Question 1
Topic: Pega Express
Skill tested: Maps Pega Express phases to DCO activities and project deliverables.
A regional insurer is starting a Pega implementation with a fixed launch date. The team has identified the business outcome but has not yet validated the detailed workflow or agreed on the first release scope. The sponsor wants business and delivery participants to collaborate continuously rather than defer requirements decisions until development is complete. The project lead proposes completing all requirements documentation before building anything. Which approach best applies Pega Express and DCO while keeping the work iterative?
Pega Express organizes delivery into Discover, Prepare, Build, and Adopt. Discover aligns the team around business outcomes and the solution opportunity; Prepare establishes the team, delivery plan, and prioritized work. In Build, DCO supports frequent collaboration, configuration, and validation rather than a handoff from a large requirements phase. Adopt focuses on preparing the organization to use and sustain the solution. The other sequences assign activities to phases where they do not belong or suppress the iterative stakeholder collaboration the sponsor requires.