Question 1

New Single answer

Topic: 1. Basics of Agile Software Development

Skill tested: Applies Agile Manifesto values when balancing delivery, collaboration, and changing requirements.

A financial-services team has completed a detailed requirements specification and test plan for a six-month release. After the first two weeks, users reveal that a planned workflow does not match how they handle urgent cases. The project lead proposes freezing requirements to protect the plan, while the product owner wants the team to adapt without losing accountability for regulatory needs. Which response best reflects the Agile Manifesto while preserving the team's ability to deliver a controlled product?

Correct Answer: B. Work with users and the product owner to reprioritize the backlog, deliver valuable increments, and retain necessary regulatory evidence.
Explanation:

Agile values working with customers and responding to change, while still recognizing that processes, plans, documentation, and contracts can have value. Reprioritizing the backlog with users lets the team respond to evidence and deliver useful increments; retaining required regulatory evidence avoids treating agility as an excuse to discard necessary controls. Freezing the specification overweights the original plan, developer-led implementation delays collaboration, and eliminating documentation misunderstands the Manifesto's qualification that documentation remains valuable when appropriate.

Question 2

New Multiple answers

Topic: 1. Basics of Agile Software Development

Skill tested: Distinguishes iterative development from incremental delivery and evaluates the value of feedback.

A product team is developing a new claims portal. Its first two-week cycle produces a working, end-to-end version of claim submission with only essential fields. In later cycles, the team adds document upload and status tracking, while changing the original form after users try it. A stakeholder argues that the team is not using an Agile approach because the complete portal is not available after the first cycle. Select TWO statements that best describe what is happening. Select TWO answers.

Correct Answer: A. The team combines incremental development with iterative refinement of previously delivered behavior.; E. The team is delivering increments of product capability while learning through repeated cycles.
Explanation:

The team adds capability in increments, and it iteratively refines earlier behavior based on user feedback. Agile delivery does not require the entire product to exist in the first iteration; a useful, working slice can support learning and inform later work. The process is not sequential merely because features are developed over time, and the scenario does not establish that each increment must be a complete production release. Delaying feedback would undermine the learning cycle that the team is already using.

Question 3

New Single answer

Topic: 1. Basics of Agile Software Development

Skill tested: Selects an Agile approach suited to adaptive planning and frequent customer feedback.

A small company is building a novel service whose users cannot fully describe their needs before seeing prototypes. The team can release a usable subset every few weeks, and a product representative is available to make priority decisions. However, the company must still plan around a fixed annual budget and report progress to senior management. Which project approach is most appropriate?

Correct Answer: C. Use short development iterations, obtain frequent feedback, and adapt the prioritized work while tracking progress against the budget.
Explanation:

Short iterations and frequent feedback suit uncertain requirements and allow the team to learn from usable subsets. Agile planning is adaptive, not absent: the product representative can reprioritize work, while the team reports progress and manages the fixed budget. A comprehensive baseline with tightly restricted change is poorly suited to needs that emerge through prototype use. A single long development phase delays learning, and avoiding planning would not address the budget or management reporting constraint.

Question 4

New Single answer

Topic: 2. Basic Agile Testing Guidelines, Procedures, and Practices

Skill tested: Integrates testing throughout an Agile iteration instead of deferring validation to its end.

During a three-week iteration, a team schedules development for the first two weeks and reserves the final week for a tester to verify all completed stories. In recent iterations, defects discovered late have forced developers to reopen work and have left little time for regression testing. The team cannot extend the iteration, and it wants to preserve its commitment to a potentially releasable increment. What is the BEST change to its testing practice?

Correct Answer: A. Have testers participate from story refinement onward and test completed work continuously as it becomes available.
Explanation:

Testing in Agile is integrated throughout the iteration, rather than treated as a separate phase after development. Tester participation during refinement can clarify testability and acceptance conditions; continuous testing then provides earlier feedback, enabling defects to be corrected before the end-of-iteration deadline. Adding testers only at the end preserves the bottleneck, while removing other testing or deferring all verification risks carrying unvalidated work forward and undermines the goal of a potentially releasable increment.

