Question 1

New Single answer

Topic: Introducing Scrum in SAFe®

Skill tested: Applies Scrum team events and iterative delivery within a SAFe Agile Team.

A product group is introducing Scrum practices across several teams on an Agile Release Train. One team proposes to treat its two-week iteration as a small project phase: complete all analysis first, then hand work to developers, and ask testers to validate everything at the end. The team must deliver integrated, potentially releasable value regularly and coordinate with other teams on the ART. What should the Scrum Master recommend?

Correct Answer: B. Organize the team around cross-functional collaboration so analysis, development, and testing occur as needed throughout the iteration.
Explanation:

A SAFe Agile Team is cross-functional and collaborates to deliver tested, integrated value in short iterations. Analysis, development, and testing are not intended to become sequential specialist handoffs that defer feedback until the end. Shortening a waterfall sequence does not remove its queues or integration risk, while moving testing to a later iteration postpones validation. Separate specialist backlogs also undermine the team's shared responsibility for completing work and coordinating with the ART.

Question 2

New Single answer

Topic: Introducing Scrum in SAFe®

Skill tested: Identifies team behaviors that support high performance and shared accountability.

A newly formed team consistently meets its iteration commitments, but members avoid raising risks during planning because they fear being blamed. Defects are discovered late, and developers tend to optimize their own assignments rather than help work reach completion. The organization wants dependable delivery, but the Scrum Master cannot impose individual performance targets or change the team's membership this quarter. Which intervention is the best first step?

Correct Answer: B. Encourage the team to surface impediments and risks safely, then reinforce collective ownership of completing work.
Explanation:

Psychological safety and shared accountability enable team members to expose risks early, ask for help, and collaborate to finish work. The Scrum Master should coach these behaviors rather than introduce individual rankings that can reinforce fear and local optimization. Increasing commitments does not address the causes of late defects, and requiring sequential coding and testing would deepen handoffs rather than improve flow.

Question 3

New Single answer

Topic: Introducing Scrum in SAFe®

Skill tested: Connects DevOps practices with continuous delivery and Release on Demand.

A business unit has teams that can complete features during each iteration, but customers receive changes only during quarterly release windows. A manual approval queue and infrequent integrated testing create long delays; the business wants the option to release value when market conditions warrant, while retaining its required governance controls. Which direction best supports this goal?

Correct Answer: B. Adopt DevOps practices that automate integration, testing, and deployment controls, while decoupling deployment from the decision to release.
Explanation:

DevOps enables frequent, reliable integration and deployment through automation and shared responsibility. Release on Demand means the organization can make a business decision about when to expose value; it does not mean every change must be released immediately. Automated controls can preserve governance while reducing the manual queue. Longer iterations and quarterly integration leave the underlying delays and integration risk intact, and checklists alone do not create a continuous delivery capability.

Question 4

New Single answer

Topic: Defining the Scrum Master / Team Coach role

Skill tested: Facilitates team self-management without taking ownership of team decisions.

During iteration planning, a department manager tells the Scrum Master to assign each story to a named developer and require individual estimates. The team has been working toward self-management, and its members have the technical knowledge to decide how to deliver the iteration goal. The manager is concerned about accountability and asks the Scrum Master to enforce the assignments. What is the most appropriate response?

Correct Answer: A. Explain the team's responsibility for organizing its work, and facilitate a discussion with the manager about transparent progress and outcomes.
Explanation:

The Scrum Master or Team Coach serves the team by facilitating self-management, removing impediments, and coaching stakeholders on effective Agile practices. The team - not the manager, Scrum Master, or Product Owner - decides how to organize its work. Transparency about goals and progress addresses accountability without assigning individuals or confusing backlog prioritization with implementation authority. Refusing stakeholder dialogue would miss an opportunity to coach the organization.

Question 5

New Single answer

Topic: Defining the Scrum Master / Team Coach role

Skill tested: Uses coaching questions to help a team diagnose and improve its delivery process.

A team has missed its iteration goal twice. In both cases, members accepted more work than they could complete and discovered dependencies only after development began. The Scrum Master has previously responded by telling the team how much to take and which stories to start. The team now waits for the Scrum Master to make these decisions. Which coaching approach is most appropriate for the next planning session?

