirmed its delivery forecast. The project manager wants delivery to proceed under clear controls and needs reliable status information for stage monitoring. What is the most appropriate next step?

Correct Answer: C. Have the team manager agree to the work package, manage its execution, and report progress and completed products to the project manager.
Explanation:

Managing Product Delivery establishes the controlled link between the project manager and team manager. The team manager agrees to the work package, ensures the authorized work is done, and reports progress and product completion so the project manager can control the stage. The Project Board governs at a higher level and should not assign routine team tasks. Managing a Stage Boundary is used near the end of a stage, not to start an authorized work package. The project manager manages delivery rather than taking over specialist production.

Question 11

New Single answer

Topic: Learning outcome 4 Understand the PRINCE2 processes and how they are carried out throughout the project

Skill tested: Selects closure activities that confirm acceptance, hand over products, and capture lessons.

A software implementation has met its acceptance criteria, and the users have formally accepted the delivered service. The project's agreed scope is complete, but the project manager has not confirmed product ownership, checked whether any follow-on actions remain, or prepared a final performance record. The executive wants the project closed in a controlled way rather than left open for informal support requests. What should the project manager do next?

Correct Answer: C. Close the project through the formal closure process, confirming acceptance and handover, assessing performance, and recording follow-on actions and lessons.
Explanation:

Closing a Project provides a controlled end to the project. The project manager confirms that products have been accepted and handed over, assesses performance against the approved plans, records lessons and any follow-on actions, and recommends closure to the Project Board. Acceptance is important but does not by itself complete all closure responsibilities. Keeping the project open indefinitely confuses temporary project work with ongoing operations, while repeating testing for hypothetical future issues is not a substitute for agreed acceptance and handover.