Question 1
Topic: Plan the Solution
Skill tested: Translate campus discovery findings into a complete low-level implementation checklist.
A regional office is replacing its access layer and adding wireless coverage. The existing network has two user VLANs, a voice VLAN, centrally managed access switches, and APs connected to switch ports. During discovery, the deployment technician finds that the network diagram does not identify the DHCP scope for the new wireless client subnet, the uplink trunk's allowed VLANs, or the switch management addressing method. The cutover window is fixed, and the team cannot make design decisions onsite. Which action best prepares the low-level design for implementation?
A usable low-level design resolves dependencies that otherwise force unplanned decisions during a constrained cutover. It should identify the VLAN and subnet plan, DHCP responsibility, trunk VLAN membership, management addressing, and AP port requirements, with unresolved items confirmed by the network owner. Reusing a subnet or permitting every VLAN assumes design authority and can create security or addressing problems. Capturing only topology leaves required configuration unknown, while postponing wired dependencies overlooks the fact that AP management and client traffic depend on correct switchport and network services.