Correct Answer: D. Ask the team to review recent evidence, identify causes of overcommitment and late dependency discovery, and choose an experiment for the next iteration.
Explanation:

A Team Coach helps the team learn from evidence and develop its own improvement actions. Reviewing actual outcomes and discussing dependency discovery can lead to a practical experiment, such as earlier coordination or a more realistic forecast. Imposing capacity or daily reassignment preserves dependence on the Scrum Master. Removing every dependent story is an overbroad response that avoids managing dependencies rather than improving the team's capability.

Question 6

New Single answer

Topic: Defining the Scrum Master / Team Coach role

Skill tested: Removes organizational impediments by facilitating stakeholder collaboration and escalation.

An Agile Team has completed a working increment, but a separate compliance group will not review it until the end of the month. The delay makes timely feedback impossible and has blocked several iterations. Team members have already documented the impact and asked the group for an earlier review, without success. The Scrum Master has no authority to change the compliance group's staffing or policy. What should the Scrum Master do next?

Correct Answer: C. Facilitate a discussion between the team and compliance stakeholders to make the impediment visible and pursue an agreed change or escalation.
Explanation:

A Scrum Master helps remove impediments and supports collaboration across organizational boundaries. Since the team cannot resolve the recurring review delay alone and the Scrum Master lacks direct authority, the next useful action is to bring the affected stakeholders together, clarify the impact, and seek a workable process or escalation. Declaring incomplete work done or deleting valid controls misrepresents delivery; stopping work needlessly transfers the problem to the team.

Question 7

New Single answer

Topic: Supporting Team Events

Skill tested: Facilitates iteration planning using a clear goal, priority, and realistic team forecast.

A team begins iteration planning with a prioritized backlog, but the Product Owner has not described the outcome most important for the iteration. Several high-priority items depend on an external service team, whose availability is uncertain. Management asks the Scrum Master to ensure that the team commits to the maximum possible number of stories. Which action best supports effective iteration planning?

Correct Answer: A. Facilitate agreement on an iteration goal, clarify the likely external dependency, and let the team forecast work it believes it can complete.
Explanation:

Iteration planning should establish a meaningful goal and enable the team to select and forecast work based on its understanding of capacity and dependencies. The Product Owner provides priority and context, while the team determines what it can accomplish. Maximizing story count or imposing a point target encourages overcommitment. Waiting for certainty about every dependency can unnecessarily delay planning; the team can instead make the risk visible and plan responsibly.

Question 8

New Multiple answers

Topic: Supporting Team Events

Skill tested: Uses team syncs to inspect progress, expose impediments, and adapt near-term work.

Midway through an iteration, an Agile Team's daily sync has become a series of status reports to the Scrum Master. A newly discovered API limitation affects two stories, and one developer is blocked while another has capacity to help. The team wants to protect the iteration goal, avoid turning the sync into a lengthy problem-solving meeting, and coordinate useful follow-up. Which TWO actions should the Scrum Master encourage? Select TWO.

Correct Answer: A. Have team members focus the sync on progress toward the goal, newly surfaced impediments, and any needed adjustments to near-term collaboration.; B. Encourage the blocked developer and available teammate to arrange a focused follow-up after the sync.
Explanation:

A team sync is a coordination opportunity for the team to inspect progress toward its goal, surface impediments, and adapt its collaboration. Detailed reporting to the Scrum Master shifts ownership away from the team. A focused follow-up allows the affected members to solve the API issue without consuming the entire sync. The Scrum Master should not unilaterally abandon the goal, and waiting until iteration review would delay action on a current blocker.

Question 9

New Multiple answers

Topic: Supporting Team Events

Skill tested: Improves backlog refinement by clarifying stories, acceptance criteria, and dependency risks.

A team repeatedly carries partially understood stories into iterations. Developers disagree about what counts as acceptable behavior, and an external data team must provide a field mapping before one feature can be tested. The Product Owner is available to work with the team, but stakeholders cannot attend every refinement session. The team wants refinement to improve readiness without treating estimates as commitments. Which TWO practices are most appropriate? Select TWO.

