Question 1

Which of the following statements about the Project Initiation Documentation are true?

1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.

2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.

Correct Answer: C. Both 1 and 2 are true
Explanation:

Both statements about the Project Initiation Documentation (PID) are correct. The PID is essential for establishing a solid foundation for the project, ensuring that all stakeholders agree on the project's objectives and how it will be managed before the Project Board authorizes it. Additionally, the PID should be updated at the end of each stage to reflect the current status of the project, ensuring that it continues to meet the project's requirements and objectives. Reference: PRINCE2 Foundation official documentation and study materials.


Question 2

How is Uncertainty Identified, assessed and controlled?

Correct Answer: C. By applying the risk practice
Explanation:

Uncertainty in a project is identified, assessed, and controlled by applying the risk practice. This practice involves systematic risk identification, analysis, and management, ensuring that risks are properly understood and addressed through appropriate responses to protect the project objectives. Reference: PRINCE2 Foundation official guide and risk management section.


Question 3

Which describes a project benefit?

Correct Answer: D. A measurable improvement resulting from an outcome
Explanation:

In PRINCE2, a project benefit is defined as a measurable improvement that results from an outcome perceived as an advantage by one or more stakeholders. Benefits are the positive effects or gains yielded by the project, which contribute directly to the organization's objectives. Reference: PRINCE2 7 Foundation Handbook and official training materials.


Question 4

What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

Correct Answer: C. Highlight Report
Explanation:

The Highlight Report in PRINCE2 is used by the Project Manager to review the performance of a Work Package against its cost tolerance, among other factors. This report provides the Project Board with a summary of the stage status, and is a key tool for monitoring overall project progress, including financial performance. Reference: PRINCE2 Foundation manual, PRINCE2 official resources


Question 5

What must be done for a project to be a PRINCE2 project?

Correct Answer: B. The project must meet the minimum requirements for applying the themes
Explanation:

For a project to be considered a PRINCE2 project, it must meet the minimum requirements for applying the seven PRINCE2 themes. These themes (Business Case, Organization, Quality, Plans, Risk, Change, and Progress) provide a framework for managing the project and ensuring that it is conducted in a systematic, consistent manner that is aligned with PRINCE2 principles.

= PRINCE2 7 Foundation handbook and online resources


Question 6

Which is a purpose of a quality register?

Correct Answer: C. To provide the status of quality activities carried out for completed products
Explanation:

The purpose of a Quality Register in PRINCE2 is to provide a detailed record of all quality activities that are planned and carried out over the course of the project. It includes information such as who will perform the quality check, what standards must be met, and the status and outcome of these quality activities. This ensures that each product meets its defined quality criteria before being deemed complete.

= PRINCE2 7 Foundation handbook and online resources


Question 7

Which is a feature of an effective project team?

Correct Answer: B. It should consist of people with a wide range of skills, abilities and viewpoints
Explanation:

An effective project team in PRINCE2 should be diverse, consisting of individuals with a variety of skills, abilities, and viewpoints. This diversity helps to ensure that the team can handle various aspects of the project effectively, bringing different perspectives to problem-solving and decision-making, which enhances the overall capability of the project team.

(PRINCE2 7 Foundation Handbook, AXELOS)


Question 8

Which is a purpose of the 'initiating a project' process?

Correct Answer: B. To enable the project board to decide whether it is worthwhile to initiate a project
Explanation:

The primary purpose of the 'Initiating a Project' process in PRINCE2 is to provide a foundation for the project board to make an informed decision about whether it is worthwhile to proceed with the project. This process involves the development of a detailed Project Initiation Documentation that outlines the project's objectives, scope, constraints, and management strategies. Reference: PRINCE2 7 Foundation Handbook and official training materials.


Question 9

In which step of the 'risk management technique should the organization's environment be considered?

Correct Answer: A. Identify
Explanation:

Similar to question 397, the correct answer for considering the organization's environment in the risk management technique is during the 'Identify' step. This initial phase of risk management involves recognizing and recording risks after considering various environmental factors that can influence the project.

PRINCE2 7 Foundation guide on risk management.


Question 10

Identify the missing word in the following sentence.

The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment.

Correct Answer: B. processes
Explanation:

The missing word in the sentence is 'processes.' PRINCE2 is a method that addresses project management through four integrated elements: principles, themes, processes, and tailoring the method to suit the project environment. The processes component includes a series of steps and activities to be carried out during the project's lifecycle. Reference: PRINCE2 7 Foundation Handbook and official training materials.


Question 11

What is the minimum number of management stages required by PRINCE2?

Correct Answer: A. Two stages: to initiate and to deliver the project
Explanation:

PRINCE2 requires a minimum of two management stages for any project: one to initiate the project and another to deliver the project. This structure ensures proper planning, delegation, monitoring, and control over the course of the project lifecycle.

= PRINCE2 7 Foundation handbook and online resources


Question 12

Identify the missing word in the following sentence.

A project's [ ? ] are the measurable improvements resulting from the outcomes achieved through the use of the project's outputs.

Correct Answer: A. benefits
Explanation:

In PRINCE2, a project's benefits are defined as the measurable improvements that result from the outcomes achieved through the use of the project's outputs. These benefits should align with the objectives set out in the business case and are an essential part of the project's value proposition. Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.


Question 13

The project manager needs to define key information so that the project board can decide whether to proceed with planning the project in more detail.

In which process should the project manager define this information?

Correct Answer: B. Initiating a project
Explanation:

During the 'Initiating a Project' process, the project manager develops key information, including the detailed Project Initiation Documentation (PID), which enables the project board to decide whether to proceed with the project. This information outlines the approach, plans, and controls that will govern the project, providing a foundation for detailed planning and informed decision-making by the project board.

PRINCE2 7 Foundation materials on the 'Initiating a Project' process.


Question 14

Identify the missing words in the following sentence.

PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.

Correct Answer: B. the project board
Explanation:

PRINCE2 requires that the business case be formally verified by the project board at stage boundaries. This verification is essential to ensure that the project remains viable and desirable from a business perspective. The project board's review of the business case at these critical points helps in deciding whether the project should continue into its next stage.

PRINCE2 Foundation Manual


Question 15

Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

Correct Answer: B. Manage by exception
Explanation:

The PRINCE2 principle supported by the setting of tolerances for the three levels of plan (Project, Stage, and Team Plans) is 'Manage by exception.' This principle allows management to set predefined tolerances for project objectives, and only escalate issues to higher management if these tolerances are exceeded, thereby facilitating efficient use of management time and focus. Reference: PRINCE2 Foundation manual, PRINCE2 official resources