Question 5

New Multiple answers

Topic: 2. Basic Agile Testing Guidelines, Procedures, and Practices

Skill tested: Uses acceptance criteria and collaborative refinement to make stories testable before implementation.

A team repeatedly discovers disagreements during sprint review because a story titled "Make account recovery easier" has no defined behavior. The product owner can meet with the team during backlog refinement, and the team wants to reduce ambiguity without turning every story into a lengthy specification. Which TWO actions are most appropriate? Select TWO answers.

Correct Answer: A. Collaboratively clarify the story and agree on observable acceptance criteria before selecting it for an iteration.; B. Use examples and discussion to identify expected outcomes, including relevant boundary cases.
Explanation:

Collaborative refinement and concrete examples help the product owner, developers, and tester establish shared expectations before implementation. Observable acceptance criteria give the team a basis for deciding whether the story meets its intended behavior, while targeted examples can expose boundaries without requiring an exhaustive specification. Developer-by-developer interpretation perpetuates disagreement; a test specification written after coding cannot prevent misunderstandings; and relying only on an ambiguous title does not create shared understanding.

Question 6

New Single answer

Topic: 2. Basic Agile Testing Guidelines, Procedures, and Practices

Skill tested: Applies whole-team quality ownership while preserving the tester's independent testing contribution.

A cross-functional team says that "quality belongs to everyone," so it has stopped assigning testers to stories. Developers perform code reviews and automated unit checks, but recent releases have exposed usability problems and inconsistent interpretation of business rules. The organization will not add staff, and testers remain available as team members. What is the most appropriate response?

Correct Answer: B. Keep testers engaged in the team to contribute risk-based testing, clarify business rules, and support the whole team's quality activities.
Explanation:

Whole-team responsibility for quality does not make testing expertise unnecessary. Testers can help identify risks, challenge assumptions about business rules, design and perform tests, and collaborate with developers and the product owner throughout delivery. A late separate phase recreates the delay that Agile practices seek to avoid. Restricting testers to unit-test automation overlooks their broader contribution, while the product owner's business knowledge does not replace systematic testing skills.

Question 7

New Single answer

Topic: 2. Basic Agile Testing Guidelines, Procedures, and Practices

Skill tested: Interprets iteration test status through transparent progress, risks, and unresolved defects.

At the daily coordination meeting, a tester reports that 18 of 20 planned checks have passed. The remaining two checks are blocked by an unstable integration environment, and one failed check affects a high-priority payment path. The team's dashboard currently shows "90% complete," which has led stakeholders to assume the feature is nearly ready. The team needs a concise, honest status that supports a decision about the iteration goal. What should the tester do?

Correct Answer: A. Update the shared status with passed, failed, and blocked checks, explain the payment-path risk, and raise the environment impediment.
Explanation:

Agile test status should give the team and stakeholders useful, current information, not a misleading completion percentage. Separating passed, failed, and blocked work makes uncertainty visible; identifying the high-priority payment risk helps the team decide what to address, and raising the environment impediment supports prompt resolution. A pass-only percentage conceals important information, blocked tests cannot be treated as passing, and waiting until review delays action on a material risk.

Question 8

New Multiple answers

Topic: 2. Basic Agile Testing Guidelines, Procedures, and Practices

Skill tested: Selects tester competencies that improve collaboration, test analysis, and continuous feedback.

A company is forming a new Agile team to replace a manual release process. Its testers are experienced at executing scripted tests but have had little exposure to iterative development. The team needs testers who can contribute effectively alongside developers and product representatives, and it cannot rely on a separate test phase. Which TWO capabilities should the team prioritize developing? Select TWO answers.

Correct Answer: B. Analyzing stories and acceptance criteria to identify test conditions early.; D. Communicating risks and test findings clearly while collaborating with the whole team.
Explanation:

Agile testers need strong collaboration and communication skills, as well as the ability to analyze stories and acceptance criteria early. These capabilities make risks and misunderstandings visible while the team can still act on them. Avoiding interaction conflicts with collaborative development, and quality is a whole-team responsibility rather than the tester's sole responsibility. Deferring test design until implementation ends recreates a late testing phase and loses opportunities to improve testability beforehand.

