Free PMI Project Management Professional (PMBOK 7th Version) PMP Exam Questions

Last updated: · 14 practice questions with answers and explanations

Page: 1 / 13 Total 187 questions

Want more questions? Get Premium Access.

Question 1

New Single answer

Topic: People

Skill tested: Facilitating conflict resolution and revising team ground rules collaboratively.

During a hybrid project, two experienced specialists repeatedly argue over whether to prioritize early demonstrations or complete design documentation before implementation. Their exchanges are disrupting planning sessions, and other team members have stopped raising concerns. The project manager has authority to facilitate working agreements but does not own either specialist's technical decisions. The project has a near-term delivery milestone, and replacing either specialist is not feasible. What should the project manager do FIRST?

Correct Answer: B. Facilitate a discussion in which the team identifies the conflict's causes, agrees on decision-making and respectful discussion ground rules, and records the updated agreements.
Explanation:

A facilitated conversation addresses the behavior and the underlying disagreement while allowing the team to own its working agreements. Revising and recording ground rules can restore psychological safety and clarify how technical disagreements will be handled. Directing a technical choice (A) exceeds the described facilitation need and does not address the damaged team interaction. Escalating immediately to the sponsor (C) is premature, while delaying dialogue (D) leaves the disruptive pattern in place and may further silence team members.

Question 2

New Single answer

Topic: People

Skill tested: Coaching a self-managing team to address uneven participation and shared accountability.

A product team has missed two sprint goals. Retrospectives show that a few vocal members select work while quieter specialists receive tasks without discussion. The team's working agreement says members share responsibility for sprint outcomes, but it does not describe how work is selected or concerns raised. The product owner is available to clarify priorities, and the organization expects the team to manage its own work. What is the project manager's BEST next action?

Correct Answer: C. Facilitate a team discussion to identify barriers, agree on inclusive work-selection practices, and update the working agreement.
Explanation:

The team's difficulty is partly a participation and accountability problem, so the project manager should help the team improve its own collaboration rather than impose task assignments. A facilitated discussion can surface barriers, establish a fair process for selecting work and raising concerns, and make the ground rules explicit. Individual daily monitoring (A) encourages a command-and-control model; having the product owner assign tasks (B) confuses product prioritization with team organization. Management approval (D) adds a control without addressing the behavior causing the missed goals.

Question 3

New Multiple answers

Topic: People

Skill tested: Facilitating a constructive resolution between team members with competing delivery priorities.

A compliance analyst wants each requirement fully documented before development begins. A developer favors short iterations to uncover integration risks early. Both are essential to a regulated release, and the disagreement has become personal during team meetings. The organization requires auditable evidence, but it permits iterative delivery when controls are demonstrated. The project manager should help the team reach a workable agreement rather than decide the technical process alone. Which TWO actions are MOST appropriate? Select TWO.

Correct Answer: A. Bring the participants together to describe their concerns and shared outcome, then facilitate a discussion of options against compliance and delivery needs.; C. Have the team agree on respectful discussion and a decision process, then document the revised ground rules.
Explanation:

A joint, facilitated conversation focuses the disagreement on the shared objective and the actual constraints, allowing the team to explore an approach that preserves auditable evidence while managing integration risk. Updating ground rules makes expectations for respectful discussion and decision-making explicit for future conflicts. A sponsor-imposed winner (B) bypasses collaboration, and removing a key contributor (D) is disproportionate. A private agreement (E) might settle a local choice but does not address the team meeting behavior or establish a sustainable team process.

Question 4

New Single answer

Topic: People

Skill tested: Selecting a conflict-resolution approach that preserves trust and team ownership.

A geographically distributed project team is preparing a release when a senior architect publicly dismisses a tester's defect findings as "noise." The tester has since stopped reporting concerns in group meetings. The defect could affect customer data, and the project manager has no evidence that the architect acted deliberately. A release review is scheduled tomorrow, so the concern cannot be deferred. What should the project manager do?

Correct Answer: C. Facilitate a timely conversation that restores respectful communication, ensures the defect is assessed on evidence, and agrees how concerns will be raised.
Explanation:

The project manager needs to address both the immediate risk and the behavior suppressing important information. A facilitated conversation can re-establish respectful dialogue, ensure the defect receives an objective assessment, and agree on a practical way to raise concerns. Automatically privileging one person's conclusion (A) is not evidence-based. Private conversations alone (B) do not ensure the defect is evaluated or restore team communication, and waiting for the sponsor (D) delays action on a potentially serious data issue.

Question 5

New Single answer

Topic: People

Skill tested: Using coaching and team agreements to improve collaboration across functional boundaries.

A project depends on a security engineer who reports to a functional manager and a development team that reports through a different organization. The engineer is repeatedly invited late to design discussions and then rejects designs that require rework. The development lead believes the engineer is obstructing progress. The project manager cannot change reporting lines, and the next design decision is due this week. What is the BEST action?