Correct Answer: C. Collaborate with the Product Owner to clarify desired outcomes and acceptance criteria for upcoming backlog items.; E. Identify and discuss the data-team dependency early, including who will follow up and what uncertainty remains.
Explanation:

Backlog refinement improves shared understanding of upcoming work, including its value, acceptance criteria, and dependencies. The Product Owner and team should collaborate on these details, and the external mapping risk should be made visible early. Estimates support planning but are not guaranteed commitments, so fixing them indefinitely is inappropriate. Pulling unclear work into an iteration increases delivery risk, while having the Scrum Master author requirements in isolation bypasses the people responsible for product direction and implementation.

Question 10

New Single answer

Topic: Supporting Team Events

Skill tested: Uses the iteration review to inspect completed outcomes and gather stakeholder feedback.

At an iteration review, a team plans to present a slide deck describing completed tasks. The actual increment includes a feature that behaves differently from what the Product Owner expected, and business stakeholders are available to discuss whether it meets their needs. The team wants useful feedback before the next planning session. What should the Scrum Master recommend?

Correct Answer: B. Present the completed increment, invite inspection and feedback from the Product Owner and stakeholders, and use the learning to inform future backlog decisions.
Explanation:

The iteration review is an opportunity to inspect the increment with relevant stakeholders and adapt based on what was learned. Showing actual working behavior, including the mismatch, makes feedback concrete and helps the Product Owner consider appropriate backlog changes. Canceling delays learning, while individual blame discourages transparency. Task slides and a private approval do not provide the shared inspection needed to understand whether the outcome meets stakeholder needs.

Question 11

New Single answer

Topic: Supporting ART Events

Skill tested: Supports PI Planning through dependency coordination, risk visibility, and team planning.

During PI Planning, a team sees that its proposed feature depends on another team delivering an interface early in the PI. The other team has not confirmed that timing, and the feature is important but not a regulatory commitment. The planning group is preparing to finalize team plans and identify risks. What should the Scrum Master do to support sound planning?

Correct Answer: C. Help both teams make the dependency visible, coordinate a discussion about timing, and record the unresolved risk for the appropriate planning follow-up.
Explanation:

PI Planning depends on collaboration across teams so dependencies and risks are visible while plans can still be adjusted. The Scrum Master should help the teams coordinate, clarify the assumption, and ensure the unresolved risk is addressed through the planning process. An unsupported commitment hides uncertainty. A dependency does not automatically make work impossible, and one team's Scrum Master cannot promise another team's delivery date.

Question 12

New Multiple answers

Topic: Supporting ART Events

Skill tested: Plans IP Iteration capacity for innovation, learning, planning, and improvement activities.

A release train is preparing for its next PI. Leaders want teams to use the Innovation and Planning (IP) Iteration as extra feature-development capacity to recover schedule, while teams report that they need time for PI Planning preparation, learning, and improvement work. The train also wants to avoid creating a new fixed feature commitment during that iteration. Which TWO recommendations best align with the purpose of the IP Iteration? Select TWO.

Correct Answer: D. Preserve capacity for activities such as innovation, learning, exploration, and improvement.; E. Use the time to support PI Planning and other necessary planning activities.
Explanation:

The IP Iteration provides time for innovation, exploration, learning, improvement, and PI Planning-related activities. Consuming all of it as feature capacity removes the buffer and undermines those purposes; it also does not guarantee that unfinished scope will be completed. Treating it as an ordinary fully loaded iteration or prohibiting planning and coordination likewise conflicts with its intended use.

Question 13

New Single answer

Topic: Supporting ART Events

Skill tested: Facilitates Inspect and Adapt problem-solving using data and actionable improvement outcomes.

At an ART's Inspect and Adapt event, teams review PI results and identify a recurring integration delay. Several participants immediately propose adding more status meetings, but the cause has not been analyzed and the proposed change has no measure of success. The ART wants an improvement that can be evaluated in the next PI, and leaders want the event to focus on systemic issues rather than blame. What should the Scrum Master encourage?

Correct Answer: A. Use the event's problem-solving discussion to examine relevant data, identify a root cause, and agree on a measurable improvement action.
Explanation:

Inspect and Adapt combines reflection on PI outcomes with structured problem-solving and improvement planning. Examining evidence and seeking a root cause helps the ART choose an action that addresses the systemic delay, while a measure makes it possible to assess progress in the next PI. Selecting a popular solution without analysis risks treating symptoms. Isolated team actions and excluding the ART from a cross-team issue prevent shared learning and coordinated improvement.