Question 9

New Single answer

Topic: 3 Technologies, Strategies, and Methods for Agile Testing

Skill tested: Chooses a test strategy that balances regression confidence with rapid iteration feedback.

An online retailer deploys small changes several times a week. Each deployment can affect a set of shared checkout services, and the team has a growing suite of automated checks. The complete suite takes several hours to run, so developers often wait too long for feedback; skipping regression testing has also allowed checkout defects to escape. The team wants faster feedback without abandoning broader regression coverage. What is the BEST strategy?

Correct Answer: B. Prioritize a fast, relevant automated test set for frequent feedback, and run broader regression tests at appropriate integration or delivery points.
Explanation:

A layered, risk-aware strategy can provide rapid feedback while retaining regression confidence. A fast set of relevant automated checks helps developers detect important problems early; broader regression testing can run at suitable integration or delivery points. Testing only new behavior leaves shared checkout services exposed, while running a multi-hour suite for every change recreates the feedback delay. Exploratory testing is valuable but does not, by itself, replace repeatable regression checks.

Question 10

New Multiple answers

Topic: 3 Technologies, Strategies, and Methods for Agile Testing

Skill tested: Prioritizes testing based on product risk, business impact, and likelihood of failure.

A healthcare software team has one iteration remaining before a pilot. The backlog includes a high-impact medication-dose calculation change with complex boundaries, a cosmetic label adjustment on a rarely used report, and a recently modified interface between patient records and the scheduling service. The team has limited test time and no permission to use live patient data. It must decide where to focus testing. Which THREE actions best apply risk-based testing? Select THREE answers.

Correct Answer: B. Test the modified patient-records/scheduling interface because a changed integration may fail across component boundaries.; C. Prioritize boundary and calculation testing for the medication-dose change because an error could cause serious harm.; E. Use anonymized or synthetic data to exercise the high-risk workflows without exposing live patient information.
Explanation:

Risk-based testing directs limited effort toward areas with high impact or increased likelihood of failure. The medication calculation warrants careful boundary testing because incorrect doses can be harmful, and the changed service interface presents integration risk. Anonymized or synthetic data allows meaningful workflow testing while respecting the prohibition on live patient data. Equal effort ignores differences in risk, and focusing on an easy cosmetic change would leave the most consequential risks insufficiently examined.

Question 11

New Single answer

Topic: 3 Technologies, Strategies, and Methods for Agile Testing

Skill tested: Uses test automation at appropriate levels to support continuous integration feedback.

A development team has frequent integration failures in a service that contains complex business rules. Its browser-based end-to-end tests are slow and intermittently fail because of timing and shared test data. Developers propose adding more browser tests to cover every rule, but the pipeline must provide dependable feedback within minutes. Which approach is MOST appropriate?

Correct Answer: B. Move most business-rule checks into focused, fast tests near the code, and retain a smaller set of end-to-end tests for critical user journeys.
Explanation:

Focused tests close to the business logic usually provide faster and more stable feedback for detailed rules, while a smaller end-to-end suite checks that critical workflows function across integrated components. This division addresses both the pipeline time constraint and the intermittent browser-test problems. Removing automation loses repeatability; expanding the slowest layer worsens feedback time and flakiness; and postponing checks until release allows integration defects to persist.

Question 12

New Single answer

Topic: 3 Technologies, Strategies, and Methods for Agile Testing

Skill tested: Uses exploratory testing to investigate risks not fully covered by scripted checks.

A travel company has released a new itinerary-change feature. Automated tests cover the specified paths, but early customer feedback suggests that some travelers lose context when they switch between a booking and an alternative itinerary. The team has limited time before its next planning meeting and wants to learn how the feature behaves in realistic use, rather than merely repeat known checks. What should the tester do NEXT?

Correct Answer: A. Conduct time-boxed exploratory testing using realistic user goals, record observations and risks, and discuss findings with the team.
Explanation:

Exploratory testing combines learning, test design, and execution, making it well suited to investigating emerging concerns that predefined checks may not cover. Realistic goals can reveal context-loss problems, and recording observations gives the team actionable information before planning. Repeating the same regression suite does not explore the reported behavior; waiting for a complete specification delays learning; and service-level checks alone cannot assess the user's interaction across screens.