Correct Answer: B. Facilitate a working session to clarify shared outcomes, involve security early, and agree on collaboration and decision-making ground rules.
Explanation:

The recurring rework is caused in part by late collaboration across organizational boundaries. Bringing the relevant people together can establish a shared understanding of the outcome, include security expertise when it can influence design, and clarify decision-making expectations. Manager-to-manager intervention (A) may be needed if the issue cannot be resolved, but it is not the best first step. Late review (C) repeats the root cause, and immediate escalation (D) bypasses a constructive team-level resolution.

Question 6

New Single answer

Topic: Process

Skill tested: Choosing a hybrid development approach based on uncertainty, regulation, and feedback needs.

A financial services organization is building a customer-facing feature that must satisfy stable audit and data-retention controls. The user workflow is poorly understood, however, and early prototypes are expected to reveal changes to the interaction design. A fixed launch date is important, but the compliance team needs traceable evidence and an opportunity to review controls. The sponsor is willing to fund short learning cycles but will not accept uncontrolled changes to the release baseline. Which development approach is MOST appropriate?

Correct Answer: C. Use a hybrid approach, plan and control compliance needs predictively while iteratively developing and validating the user workflow.
Explanation:

The scenario contains both relatively stable, auditable requirements and substantial uncertainty about user interaction. A hybrid approach can plan and trace compliance controls while using iterative prototypes and feedback to refine the workflow. A fully predictive approach (A) makes learning expensive, whereas unrestricted adaptation (B) conflicts with controlled changes and traceability. Deferring compliance planning (D) risks late rework and does not satisfy the organization's evidence needs.

Question 7

New Multiple answers

Topic: Process

Skill tested: Tailoring an adaptive delivery approach to dependencies, uncertainty, and stakeholder feedback.

A public agency is replacing a permit application process. Policy rules are approved and must be traceable, but applicants have difficulty describing what would make the online experience usable. The program must integrate with a legacy identity service during each release, and a limited pilot is possible before agency-wide rollout. Procurement requires a documented baseline for the policy rules; it does not require a fixed design for every screen. Which TWO planning decisions are MOST appropriate? Select TWO.

Correct Answer: A. Baseline the approved policy requirements and their traceability while allowing interface details to evolve through feedback.; C. Plan short delivery and feedback cycles that include integration validation with the legacy identity service.
Explanation:

The approved policy rules need a controlled, traceable baseline, while the uncertain interface benefits from progressive elaboration and user feedback. Short cycles should include identity integration because that dependency can reveal important risks before deployment. Freezing the entire interface (B) undermines learning; postponing integration (D) creates late discovery risk; and making policy rules negotiable without traceability (E) violates the procurement and governance constraint.

Question 8

New Single answer

Topic: Process

Skill tested: Updating an integrated project management plan after an approved scope and schedule change.

A project's steering committee has approved adding a data-migration rehearsal to protect a critical launch. The change affects the schedule, resource assignments, test strategy, risk responses, and stakeholder communications. The project manager has updated the schedule file, but team members are still using the earlier test plan and the vendor has not received revised dates. No further approval is needed for this change. What should the project manager do NEXT?

Correct Answer: B. Update the integrated project management plan and affected subsidiary plans and baselines as applicable, then communicate and distribute the approved revisions.
Explanation:

An approved change that affects several planning components requires coordinated updates so the project remains internally consistent. The project manager should revise the integrated plan and relevant subsidiary plans or baselines according to the project's change-control rules, then communicate the current versions to the team and vendor. Updating only the schedule (A) leaves conflicting guidance. Requiring redundant approvals (C) is unnecessary because the change is already approved, and recording it only as a lesson (D) does not direct current work.

Question 9

New Multiple answers

Topic: Process

Skill tested: Integrating risk responses and dependencies into iterative release planning.

A medical-device software team plans three releases. The first release can validate a new user workflow, but a third-party data interface has not been tested and the supplier's test environment is available for only two weeks next quarter. A safety review must occur before any release is used in a clinical setting. The product owner wants early feedback, while the project manager must maintain a credible delivery plan. Which TWO actions should the project manager take? Select TWO.

Correct Answer: A. Schedule an early integration experiment during the supplier environment window and incorporate its findings into release planning.; C. Plan the safety review as a required release dependency and make its entry criteria and timing visible in the integrated plan.
Explanation:

The short supplier test window creates a time-sensitive risk, so an early integration experiment provides evidence while the environment is available. The safety review is a mandatory dependency for clinical use and must be visible in the release plan, including relevant criteria and timing. Committing to the date based only on workflow feedback (B) conflates usability evidence with interface readiness. Waiting for a confirmed defect (D) is reactive, and withholding all prototype feedback (E) is unnecessary if nonclinical learning can proceed safely.

Question 10

New Single answer

Topic: Process

Skill tested: Selecting an adaptive approach when requirements uncertainty makes fixed-scope planning unsuitable.

