Question 1
Topic: Project Management
Skill tested: Configures project task dependencies to represent schedule logic and drive sequencing.
A utilities organization is moving a set of interdependent field deployments into Project Workspace. A deployment project contains design, permitting, procurement, and construction tasks. Construction must not begin until both permitting and procurement are complete, while design is a predecessor to each of those tasks. The project manager wants the schedule to reflect these relationships so that date changes can propagate through the plan. They do not want to rely on manually entered dates or use a single chain that incorrectly makes permitting and procurement sequential. Which configuration best represents the required schedule logic?
The required logic is a dependency network: design precedes both permitting and procurement, and both must precede construction. Recording these predecessor relationships lets the project schedule calculate sequencing based on the dependencies without imposing a false order between permitting and procurement. A single chain makes procurement wait for permitting even though the scenario permits parallel work. Reversing the relationships contradicts the intended sequence, while fixed dates without dependencies do not express the schedule logic or support dependency-driven rescheduling.