A retailer is developing a recommendation feature using customer behavior data. The data is available, but neither the business sponsor nor the analysts know which signals will produce useful recommendations until experiments are run. A quarterly funding review requires measurable progress, and privacy controls must be reviewed before customer data is used. The sponsor initially requests a fixed feature list and a detailed schedule, but agrees that outcomes may change as evidence emerges. Which approach BEST fits the work?

Correct Answer: B. Use an adaptive, experiment-driven approach with short feedback cycles, defined outcome measures, and privacy review before data use.
Explanation:

The feature's value and requirements are uncertain until experiments generate evidence, making an adaptive approach more suitable than freezing a detailed solution. Short cycles and measurable outcomes provide evidence for quarterly funding decisions, while privacy review remains a necessary control before customer data is used. A fixed feature list (A) is unlikely to survive learning. Uncontrolled experimentation (C) ignores governance and progress visibility, while treating negative findings as defects (D) misunderstands experimentation.

Question 11

New Single answer

Topic: Process

Skill tested: Replanning an integrated project plan when a critical dependency threatens a milestone.

A construction project's electrical inspection is delayed because the municipal inspector is unavailable. The inspection is a required predecessor to energizing the facility, and the contract prohibits energizing before approval. The project manager has identified alternative sequencing for interior work, but that sequence may affect labor costs and the commissioning date. The sponsor has not authorized additional budget or a date change. What should the project manager do NEXT?

Correct Answer: B. Update the schedule to reflect the inspection delay, assess impacts and feasible sequencing options, and present an integrated change recommendation through governance.
Explanation:

The inspection is a mandatory predecessor, so the project manager must not bypass it. The appropriate next step is to assess the schedule, cost, resource, and commissioning effects of the delay and alternative sequencing, then bring a coherent recommendation to the applicable decision authority. Energizing before approval (A) violates the stated contract constraint. Unanalyzed overtime (C) assumes both feasibility and authorization, while removing the dependency (D) hides rather than manages the impact.

Question 12

New Single answer

Topic: Process

Skill tested: Choosing a development approach that combines predictable delivery controls with iterative discovery.

An enterprise is implementing a new employee onboarding service. Legal forms and retention periods are specified and must be approved before use. The service's navigation and notification preferences are uncertain, and employees can participate in frequent usability sessions. A release must connect to an existing payroll platform, whose interface changes are controlled by another department. The organization needs predictable checkpoints but permits incremental delivery. Which approach is MOST appropriate?

Correct Answer: C. Use a hybrid approach: control legal content and external integration checkpoints while iterating on navigation and notifications.
Explanation:

The solution has stable legal content and an externally controlled integration, both of which benefit from defined approvals and checkpoints, alongside uncertain user-facing elements that can improve through frequent testing. A hybrid approach tailors the lifecycle to those different levels of uncertainty. Deferring usability work (A) delays learning, and removing checkpoints (B) ignores the payroll dependency. Reversing the approach for legal content and navigation (D) applies flexibility to the more controlled area and rigidity to the less certain one.

Question 13

New Single answer

Topic: Process

Skill tested: Coordinating change control and plan updates after an external interface change.

A supplier announces that its application programming interface will change before the project's next planned release. The change may affect integration design, security testing, schedule, and the agreed service level. The team has identified a workaround, but its operational cost is not yet known. The project's change-control process requires an impact assessment before baseline changes, and the release date is contractually important. What is the project manager's BEST next step?

Correct Answer: B. Assess the change and workaround across scope, schedule, cost, quality, security, and operations; then submit the recommendation through change control.
Explanation:

The external interface change has cross-project impacts, and the stated process explicitly requires an impact assessment before baseline updates. The project manager should evaluate the workaround and alternatives across relevant plan components, including operational cost and security, and then use change control to obtain the appropriate decision. Immediate implementation (A) bypasses required assessment. Continuing against a superseded interface (C) does not resolve the dependency, while unapproved reductions in service or security (D) trade away requirements without governance.

Question 14

New Single answer

Topic: Business Environment

Skill tested: Defining governance roles and escalation routes for a mandatory compliance requirement.

A project to launch an online lending service discovers that a new regulatory interpretation may require an additional customer disclosure before applications are submitted. Legal has not yet determined whether the interpretation applies, and the launch date is approaching. The project manager can coordinate analysis but cannot accept regulatory risk or authorize a change to the organization's compliance policy. Several executives have been copied on email, but no one is identified as the decision owner. What should the project manager do FIRST?

Correct Answer: B. Define and use a governance path that assigns legal/compliance decision authority, required evidence, and escalation timing for the applicability decision.
Explanation:

The unresolved issue concerns regulatory applicability, and the project manager lacks authority to accept that risk. Governance should identify the accountable legal or compliance decision-maker, the evidence needed, and a timely escalation path so the project can make a defensible decision. Adding an unconfirmed requirement immediately (A) may create avoidable scope and still does not establish interpretation authority. Launching without resolution (C) exposes the organization to compliance risk, while relying on the sponsor alone (D) omits the relevant expertise and accountability.